Templeton v. Sam Klain & Son, Inc.

Decision Date31 August 1981
Docket NumberNo. 881S222,881S222
Citation425 N.E.2d 89
PartiesG. C. TEMPLETON, Jr., Defendant-Appellant, v. SAM KLAIN & SON, INC., Plaintiff-Appellee.
CourtIndiana Supreme Court

Charles G. Reeder, Johnson & Weaver, Indianapolis, for defendant-appellant.

Marvin Mitchell, Eskenazi, Mitchell, Yosha & Hurst, Indianapolis, for plaintiff-appellee.

PRENTICE, Justice.

Plaintiff, Appellee, Sam Klain & Son, Inc., formerly the Sam Klain & Son Partnership (Klain) recovered a judgment against the defendant, Appellant (Templeton) in the sum of $9,071.90 principal and interest, plus attorneys' fees in the sum of $3,200.00, for a total of $12,271.90, together with an order of foreclosure and sale, pursuant to its suit upon a mechanic's lien held under Ind.Code § 32-8-3-1 (Burns 1973). Thereafter, Templeton initiated appellate proceedings and Klain petitioned for and was awarded an additional sum for attorney's fees in the sum of $2500.00, secured by the lien and payable in the same manner as the judgment, in defense of the judgment on appeal.

Templeton's appeal was perfected and resulted in an affirmance of the trial court's judgment, except with respect to the award of the additional attorneys fees, and in this regard, it was reversed. The decision and opinion of the Court of Appeals, First District, may be found at 400 N.E.2d 1198.

The matter is now before us upon the petitions to transfer filed by both parties, and transfer is now granted pursuant to Ind.R.App.P. 11(B)(2)(b) in that the Court of Appeals has erroneously decided a new question of law, i. e. the entitlement to attorneys fees under Ind.Code § 32-8-3-14 (Burns 1973) incidental to the defense on appeal of the initial judgment; and the aforesaid decision and opinion of the Court of Appeals is now ordered vacated.

The appeal presents four (4) issues:

(1) Did the trial court err in finding that the materials furnished had not been paid for?

(2) Did the trial court err in holding, under the facts of this case, that evidence of delivery of the materials to the job site established a presumption that they were incorporated into the improvements for which they were furnished?

(3) Did the trial court err in holding that Templeton was personally liable for the amount secured by the lien?

(4) Did the trial court err in awarding Klain attorney's fees incidental to the defense, on appeal, of the initial judgment?

The facts necessary for understanding the issues are as related in the opinion of the Court of Appeals, authored by Judge Robertson; and we adopt the opinion of that Court upon Issues One (1), Two (2) and Three (3), as follows:

" * * * G. C. Templeton, Jr. (Templeton), the appellant-defendant, owned real estate in Indianapolis which he wished to develop, with himself as general contractor, into condominium units known throughout litigation as the 'Overlook' project. In 1974, Templeton and the Dallas Company (Dallas) entered into an agreement whereby Dallas would perform the plumbing and heating work on the project. Dallas began work on the project in August of 1974 and continued until February 21, 1975, when Dallas was forced out of business by a secured creditor. Dallas had gotten supplies and materials for the project from the appellee-plaintiff, Sam Klain & Son, Inc., formerly the Sam Klain & Son partnership (Klain), with whom Dallas had been doing business for some time.

"The trial court found that Klain had not been paid by Dallas for materials incorporated into the Overlook project in the amount of $7,674.86. The trial court further found that Templeton was indebted to Dallas in a sum in excess of $7,674.86. The trial court also found that Klain had fulfilled all the statutory notice and filing requirements necessary to obtain a mechanic's lien. Judgment for the above sum, interest and attorney's fees was awarded to Klain against Templeton and an order to foreclose a mechanic's lien also given. This appeal began and the trial court further ordered attorney's fees to be given for defending the judgment on appeal.

"The first issue presented for review is whether the trial court erred in finding that the materials which are the subject of the lien were not paid for by Dallas. The problem is one of application of the sums paid to Dallas by Templeton and those paid to Klain by Dallas. We first review the payment practice of the parties in this case. Dallas had done business with Klain for a number of years previous to the job out of which this case arises. Klain's method of billing was through the use of invoices, on which there was a number which signified the job for which Dallas was using the materials. Klain reviewed those invoices to check on how much credit was being given on any one job. The trial court specifically found that Klain extended credit based on the job on which Dallas was working. Klain kept, however, one open account for Dallas and did not keep job by job accounts. A monthly total was kept and the amounts owing were split in the length of period the account was due or overdue. As payments came in, Klain applied the sums, not on a job by job basis, but rather to the oldest invoices due. Dallas was aware of the Klain billing method. At the start of the Overlook job, Dallas had an unpaid balance of over $100,000.

"Templeton paid Dallas six times, once a month, starting September 10, 1974, a total sum of $85,976. The check with which Templeton paid Dallas contained a restrictive endorsement that stated in part, 'Payee certifies ... that he/it has paid for all labor and material for which this check is payment.' Templeton did keep a retainage for work done each month. Dallas placed the sums from these checks into a general account with other funds from other sources. During the period of September 10, 1974 through January 13, 1975 Dallas made six payments to Klain on Dallas' account in the total sum of $102,438.79 and also received credit from Klain for returned goods in the amount of approximately $45,000.00. Again, these credits and payments were applied to the oldest outstanding invoices.

"When Dallas' secured creditor forced Dallas out of business on February 21, 1975, Klain had not been paid under this method for materials used on the Overlook project in the amount of $7,674.86.

"Templeton does not question the general rule in the application of a partial payment by a debtor to a creditor to whom more than one debt is due that the debtor has the right at or before payment to direct the application of the payment to whatever debt or debts he chooses, and if the debtor fails to do so the creditor may make the application as he sees fit. Western & Southern Indemnity Co. v. Cramer, (1937) 104 Ind.App. 219, 10 N.E.2d 440. It has also been stated that if neither the creditor nor the debtor allocates, the court will apply the payments as justice dictates, generally to the advantage of the creditor in the absence of supervening equities. See American Oil Co. v. Brown Paving Co., 298 F.Supp. 528 (S.D.S.C.1969) (and cases cited therein). It has also been said that, in regard to running accounts, the law will make the appropriation to the oldest account first. Born v. Union Elevator Co., (1918) 67 Ind.App. 97, 118 N.E. 973.

"Templeton attempts to invoke an exception to this rule recognized in a growing number of jurisdictions which limits the power of the creditor to apply the payment as he chooses (absent direction by the debtor) when the rights of third parties are affected. In our research we find two general grounds for this exception. One is based on a contractual obligation between the third party and the debtor that the debtor will apply specific funds received from the third party to the creditor in a certain manner. The other ground is based on general equitable considerations to protect, for example, innocent owners who pay in full from liens by materialmen.

"Templeton contends, because of the restrictive agreement quoted above, that Templeton directed that the materials be paid out of the proceeds of the payments received by Dallas from Templeton. Dallas, in signing the restrictive endorsement, did certify that he had paid for the materials that Templeton, in turn, was paying Dallas for. We note, however, that there was no agreement here that Dallas would apply the very funds received from Templeton to the materials that Dallas purchased for the project.

"Thus, whatever reliance Templeton places on Section 388 of the Restatement of Contracts (1932) is misplaced. 1 The section states:

"If the payor is under a duty to a third person to devote money paid by him to the discharge of a particular debt the payment must be so applied if the creditor knows, or has reason to know, of the payor's duty, in spite of the fact that the payor directs that the payment shall be applied to the discharge of another debt.

"The comment to this section states:

"... it is essential that the debtor shall be under a contract with the third person, not merely to pay a particular debt, but to devote to that debt the very money with which payment was made.

"As there was no obligation to use Templeton's payment to pay Klain, Templeton cannot rely on the contractual ground found in Section 388 and cannot rely on such case law as General Plywood Corp. v. S. R. Brunn Construction Co., (1971) Mo.App., 511 S.W.2d 905.

"We turn, then, to the second ground which is the general equitable principle recognized in many states that where a contractor owes a materialman more than one debt for materials used in several constructions and the materialman knows that funds paid to him by the contractor were received by the contractor on account of one of those debts, the materialman cannot apply such funds to another debt to the prejudice of the paying owner. Duffy v. Bourg, (1968) La.App., 209 So.2d 502; Ellingsen v. Western Farmers Ass'n., (1974) 12 Wash.App. 423, 529 P.2d 1163; Mutual Lumber Co. v. Gero, (1968) Me., 244 A.2d 564 (if materialman had knowledge of the...

To continue reading

Request your trial
26 cases
  • Campins v. Capels
    • United States
    • Indiana Appellate Court
    • March 28, 1984
    ...case law, we believe that this statutory provision for "reasonable" attorney fees encompasses appellate fees. See Templeton v. Sam Klain & Son, Inc., (1981) Ind., 425 N.E.2d 89 (in mechanics lien statute, "reasonable attorneys fees" includes appellate fees). Counsel for the Capelses filed a......
  • Coplay Cement Co., Inc. v. Willis & Paul Group
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • January 21, 1993
    ...against the subcontractors', since the owner is liable only up to the net amount that he owes the contractor. Templeton v. Sam Klain & Son, Inc., 425 N.E.2d 89, 94 (Ind.1981); Pioneer Lumber & Supply Co. v. First-Merchants National Bank, supra, 169 Ind.App. at 413, 349 N.E.2d at 223-24; Bla......
  • Parrish v. Terre Haute Sav. Bank
    • United States
    • Indiana Appellate Court
    • July 26, 1982
    ...v. WNC Development Co., (1975) 165 Ind.App. 141, 331 N.E.2d 452; 20 C.J.S. Costs Sec. 218 (1940). Recently, in Templeton v. Sam Klain & Son, Inc., (1981) Ind., 425 N.E.2d 89, a mechanic's lien case, our Supreme Court held that a statutory provision for "reasonable attorneys fees," Ind.Code ......
  • City of Hammond v. Marina Entertainment Complex, Inc.
    • United States
    • Indiana Appellate Court
    • June 13, 1997
    ...438 N.E.2d 1, 3 (Ind.Ct.App.1982). This includes legal services incurred defending a fee award. See id. (citing, Templeton v. Sam Klain & Son, Inc., 425 N.E.2d 89, 95 (Ind.1981)). Accordingly, this Court affirms the judgment and remands the case with instructions to the trial court to consi......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT