Tna Merch. Projects Inc. v. Fed. Energy Regulatory Comm'n

Decision Date10 August 2010
Docket NumberNo. 08-1201.,08-1201.
Citation616 F.3d 588
PartiesTNA MERCHANT PROJECTS, INC., Petitioner v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent Bonneville Power Administration, Intervenor.
CourtU.S. Court of Appeals — District of Columbia Circuit

OPINION TEXT STARTS HERE

On Petition for Review of Orders of the Federal Energy Regulatory Commission.

Brian R. Gish argued the cause for petitioner. With him on the briefs was John Cameron.

Samuel Soopper, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Cynthia A. Marlette, General Counsel, and Robert H. Solomon, Solicitor. Barbara C. Biddle and Jeffrey A. Clair, Attorneys, U.S. Department of Justice, entered appearances.

Elizabeth K. Loebach argued the cause for intervenor Bonneville Power Administration. With her on the brief was Mary K. Jensen.

Before: SENTELLE, Chief Judge, and HENDERSON and GARLAND, Circuit Judges.

Opinion for the Court filed by Circuit Judge GARLAND.

GARLAND, Circuit Judge:

Chehalis Power Generating, L.L.C., petitions for review of two orders of the Federal Energy Regulatory Commission (FERC). 1 The orders held that the rate schedule Chehalis proposed for supplying reactive power to the Bonneville Power Administration (BPA) constituted a “changed rate” that was subject to the suspension and refund provisions of § 205(e) of the Federal Power Act (FPA), 16 U.S.C. § 824d(e). Chehalis contends that its proposal was for an “initial rate,” not a “changed rate,” and hence was not subject to suspension or refund. Because the Commission failed to respond to Chehalis' argument that its rate cannot be classified as “changed” since it was not previously filed, we vacate the Commission's orders and remand the case.

I

The Chehalis facility is a 520 megawatt electric generating plant located in Chehalis, Washington. The plant is interconnected with the BPA electric transmission system. In February 2005, Chehalis and other independent generators entered into a settlement agreement with BPA laying out a process through which they could seek compensation for supplying BPA with reactive power. 2 Pursuant to the settlement, Chehalis submitted a proposed rate schedule to FERC “set[ting] forth Chehalis' rates for the provision of Reactive Power Service” to BPA. Rate Schedule at 1 (May 31, 2005) (J.A. 10). The letter accompanying the schedule characterized the submitted rates as “initial rates,” stating: [T]he subject of the submitted rates is a new service offered by Chehalis in that it has never sought to charge for this service before. In addition, BPA is not an existing customer of Chehalis for any purpose.” Letter from Davis Wright Tremaine LLP to FERC at 6 (May 31, 2005) (J.A. 6).

On July 27, 2005, FERC found that Chehalis' proposed tariff was not an initial rate schedule. “An initial rate schedule,” the Commission said, “must involve a new customer and a new service.” Chehalis Power Generating, L.P., 112 F.E.R.C. ¶ 61,144, at 61,806 (2005) (hereinafter Suspension Order). “Chehalis,” however, “has been providing reactive power to BPA pursuant to an interconnection agreement, albeit without charge. Thus, the proposed rates for reactive power ... are not initial rates, but are changed rates.” Id. at 61,807. This finding was significant because § 205(e) of the FPA authorizes FERC to suspend changed rates and make them effective subject to refund, but does not permit it to do the same for initial rates. 16 U.S.C. § 824d(e); see Southwestern Elec. Power Co. v. FERC, 810 F.2d 289, 291 (D.C.Cir.1987) (holding that § 205 “empowers the Commission to exercise suspension and refund authority only over filings legitimately characterized as changed rates; as to initial rates, the Commission's ratemaking powers are purely prospective” (citing Middle South Energy, Inc. v. FERC, 747 F.2d 763, 772 (D.C.Cir.1984))). Exercising its authority under § 205(e), FERC accepted Chehalis' filing, “suspend[ed] it for a nominal period, to become effective August 1, 2005 ... subject to refund,” and established “hearing and settlement judge procedures.” Suspension Order, 112 F.E.R.C. at 61,807.

On August 26, 2005, Chehalis moved for rehearing, arguing that FERC had wrongly characterized the rate schedule as “changed” rather than “initial.” Req. for Reh'g at 4-6. Of particular pertinence to this appeal, Chehalis argued (among other things) that FERC's § 205(e) authority extends only to rates described in § 205(d), which, in turn, only encompasses changes to rates described in § 205(c). Id. at 5. And § 205(c), Chehalis contended, only covers rates that have been filed with the Commission. Id. Because Chehalis had not previously filed any rates with FERC for providing reactive power to BPA, it contended that the proposed rates fell outside FERC's authority under § 205(e).

On December 15, 2005, FERC denied Chehalis' request for rehearing, Chehalis Power Generating, L.P., 113 F.E.R.C. ¶ 61,259 (2005) (hereinafter Rehearing Order), once again ruling that the proposed rate schedule contained changed rates. Id. at 62,025. Emphasizing the “latitude that the Commission has to interpret what constitutes a changed rate versus what constitutes an initial rate,” FERC held that its “well-settled precedent [established] that an initial rate is one that provides for a new service to a new customer.” Id. Applying this definition, FERC determined that, because “prior to [submitting its proposed rate schedule] ... Chehalis had been providing reactive power to BPA pursuant to its interconnection agreement[,] ... it is not now providing a new service nor is it now providing service to a new customer.” Id.

This petition for review followed.

II

We have jurisdiction to review FERC's orders pursuant to § 313(b) of the FPA. 16 U.S.C. § 825 l(b). The orders are subject to reversal if they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see ExxonMobil Gas Mktg. Co. v. FERC, 297 F.3d 1071, 1083 (D.C.Cir.2002). To the extent Chehalis is challenging FERC's interpretation of the meaning of FPA § 205(e), we review that interpretation under the familiar two-step framework of Chevron U.S.A. Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984); see ExxonMobil Gas Mktg., 297 F.3d at 1083. Under that framework, [i]f the intent of Congress is clear, ... [a court] must give effect to the unambiguously expressed intent of Congress.” Chevron, 467 U.S. at 842-43, 104 S.Ct. 2778. But “if the statute is silent or ambiguous with respect to the specific issue,” the court must uphold the agency's interpretation as long as it is reasonable. Id. at 843, 104 S.Ct. 2778.

Chehalis advances a host of grounds for reversing the Commission's orders. First, it contends that there is “no evidence in the record as to whether Chehalis had been providing any reactive power prior to filing its rate schedule,” and hence no support for regarding the schedule as anything other than “initial.” Pet'r Br. 20. Second, it argues that, regardless of whether it had previously supplied reactive power to BPA, it had “never before charged or collected one cent of revenue for the provision of reactive power,” and “BPA had never been [its] customer ... for any power service.” Id. at 17. Thus, its rate filing fits FERC's definition of an initial rate as a “new service to a new customer.” Id. Third, Chehalis maintains that, to the extent consumer protection concerns drove FERC to expand its interpretation of what constitutes an initial rate under FPA § 205, amendments to FPA § 206 now provide “virtually the same refund protection ... for an initial rate ... as there is for a changed rate,” thus giving FERC no reason “to try to stretch the definition of changed rates.” Id. at 26-27 (citing the Energy Policy Act of 2005, Pub L. No. 109-58, 119 Stat. 594, and the Regulatory Fairness Act, Pub.L. No. 100-473, 102 Stat. 2299 (1988)). Fourth, Chehalis argues that FERC's Suspension Order was not supported by the precedents upon which it relied. Id. at 24-25 (contending that Calpine Oneta Power, L.P., 103 F.E.R.C. ¶ 61,338 (2003), was wrongly decided, and that WPS Canada Generation, Inc., 103 F.E.R.C. ¶ 61,193 (2003), Florida Power & Light Co., 65 F.E.R.C. ¶ 61,411 (1993), and Florida Power & Light Co. v. FERC, 617 F.2d 809 (D.C.Cir.1980), are inapposite).

In the proceedings below, FERC responded to these arguments. First, the Commission found that “Chehalis ha[d] been providing reactive power to BPA pursuant to an interconnection agreement,” Suspension Order, 112 F.E.R.C. at 61,807, a point it now contends is made plain by the text of Chehalis' proposed rate schedule, Resp't Br. 13. Second, the Commission answered Chehalis' claim that a service being provided at no cost cannot qualify as an initial rate by noting that its precedents define initial rates as requiring both “a new customer and a new service.” Suspension Order, 112 F.E.R.C. at 61,806-07 & n. 9. Consistent with its decision in Calpine Oneta Power, L.P., 103 F.E.R.C. at 62,282-83, the Commission held that Chehalis' prior provision of reactive power to BPA-even at no cost-means that it was not proposing to provide a new service. Third, the Commission noted that, notwithstanding the amendments to FPA § 206, “a fundamental difference still exists” between § 205 and § 206. Rehearing Order, 113 F.E.R.C. at 62,025 n. 18. On appeal, FERC further argued that its decision to proceed under § 205 made the petitioner's arguments concerning § 206 irrelevant. Resp't Br. 17. Finally, FERC maintained that none of the precedents Chehalis cited were in conflict with the orders at issue here. To the contrary, it argued-as it did below-that Calpine Oneta Power was directly on point. Id. at 18-19.

We need not determine who has the better of any of these four arguments because Chehalis also advanced a fifth, substantial argument that the Commission...

To continue reading

Request your trial
11 cases
  • Ass'n of Private Colleges & Univs.v. Duncan
    • United States
    • U.S. District Court — District of Columbia
    • June 30, 2012
    ... ... Negotiated Rulemaking Committees, 74 Fed.Reg. 24,728, 24,728 (May 26, 2009). After three ... Bioscience, Inc. v. Thompson, 269 F.3d 1077, 1083 ... TNA Merchant Projects, Inc. v. FERC, 616 F.3d 588, 591 (D.C.Cir.2010) ... The debt measures are a significant regulatory intervention, but they do not [870 F.Supp.2d ... ...
  • Singh v. Attorney Gen. of the U.S
    • United States
    • U.S. Court of Appeals — Third Circuit
    • August 31, 2021
    ... ... 2016) (quoting Gustafson v. Alloyd Co., Inc. , 513 U.S. 561, 568, 115 S.Ct. 1061, 131 ... v. Reliant Energy Servs., Inc ., 551 U.S. 224, 232, 127 S.Ct ... " its interpretation is reasonable); TNA Merch. Projects, Inc. v. F.E.R.C ., 616 F.3d 588, 593 ... definition by the [Federal Energy Regulatory] Commission, we cannot defer to one that is ... ...
  • Miller v. Clinton
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • August 7, 2012
    ... ... Inc. v. Natural Resources Defense Council, Inc., 467 ... TNA Merchant Projects, Inc. v. FERC, 616 F.3d 588, 593 (D.C.Cir.2010); ... Regulation (FAR) and its web of regulatory and associated statutory provisions governing the ... v. Brownlee, 389 F.3d 1243, 1248 (Fed.Cir.2004); Redland Co., Inc. v. United States, ... ...
  • Southcarolina v. United States
    • United States
    • U.S. District Court — District of South Carolina
    • March 14, 2017
    ... ... United States; United States Department of Energy; Rick Perry, in his official capacity as ... See Fed. R. Civ. P. 12(d); Zak v ... Chelsea Therapeutics ... v ... Kolon Indus ., Inc ., 637 F.3d 435, 448 (4th Cir. 2011)). Such ... In re New Haven Projects Ltd ... Liability Co ., Page 20 225 F.3d 283, ... Air Regulatory Grp ... v ... Envtl ... Prot ... Agency , ___ U.S ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT