Town of Winnsboro v. Wiedeman-Singleton, Inc.

Citation307 S.C. 128,414 S.E.2d 118
Decision Date08 October 1991
Docket NumberNo. 23563,INC,WIEDEMAN-SINGLETO,23563
CourtUnited States State Supreme Court of South Carolina
PartiesTOWN OF WINNSBORO, Plaintiff-Respondent, v., and Turner-Murphy Company and American Enviroport, Inc., Defendants, of which Specialty Constructors, Inc., f/k/a American Enviroport, Inc., is Petitioner, and Turner-Murphy Company, Inc. is Respondent. . Heard

Walter B. Todd, Jr., and Tobias G. Ward, Jr., both of Todd & Barber, PC, Columbia, for petitioner.

Stephen G. Morrison and James C. Gray, Jr., both of Nelson, Mullins, Riley & Scarborough, Columbia, for respondent.

ON WRIT OF CERTIORARI TO THE COURT OF APPEALS

TOAL, Justice:

We granted certiorari in this case to review the judgment of the Court of Appeals in Town of Winnsboro v. Specialty Constructors, Inc., 303 S.C. 52, 398 S.E.2d 500 (Ct.App.1990). The petitioner, Specialty Constructors, asserts that the Court of Appeals erred in (1) affirming the trial court in directing a verdict against Specialty for equitable indemnity; (2) that the Court of Appeals erred in overruling its former decision in JKT Co. v. Hardwick, 284 S.C. 10, 325 S.E.2d 329 (Ct.App.1984); and (3) that the Court of Appeals erred in affirming the trial court because Turner-Murphy did not allege breach of contract. We affirm the Court of Appeals decision.

FACTS

The Town of Winnsboro ("Winnsboro") hired Wiedeman-Singleton ("Engineers") to design a wastewater treatment facility ("sewer"). Turner-Murphy Company was hired as the general contractor to construct the sewer. Specialty Constructors was hired by Turner-Murphy and approved by Winnsboro to manufacture and install the filter system for the sewer.

Winnsboro experienced numerous problems with the new sewer. Ultimately, Winnsboro brought suit against the Engineers and the general contractor, Turner-Murphy. After discovery began, it became apparent that many of the problems experienced by Winnsboro were a result of the malfunction of the filter system which was manufactured and installed by Specialty Constructors.

Turner-Murphy filed a motion to implead Specialty Constructors. The motion was denied. Thereafter, Winnsboro amended its complaint to add Specialty Constructors as a party defendant. Turner-Murphy amended its answer and asserted a cross-claim against Specialty Constructors for any judgment Winnsboro might receive against it and for attorney fees and costs.

At trial, the judge sent the case to the jury, reserving the cross-claim issues until the jury decided the issues in the complaint. The jury returned a verdict in favor of Winnsboro against Specialty Constructors in the amount of $85,000.00 on a negligence theory. Further, the jury found Specialty Constructors guilty of willful and wanton conduct and awarded punitive damages to Winnsboro. Turner-Murphy was found not liable to Winnsboro by the jury.

The trial judge directed a verdict in favor of Turner-Murphy on its cross-claim for attorney fees and costs against Specialty Constructors. Specialty Constructors appealed. The Court of Appeals affirmed in Town of Winnsboro v. Specialty Constructors, Inc., 303 S.C. 52, 398 S.E.2d 500 (Ct.App.1990). We granted certiorari to

Specialty Constructors to review the decision of the Court of Appeals.

ISSUES

1. Did the Court of Appeals err in affirming a directed verdict on the cross-claim for equitable indemnity?

2. Did the Court of Appeals err in overturning JKT Co. v. Hardwick because the complaint should determine the status of "joint tort-feasor" as a bar to equitable indemnity?

3. Did the Court of Appeals err in affirming the directed verdict in favor of Turner-Murphy, when Turner-Murphy's cross-claim did not allege breach of contract?

ANALYSIS

This Court has long recognized the principle of equitable indemnification. See e.g. Stuck v. Pioneer Loggins Machinery, Inc., 279 S.C. 22, 301 S.E.2d 552 (1983); Addy v. Bolton, 257 S.C. 28, 183 S.E.2d 708 (1971); South Carolina Electric & Gas Co. v. Utilities Construction Co., 244 S.C. 79, 135 S.E.2d 613 (1964). The damages which can be claimed under equitable indemnity may include the amount the innocent party must pay to a third party because of the at-fault party's breach of contract or negligence as well as attorney fees and costs which proximately result from the at-fault party's breach of contract or negligence. See Addy v. Bolton, 257 S.C. 28, 183 S.E.2d 708 (1971); South Carolina Electric & Gas Co. v. Utilities Construction Co., 244 S.C. 79, 135 S.E.2d 613 (1964). The principle of equitable indemnity including attorney fees and costs is not new to American law. In the early part of this century, the Maryland Court of Appeals wrote:

The general rule is that costs and expenses of litigation, other than the usual and ordinary court costs, are not recoverable in an action for damages, nor are such costs even recoverable in a subsequent action; but, where the wrongful acts of the defendant have involved the plaintiff in litigation with others, or placed him in such relations with others as make it necessary to incur expenses to protect his interest, such costs and expenses should be treated as the legal consequences of the original act.

McGaw v. Acker, Merrall & Condit Co., 111 Md. 153, 73 A. 731 (1909).

In Addy v. Bolton, 257 S.C. 28, 183 S.E.2d 708 (1971), this Court allowed the owner/lessor to recover attorney fees and costs from the contractor who negligently set fire to the building damaging the lessee's property. The lessee, Addy, sued the lessor Bolton and the contractor Thompson. The jury found Thompson negligent and exonerated Bolton. This Court allowed Bolton to recover attorney fees and costs from Thompson incurred in defending for Thompson's negligence.

The relationship between Bolton, the owner, and Thompson, the contractor, was sufficient in that case to allow Bolton to recover his attorney fees and costs for defending the negligence of Thompson. Thompson...

To continue reading

Request your trial
36 cases
  • Dent v. Beazer Materials and Services, Inc.
    • United States
    • U.S. District Court — District of South Carolina
    • December 28, 1995
    ...provision, mere allegations in a complaint do not control whether the non-culpable party is entitled to indemnification. Town of Winnsboro, 414 S.E.2d at 120-21. The jury found that Conoco was named in this lawsuit solely because of Beazer's use of the leased premises and, thus, Conoco is c......
  • Kuznik v. Bees Ferry Associates
    • United States
    • South Carolina Court of Appeals
    • September 25, 2000
    ...Town of Winnsboro v. Wiedeman-Singleton, Inc. (Winnsboro I), 303 S.C. 52, 56, 398 S.E.2d 500, 502 (Ct.App.1990), aff'd 307 S.C. 128, 414 S.E.2d 118 (1992) (Winnsboro II) (citation omitted). "In an action at law, on appeal of a case tried without a jury, the findings of fact of the judge wil......
  • Myrtle Beach Pipeline Corp. v. Emerson Elec. Co., No. 3:86-1796-21.
    • United States
    • U.S. District Court — District of South Carolina
    • December 8, 1993
    ...fact. See generally Town of Winnsboro v. Wiedeman-Singleton, Inc., 303 S.C. 52, 398 S.E.2d 500, 502-03 (Ct.App. 1990), aff'd, 307 S.C. 128, 414 S.E.2d 118 (1992); 42 C.J.S. Indemnity § 3 (1991). Indemnity imposed by fact is "express indemnity" and is usually based on explicit language in a ......
  • VERMEER CAROLINA'S v. Wood/Chuck Chipper
    • United States
    • South Carolina Court of Appeals
    • June 1, 1999
    ...Town of Winnsboro v. Wiedeman-Singleton, Inc. (Winnsboro I), 303 S.C. 52, 56, 398 S.E.2d 500, 502 (Ct.App.1990), aff'd, 307 S.C. 128, 414 S.E.2d 118 (1992) ((Winnsboro II) (citation Traditionally, courts have allowed equitable indemnity in cases of imputed fault or where some special relati......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT