The Board of Commissioners of Fulton County v. Gibson
Decision Date | 14 May 1902 |
Docket Number | 19,459 |
Citation | 63 N.E. 982,158 Ind. 471 |
Parties | The Board of Commissioners of Fulton County v. Gibson |
Court | Indiana Supreme Court |
From Kosciusko Circuit Court; H. S. Biggs, Judge.
Action by Jordan E. Gibson against the board of commissioners of Fulton county for extra work performed and material furnished in the construction of a court-house. From a judgment for plaintiff, defendant appeals.
Affirmed.
G. W Holman, R. C. Stephenson, E. Myers and J. D. Widaman, for appellant.
L. W Royse, B. Shane, I. Conner, J. Rowley, W. C. Bailey and C. A Cole, for appellee.
The complaint in this action is in two paragraphs, both declaring on the quantum meruit, for extra work done and extra material furnished in and about the construction of a subbasement to a court-house, which said appellant caused to be built at Rochester, Indiana, for the county of Fulton. While this is the first appeal of this particular action, yet the subject-matter of the controversy here involved has been twice before this court. See Myers v. Gibson, 147 Ind. 452, 46 N.E. 914; Myers v. Gibson, 152 Ind. 500, 53 N.E. 646. The appellant, after taking the various preliminary steps required by statute for the building of a court-house, awarded a contract therefor to appellee at and for the price of $ 76,073. The appellee sought by this action to recover the additional sum of $ 19,996.42. He recovered a judgment below in the sum of $ 11,595.81, and from said judgment the appellant prosecutes this appeal.
According to the testimony of the appellee, after the execution of the original contract, and after he had torn down the old court-house, the board of commissioners and the architect proceeded to locate the new building, and fixed a grade line for it. The natural surface of the ground on which the building was to stand was irregular, and it was higher on one side than on the other. After the fixing of the grade line, appellee proceeded to excavate the dirt for the trenches for the walls of the building. The depth of the exterior trenches, when completed, was three feet and ten inches below the grade line, and it was at that level, if the specific provisions of the plans and specifications had been followed, that the footings for the exterior walls should have been put in. Appellee then notified the members of the board of commissioners and the architect that the excavation was ready for their inspection. The lower surface of the ground in the trenches was, as appellee testified, "part of it loam, some of it hard-pan, some sand and gravel, varied at different points all around the building". He further testified upon this subject that "there would be a few feet of sand, and some hard-pan, and on the low side we would come around to sand or loam before we would strike the hard-pan". After examining the trenches, the architect said, in the presence of appellee and the members of the board: . He then directed that the excavation be carried down to a solid and suitable foundation, and that twelve inches of concrete should be put in below the stone footings indicated in the plans. The board entered an order in its record, on the same day, as follows: Appellee did not know that this order had been made until he was advised of it that afternoon, when all of the parties again met. After further consideration, it was suggested by one of the members of the board that, in view of the fact that the foundation would have to be put down much deeper, it would cost but little more to make a subbasement, to put the steam pipes, etc., in, and save the basement rooms for offices. The members of the board asked the architect for an estimate of the cost of the change, but he said that he could not make it at that time. Then they asked the appellee to make an estimate. After making some borings, to ascertain the character of the soil below, and making a calculation as to the cost of the additional labor and material necessary to accomplish the change, appellee met with the three members of the board and the architect in the appellee's temporary office that had been put up on the court-house square. Appellee then informed the members of the board that he thought that the construction of such a subbasement as he understood that they wanted would cost about $ 20,000. It was finally orally agreed that such subbasement should be put in, and that the architect should make an estimate, presumably of the cost, later. The following agreement was then reduced to writing, and signed by the three commissioners and the appellee:
The specifications that were a part of the original contract contained, among others, the following provisions: It is further provided in said specifications that "all footings for piers, columns, and the walls of the building are to be laid below the basement floor line and to the depths shown on sections."
The fourth section of the contract authorized the board to make changes, and provided that "the difference for work omitted, as aforesaid, shall be deducted from the amount of this contract, by a reasonable and proper valuation thereof, and for any additional work required, as aforesaid, in alterations, or modifications of said work, the amount based upon same prices, at which contract is taken, shall be agreed upon, before commencing additions, alterations or modifications aforesaid, as provided and hereinafter set forth in the seventh clause of this contract." The sixth section of the contract is as follows: "Should any dispute arise, respecting the true construction, interpretation or meaning of the drawings or specifications, or of any part thereof, or as to what is extra work, outside of the contract, the same shall be decided by A. W. Rush & Son, architects, and the said board, and their decision shall be final and conclusive." The seventh section of the contract contained the following provision: "No new work of any description done on the premises, or any work whatsoever, shall be considered as extra, unless a separate estimate in writing for the same, before its commencement, shall have been submitted by the contractor to the superintending architects and the board of commissioners, and their signatures obtained thereto."
After the contract of June 12, 1895, was executed, the appellee constructed said subbasement, and in doing so he put in the footings for the exterior walls nine feet below the depth of the trenches as originally dug, and made corresponding changes in the depths of the foundations for the interior walls and tower piers. There is testimony in the record which conflicts with many of the above statements, but we have set out the evidence in outline, except upon the subject of values, that tends to support the verdict. Upon the completion of the building, appellee filed his said claim with the board of commissioners, but the claim was disallowed.
...
To continue reading
Request your trial-
Paterson v. Condos
... ... from District Court, Washoe County; L. O. Hawkins, Judge ... Action ... Karnes, 2 Kan. App. 782, 44 P ... 41; Board of Com'rs v. Gibson, 158 Ind. 471, 63 ... N.E. 982; Moore ... ...
-
Kann v. Brooks
... ... Roush ... (1899), 154 Ind. 562, 564, 55 N.E. 1017; Board etc ... v. Gibson (1901), 158 Ind. 471, 485, 63 N.E. 982; ... ...
-
Kann v. Brooks
...such interpretation in arriving at the true intention of the parties. Roush v. Roush, 154 Ind. 562-564, 55 N. E. 1017;Board, etc., v. Gibson, 158 Ind. 471-485, 63 N. E. 982;Beck, etc., Co. v. E. B. Co., 25 Ind. App. 662-665, 58 N. E. 859; 9 Cyc. 588 et seq. [6] If we view the lease in quest......
-
Graham v. Mercereau Hawkins Tie Company
... ... circumstances presented in this case. Board, etc., ... v. Gibson (1902), 158 Ind. 471, 63 N.E. 982; ... ...