Sun Oil Company v. Federal Power Commission Sunrayoil Co v. Federal Power Commission, MID-CONTINENT

Decision Date27 June 1960
Docket NumberNos. 321,MID-CONTINENT,335,s. 321
PartiesSUN OIL COMPANY, Petitioner, v. FEDERAL POWER COMMISSION. SUNRAYOIL CO., Petitioner, v. FEDERAL POWER COMMISSION
CourtU.S. Supreme Court

Mr. Howard E. Wahrenbrock, Washington, D.C., for respondent.

Mr. Justice BRENNAN delivered the opinion of the Court.

This case presents many of the same issues as Sunray Mid-Continent Oil Co. v. Federal Power Comm., 364 U.S. 137, 80 S.Ct. 1392.

Petitioner, Sun Oil Company, is an independent producer making sales of natural gas to transmission companies in interstate commerce for ultimate resale to the public. In 1947 it entered into a contract with the Southern Natural Gas Company, a transmission company, for the sale of natural gas which petitioner controlled in the Gwinville Gas Field in Jefferson Davis and Simpson Counties, Mississippi. The term of the contract was 10 years and the sales price was roughly eight cents per Mcf.

After this Court's decisions in Phillips Petroleum Co. v. State of Wisconsin, 347 U.S. 672, 74 S.Ct. 794, 98 L.Ed. 1035, on June 7, 1954, the Commission, in a series of orders, required independent producers engaging in jurisdictional sales on or after the date of the decision to apply for certificates of public convenience and necessity pursuant to § 7(c) of the Natural Gas Act, 15 U.S.C.A. § 717f(c).1 Under protest, petitioner applied for a certificate 'authorizing the sale of natural gas in the circumstances * * * described' in its application. The described circumstances consisted simply of a reference to its contract with Southern Natural, which was at the same time submitted by petitioner as its rate schedule. In an abbreviated and consolidated proceeding disposing of over 100 separate docket certificate applications from 40-odd independent producers, scattered from Colorado and New Mexico to West Virginia, the Commission on May 28, 1956, ordered issued to petitioner and each of the other applicants a certificate of public convenience and necessity, in the terms set out in the margin.2 Petitioner's contract-rate-schedule was accepted as its FPC Gas Rate Schedule No. 55.

The 1947 contract between petitioner and Southern Natural expired on August 26, 1957. The parties however entered into a new 20-year contract for continued sale of gas from the same field, commencing on September 3, 1957. The contract called for an initial price increase of roughly 150 per cent, to 20 cents per Mcf.3 Petitioner took the view that the certificate it had received in 1956 was limited in term to the duration of the old contract. It accordingly filed on application for a new certificate covering the new contract, and filed the new contract as an initial rate schedule under the new certificate, pursuant to § 5 of the Act, 15 U.S.C.A. § 717d.4 The Commission, in a letter order of September 12, 1957, rejected the certificate application as duplicative of petitioner's existing certificate to make sales from the field in question, and rejected the rate-schedule filing on the ground that the purported initial rate schedule was actually a change in its existing Schedule No. 55. A motion for reconsideration was later denied; and at the same time the Commission ordered suspended, under § 4(e) of the Act,5 the effectiveness of the rates in the new contract, which petitioner had, after their rejection as an initial rate schedule, filed under protest, as rate changes pursuant to § 4(d). 18 F.P.C. 609, 611. After an application for rehearing of the suspension order was rejected, petitioner petitioned for review of all these orders of the Commission in the Court of Appeals for the Fifth Circuit.6 That court affirmed, by a divided vote. 5 Cir., 266 F.2d 222. We granted certiorari. 361 U.S. 880, 80 S.Ct. 151, 4 L.Ed.2d 117.

Petitioner's contention here, as it was below, is that the initial certificate it obtained in 1956 was to remain in effect only during the life of the 1947 contract. This in its view would leave it free to discontinue interstate sales after the 1957 expiration of the contract, or to apply for a new certificate for new sales, and, not unimportantly, file the new sales contract as an initial rate schedule thereunder rather than as a rate change, We reject this contention and affirm the judgment of the Court of Appeals.

First. The major part of petitioner's argument is based on a want of authority in the Commission, over objection, to grant an independent producer a certificate for a longer duration than the term of a sales contract which its application seeks permission to fulfill. To be sure, if the Commission had no such authority, we might take pains to read the petitioner's application as seeking a certificate so limited in time, though, as compared with Sunray's in the companion case, it is highly inexplicit as to its desire that only a term certificate be issued. But we have held today in the Sunray case, 364 U.S. at page 137, 80 S.Ct. at page 1392, that in these circumstances the Commission has authority to tender a permanent certificate under an application for a term certificate; and accordingly this keystone of petitioner's argument falls.

Second. Of course, if, despite its authority to grant a permanent certificate, the Commission had in 1956 actually granted a term certificate to petitioner, petitioner would after the term have been free to apply for a new certificate to authorize the sale under the new contract. But we agree with the Commission that the 1956 certificate was a permanent one. The application itself, under the construction we have given the statute in Sunray, did not with any explicitness ask for a limited certificate. It asked for one 'authorizing the sale of natural gas' under the 1947 contract; but as we said in Sunray, a permanent certificate would do that. See 364 U.S. at page 149, 80 S.Ct. at page 1399. And the certificate issued makes no reference to any limitation of time. This is in contrast with explicit references to the limitation in those instances where the Commission had previously issued term certificates.7 The Commission's order, which blanketed the many applications before it in the mass proceeding, is no more explicit about limitation than the application, and refers, in fact, to the certificate as both 'authorizing the sale' of natural gas, and authorizing a 'service,' which accords with our construction of § 7(e) in Sunray. Under these circumstances we would hardly see any basis for overturning the Commission's view that no limitation as to time was implied. Cf. Andrew G. Nelson, Inc. v. United States, 355 U.S. 554, 560, 78 S.Ct. 496, 499, 2 L.Ed.2d 484.

Moreover, if there were any doubt as to the matter, it would be removed by the fact that the batch of certificates containing petitioner's was issued at a time when the Commission was asserting that it lacked even the power to...

To continue reading

Request your trial
23 cases
  • Gulf Oil Corp. v. F. P. C.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • 7 Septiembre 1977
    ...on Sunray Mid-Continent Oil Co. v. F. P. C., 364 U.S. 137, 80 S.Ct. 1392, 4 L.Ed.2d 1623 (1970), and Sun Oil Co. v. F. P. C., 364 U.S. 170, 80 S.Ct. 1388, 4 L.Ed. 1639 (1960), is, in my view, irrelevant because these cases deal with the interpretation, not the procedure for initial interpre......
  • California v. Southland Royalty Company El Paso Natural Gas Company v. Southland Royalty Company Federal Energy Regulatory Commission v. Southland Royalty Company
    • United States
    • U.S. Supreme Court
    • 7 Diciembre 1977
    ...of unlimited duration, and this certificate was among those construed as "permanent" by this Court in Sun Oil Co. v. FPC, 364 U.S. 170, 175, 80 S.Ct. 1388, 1391, 4 L.Ed.2d 1639 (1960).2 Gulf entered into a second contract to sell additional volumes of gas to El Paso in 1972, and obtained a ......
  • JM Huber Corporation v. Denman
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 20 Septiembre 1966
    ...of January 20, 1939 and November 2, 1939. 11 American Oil Co. v. Hart, 5 Cir., 1966, 356 F.2d 657. 12 Sun Oil Co. v. FPC, 1960, 364 U.S. 170, 80 S.Ct. 1388, 4 L.Ed.2d 1639; United Gas Pipe Line Co. v. FPC, 5 Cir., 1965, 350 F.2d 689, cert. granted, 1966, 383 U.S. 924, 86 S.Ct. 930, 15 L.Ed.......
  • Weymouth v. Colorado Interstate Gas Company
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 20 Septiembre 1966
    ...v. Wisconsin, 1954, 347 U.S. 672, 74 S.Ct. 794, 98 L.Ed. 1035. 13 FRIC: for resale in interstate commerce. 14 Sun Oil Co. v. FPC, 1960, 364 U.S. 170, 80 S.Ct. 1388, 4 L.Ed.2d 1639, affirming, 5 Cir., 1959, 266 F.2d 15 The FPC has, in effect, so held, as have we in upholding their order in U......
  • Request a trial to view additional results
1 books & journal articles
  • CHAPTER 13 THE QUANDARY OF A REGULATED PIPELINE IN A DEREGULATED GAS MARKETING ENVIRONMENT
    • United States
    • FNREL - Special Institute Natural Gas Marketing II (FNREL)
    • Invalid date
    ...(1979); California v. Southland Royalty Co., 436 U.S. 519 (1978); United Gas Pipe Line Co. v. FPC, 385 U.S. 83 (1966); Sun Oil Co. v. FPC, 364 U.S. 170 (1960); Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137 (1960). [11] Short term commodity markets are cyclical. A recent empirical study ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT