Texas & St. L. Ry. Co. v. Rust

Citation17 F. 275
PartiesTEXAS & ST. L. RY. CO. in Missouri and Arkansas v. RUST and another.
Decision Date01 January 1883
CourtU.S. District Court — Eastern District of Arkansas

On the twenty-second of April, 1882, a contract was entered into between the plaintiff railway company and Rust & Coolidge the defendants, for building a railroad bridge across the Arkansas river. The defendants were to complete the bridge by the first of November, 1882, and were to receive therefor the sum of $305,000, to be paid on 'pro rata monthly estimates, ninety per cent. thereof to be paid during progress of the work, upon material furnished and work performed, and balance due upon completion thereof.'

The contract contains this provision:

'In case of non-completion of the bridge upon November 1, 1882 or of providing a crossing for trains by said date, then in such event, the sum of $1,000 per week, for the period of time such completion or provision for crossing of trains is delayed, shall be deducted from said contract price; and in like manner, should the bridge be completed at an earlier date than November 1, 1882, then, in such event the sum of $1,000 per week shall be added to said contract price for the period by which said fixed date of completion shall be anticipated.'

Rust & Coolidge entered upon the work of building the bridge, but it was not completed the first of November, and is not yet completed. The defendants continued to work on the bridge, and their monthly estimates for work done and materials furnished were honored and paid by the railway company down to and including the month of April, 1883. The total amount thus paid by the railway company to the defendants under the contract was $268,000.

The May estimate for work done and materials furnished, amounting to $15,932.58, after deducting the 10 per cent., the railway company refused to honor. In a letter of the defendants of June 29, 1883, they state that unless the differences between the parties are adjusted at a proposed conference, 'we shall, upon Saturday, July 7, 1883, stop or suspend work upon the Arkansas river bridge until a definite understanding is reached. ' A conference took place between the president of the railway company and the defendants at Pine Bluff on the sixth of July, 1883. They were unable to reconcile their differences, and on the same day the plaintiff brought suit, by attachment, in the Jefferson circuit court against the defendants for $35,000, being $1,000 per week for the number of weeks that had elapsed since the first of November, 1882, and caused the defendants' plant at the bridge, consisting of machinery, tools, houses for hands, camp, camp equipage, and provisions to be attached. The next day the plaintiff filed a bill against the defendants on the equity side of the Jefferson circuit court, setting up, in substance, that the road was completed and ready for traffic, and that the running of trains thereon was only prevented by the non-completion of the bridge; that the bridge could be completed in 20 or 30 days; that the defendants had been paid the full contract price for building the bridge, counting as part payment the weekly forfeiture of $1,000 for 35 weeks; that at the conference between the president of the railway company and the defendants, the day previous, the latter demanded of the plaintiff, as a condition of going on with the work, a release from all claims for damages by reason of the delay in the completion of the bridge, and also $20,000 for extra work and materials, and threatened, if these demands were not acceded to, to stop work on the bridge and remove their plant out of the state; and that plaintiff believed they would carry their threat into execution, unless restrained; that the plant for the construction of the bridge was of such a character that, if removed, it would cost a large sum of money and take months to replace it; and that the plaintiff and the public were deeply interested in a speedy completion of the bridge, to the end that the railroad might be opened for traffic. The bill concludes as follows:

'The plaintiff is willing to pay into the registry of this court such sum as shall be necessary for the completion of said work, if such court shall order and direct the progress of the work by a receiver appointed by the court. The premises considered, the plaintiff prays for process according to law that the said defendants, their agents, servants, or employes, and all other persons, be restrained and enjoined from destroying, injuring, or interfering with, or removing, said tools, machinery, or appliances necessary to said work, or the materials used therein; and that a receiver be appointed by the court to take charge of said work, and the material, fixtures, and tools used therein, and proceed to carry out and complete the same in accordance with the specifications thereof, and for said purpose be fully authorized to employ men and labor, and use the tools of defendant therefor.'

Upon filing this bill, without notice to the defendants or their agents, the state court made an order enjoining the defendants from taking possession of, using, or in any manner interfering with their plant at the bridge, and appointing a receiver 'with full power and authority, so far as possible for him to do, to carry out and execute in full, and according to the specifications thereof, the contract between the plaintiff and defendants in relation to the building of said bridge, and for said purpose he is hereby authorized and empowered to take charge of and use all material now in the vicinity of said work, together with all the tools, machinery, or other appliances necessary to the work thereon, offices and houses for hands, kitchen and dining-room furniture,' and concludes with an order to the sheriff to turn over to the receiver the defendants' plant in his custody on the writ of attachment. The order does not state from what source the receiver is to obtain funds to carry on the work. On the ninth of July the defendants filed in the state court their petition and bond for the removal of the cause to this court, on the ground of the citizenship of the parties. The record in the case was filed in this court on the twelfth of July, and afterwards the defendants, upon due notice to the plaintiff, moved to dissolve the injunction and discharge the receiver. Thereupon the plaintiff moved for leave to amend its bill, which leave was given, and an amended bill filed accordingly. The amended bill sets out at length the contract and correspondence between the parties; repeats the allegations of the original bill, with some variations of statement and addition of detail; alleges that the defendants, in making their proposal and estimates for the building of the bridge, included in the same the value of the use of the plant, tools, and machinery required to be used by the defendants in the construction of the bridge, and that the estimates that were made from time to time included the value of the use of said plant, and entitled plaintiff to the use of said plant until the completion of the bridge; that at the Missouri and Texas state lines the plaintiff's road connected with roads in these states, making the road in this state a connecting link in a continuous line extending from Gatesville in Texas to Cairo, Illinois, a distance of about 750 miles, and that as soon as the bridge is completed so that trains can cross thereon, the United States mail will be carried over the whole of said line; that the bridge is so nearly completed that the same can be finished in 20 days, at an expense of not more than $10,000, 'in connection with the use of the materials, tools, machinery, and plant now at said bridge,' but that if defendants are allowed to remove their plant the bridge cannot be finished in a less period than six months, and at a cost of not less than $50,000; that plaintiff 'is willing to pay and indemnify the defendants from any and all loss which they may sustain by reason of the institution of this suit, if wrongfully brought, and the use of the plant and property of the defendants by the receiver in the completion of said bridge. ' The bill does not allege that the defendants are insolvent. The defendants have filed an answer to the original and amended bill, in which the delay in the construction of the bridge is stated to have arisen from sickness of laborers,--particularly skilled laborers, whose places could not be supplied,-- from bad weather, repeated and unlooked-for floods in the ...

To continue reading

Request your trial
9 cases
  • Dunn v. Burlington, Cedar Rapids & Northern Railway Co.
    • United States
    • Supreme Court of Minnesota (US)
    • March 12, 1886
    ......Cas. 313; Ohle v. Chicago & N.W. Ry. Co., 64 Iowa 599, (21 N.W. 101;). Ellerman v. New Orleans, etc., R. Co., 2. Woods 120, 8 F. Cas. 524; Texas, etc., Ry. Co. v. Rust, 5 McCrary 348, (17 F. 275;). Clippinger v. Mo. Valley Life Ins. Co., 1. Flippin 456, 5 F. Cas. 1066; Spear, Fed. Jud. 472, ......
  • Antero & Lost Park Reservoir Co. v. Lowe
    • United States
    • Supreme Court of Colorado
    • November 23, 1920
    ...... equity at the suit of the defendant to perform it on his. part. The remedy must be mutual. Texas & St. L. Ry. Co. v. Rust, (C. C.) 17 F. 275; Strang v. Richmond P. & C. R. Co. (C. C.) 93. Fed. 72; Strang v. Richmond P. & C. R. Co., 101. F. ......
  • Core v. Southwestern Bell Telephone Co.
    • United States
    • U.S. District Court — Western District of Arkansas
    • November 9, 1987
    ...& T. Coal Co., 96 F. 353 (8th Cir.1899), rev'd on other grounds, 183 U.S. 185, 22 S.Ct. 47, 46 L.Ed. 144 (1901); Texas & St. L.R. Co. v. Rust, 17 F. 275 (8th Cir.1883). Even though state court orders are not conclusive, they do remain binding on the federal court until set aside. Wright, Mi......
  • Lane v. Pacific & Idaho Northern Co.
    • United States
    • United States State Supreme Court of Idaho
    • January 22, 1902
    ......Railroad Co., 1 Dill. (U. S.) 121, F. Cas. No. 4629; Ross v. Union P. R. Co., 1 Woolw. 26,. F. Cas. No. 12,080; Railway Co. v. Rust, 17 F. 275,. 282; Center v. Davis, 48 Cal. 453; Sumers v. Bean, 13 Gratt. (Va.) 404; Angus v. Robinson,. 32 Vt. 60; 20 Ency. of Pl. & Pr. 438; ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT