Teledyne Industries, Inc. v. Eon Corporation
| Decision Date | 20 March 1974 |
| Docket Number | No. 72 Civ. 3261.,72 Civ. 3261. |
| Citation | Teledyne Industries, Inc. v. Eon Corporation, 373 F.Supp. 191 (S.D. N.Y. 1974) |
| Parties | TELEDYNE INDUSTRIES, INC., Plaintiff, v. EON CORPORATION et al., Defendants. |
| Court | U.S. District Court — Southern District of New York |
Breed, Abbott & Morgan, New York City (Stephen R. Lang, Charles M. Mitchell, New York City, of counsel), for plaintiff.
Feldshuh & Frank, New York City (Sidney Feldshuh, Richard Weinberger, New York City, of counsel), for defendants Srybnik, Podell, Anton and Waller.
This is a diversity action brought by Teledyne Industries, Inc., a California corporation with its principal place of business in Los Angeles against Eon Corporation, a New York corporation with its principal place of business in Brooklyn, and four of its officers and/or directors, Podell, Srybnik, Anton and Waller.1 Before the court are two motions, one by the plaintiff and one by the four individual defendants.2 Plaintiff moves pursuant to Rule 37(a)(2) of the Federal Rules of Civil Procedure for an order compelling production of certain documents previously requested under Rule 34. Defendants move, pursuant to Rule 56, for partial summary judgment dismissing plaintiff's action as against them. I shall first consider defendants' motion, for it requires an exposition of the underlying facts necessary for an understanding of the discovery motion as well.
As an introduction to the discussion of the summary judgment motion, it will be useful to set forth those facts which are undisputed. What follows, then, is drawn from defendants' 9(g) statement, the pleadings, and the transcripts of the various depositions submitted by the parties.
The Eon Corporation, founded in 1961, is engaged in the development and manufacture of "medical, nuclear, electronic and optical devices."3 In December, 1968 it acquired what became its American Marc Division, which was located in Inglewood, California and was engaged in the manufacture of diesel engines and electric generators. Of the individual defendants, Anton is president of Eon, Podell chairman of the board, Waller secretary, and Srybnik, both individually and through corporations he controls, the largest single shareholder. All are directors of Eon, and were at the time of the events in question.
On or about June 20, 1969, Eon, through American Marc, was awarded a contract by the United States Army, No. DAAKO1-69-C-A359, for the manufacture, production and delivery of 1.5 KW generator sets. At some point in 1970, the Eon board decided to find a subcontractor to fulfill its remaining commitments thereunder. This decision had been reached pursuant to its earlier determination to terminate the operations of the unprofitable American Marc Division. Eon's interest in locating such a subcontractor had been communicated to one Eugene Wolper by M. J. Leonard, an Eon director and head of the American Marc Division. Wolper in turn contacted Harold Rouse, a Teledyne vice president, during the week of May 3, 1971. When Rouse expressed interest, a meeting was arranged in Los Angeles between Teledyne and Eon representatives for May 10, 1971.
The negotiations were completed in the brief span of three days, and culminated in the signing of contracts on May 12, 1971. Present during all or part of the negotiations were Leonard, Wolper, Rouse, and Homer Coleman, another Teledyne executive. Anton arived in Los Angeles on May 12, and participated in the final discussions and execution of the agreement.
Two documents were executed on that day. One was Purchase Order No. M-1257, wherein Teledyne agreed to manufacture 4,372 generator sets at a unit price of $360,4 or a total cost of $1,573,920, and to deliver them as specified in the original Army contract. The other was an inventory agreement which provided, in essence, that Teledyne would purchase from Eon all of the generator set parts and material which Eon possessed in good condition on August 31, 1971, at a price equal to 75% of the inventory value of such equipment as well as the tooling, gauges, and other equipment necessary to perform the contract.
In addition, the parties also made certain arrangements for payment from Eon to Teledyne. A letter from Rouse to Leonard dated May 13, endorsed with Leonard's acceptance on May 25, set out the essential terms:
The arrangements were spelled out in a letter dated May 25, 1971, from Leonard to the Palos Verdes branch of the Bank of America.5 The letter, which is set out in full in the margin,6 provided for the deposit of all funds received by Eon from the sale of the generator sets to the government "in our special account which we have opened at the Bank of America for this purpose." Payments to Teledyne were to be made by cashier's check after Eon received the Teledyne invoices for generator sets produced and shipped, and after the government had paid Eon. The letter also provided that "the balance in the account will be dispursed (sic) according to the direction of American Marc Division of Eon Corporation." The meaning of this phrase, as will be noted below, is very much in doubt.
Teledyne commenced production and delivery of the generator sets later in 1971, and for a time the arrangement worked as planned. However, in April or May of 1972, Eon informed Teledyne that it would no longer make payments under the subcontract. According to Anton, Eon's president, Eon was compelled to use the money received from the government for other corporate purposes. Had Eon paid Teledyne instead, he asserted, "the company would have stopped existing."7 This lawsuit was commenced by Teledyne on July 27, 1972.
In its complaint, Teledyne sets forth two causes of action. In the first, it alleges that the defendants embarked upon a scheme to defraud Teledyne by inducing it to enter into a contract which they knew Eon lacked the means to perform. In pursuance of this scheme, it is charged that two fraudulent representations were made to Teledyne: (a) that the amount remaining to be paid Eon by the Army under the contract exceeded the subcontract price, and (b) that Eon had clear and unencumbered title to the inventory, tooling, and other equipment which Teledyne had agreed to purchase. The second cause of action alleges, in essence, a breach of fiduciary duty owed by Eon to Teledyne. It is claimed that Eon undertook to establish a special account for the payment of Teledyne's invoices, and further undertook not to withdraw any funds from this account until Teledyne had been paid in full. The funds received by Eon from the Army were "held in trust" in this account, it is alleged, and the subsequent diversion of such funds to other purposes constituted a breach of trust and an act of conversion.
In support of its motion for summary judgment with regard to the first cause of action, defendants argue that the facts as developed in the numerous depositions taken demonstrate beyond cavil that they made no fraudulent representations to Teledyne, and did nothing to induce it to enter into the subcontract. Plaintiff, of course, argues that there is a more than adequate basis in the record thus far developed for concluding that the defendants participated in the allegedly fraudulent scheme.
At this juncture, then, it will be useful to review the familiar standards that govern motions for summary judgment. I must at the outset acknowledge the pertinence of Professor Moore's observation that "summary judgment is apt to be inappropriate in an action based on a complex scheme of fraud where the court is asked to decide the motion on lengthy affidavits and documents and voluminous depositions."8 Moore adds the obvious caveat that the party opposing summary judgment cannot rely merely on complexity; he must proffer evidence that raises triable issues of fact.
The prevailing rule, then, is that allegations of fraud do not readily lend themselves to resolution by way of summary judgment. Clyde v. Hodge, 413 F.2d 48 (3rd Cir. 1969). Fraudulent intent is an issue best determined by a careful examination of the underlying facts and an evaluation of the credibility of the parties and witnesses. Categorical denials of such intent contained in affidavits (or, as here, in depositions) scarcely provide an adequate basis for such a determination. Associated Hardware Supply Co. v. Big Wheel Distributing Co., 355 F.2d 114 (3rd Cir. 1966); F. S. Bowen Electric Co. v. J. D. Hedin Construction Co., 114 U.S.App.D.C. 361, 316 F.2d 362 (1963); Paine-Henderson v. Eastern Greyhound Lines, 320 F. Supp. 1138 (D.S.C.1970). See also Poller v. Columbia Broadcasting System, Inc., 368 U.S. 464, at 473, 82 S.Ct. 486, 7 L.Ed.2d 458 (1962); Cross v. United States, 336 F.2d 431 (2nd Cir. 1964). In order to establish that no genuine issue of material fact exists, defendants must sustain a heavy burden. Weiss v. Kay Jewelry Stores, Inc., 152 U.S.App. D.C. 350, 470 F.2d 1259 (1972).
The standard against which the liability of the individual defendants is to be measured is also a familiar one. It is now well settled that an officer or director is not, merely by virtue of his office, liable for the tortious acts of the corporation. He must direct, authorize, or in some meaningful sense participate actively in the assertedly wrongful conduct. Armour and Company v. Celic, 294 F.2d 432 (2nd Cir. 1961); Hagemeyer Chemical Co. v. Insect-O-Lite Co., 291 F.2d 696 (6th Cir. 1961); Lobato v. Pay Less Drug Stores, 261 F.2d 406 (10th Cir. 1958); Lahr v. Adell Chemical Co., 300 F.2d 256 (1st Cir. 1962); Lemmons v. Zurich Insurance Co., 403 F.2d 512 (5th Cir. 1968); United States Liability Insurance Co. v. Haidinger-Hayes, Inc., 1 Cal.3d 586, 83 Cal.Rptr. 418, 463 P.2d 770 (1970). The question presented for...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Tew v. Chase Manhattan Bank, NA
...(citing New York law that banker-customer relationship is of a debtor-creditor, not fiduciary nature); Teledyne Industries, Inc. v. Eon Corp., 373 F.Supp. 191, 201 (S.D.N.Y. 1974) There are also no issues of fact from which a reasonable jury could find the existence of a fiduciary duty. Con......
-
In re Euro-Swiss Intern. Corp.
..."allegations of fraud do not lend themselves to resolution by way of summary judgment." Id. at 947, quoting Teledyne Industries v. Eon Corp., 373 F.Supp. 191, 195 (D.C.S.D.N.Y.1974); see United States v. Diebold, Inc., 369 U.S. 654, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962); Friedman v. Meyers, su......
-
Am. Elec. Power Co., Inc. v. Westinghouse Elec. Corp.
...for summary judgment is directed toward plaintiffs' allegations of fraud, the motion must be denied. See Teledyne Industries, Inc. v. Eon Corp., 373 F.Supp. 191, 198 (S.D.N.Y. 1974). (c) Express Warranties and With respect to remedies for breach of express warranties, or for negligence, it ......
-
Petedge, Inc. v. Garg
...Shostack v. Diller , No. 15-cv-2255 (GBD) (JLC), 2015 WL 5535808, at *5 (S.D.N.Y. Sept. 16, 2015) (quoting Teledyne Indus., Inc. v. Eon Corp. , 373 F.Supp. 191, 196 (S.D.N.Y. 1974) ). PetEdge's conclusory allegations regarding Garg's direct involvement in the alleged scheme fail to meet the......