TWB Architects, Inc. v. Braxton, LLC

Decision Date22 July 2019
Docket NumberNo. M2017-00423-SC-R11-CV,M2017-00423-SC-R11-CV
Citation578 S.W.3d 879
Parties TWB ARCHITECTS, INC. v. The BRAXTON, LLC et al.
CourtTennessee Supreme Court

William R. O’Bryan, Jr., and Kevin C. Baltz, Nashville, Tennessee, for the appellants, The Braxton, LLC, and Fidelity and Deposit Company of Maryland.

Donald N. Capparella, Nashville, Tennessee, for the appellee, TWB Architects, Inc.

Sharon G. Lee, J., delivered the opinion of the Court, in which Jeffrey S. Bivins, C.J., Cornelia A. Clark, Holly Kirby, and Roger A. Page, JJ., joined.

Sharon G. Lee, J.

We granted review to determine whether summary judgment was properly granted to an architect firm seeking to recover its design fees from a development company. The architect firm designed a condominium project for the development company. The development company ran short of funds and was not able to pay the architect firm under their design contract. As a result, the architect firm’s president agreed to accept a condominium in the project instead of the fee. But the development company did not fulfill that agreement because the development company had pledged the condominium as collateral for a construction loan. The architect firm filed a mechanic’s lien for its unpaid fee under the parties' design contract, and then filed this suit to enforce the lien. The trial court granted summary judgment to the architect firm, holding that the firm was entitled to its fee under the design contract, and there was insufficient evidence that the parties intended a novation by substituting the agreement to convey a condominium for the design contract. The Court of Appeals affirmed. We find that disputed questions of material fact exist about whether the architect firm and the development company intended a novation when they entered into the agreement for the condominium. Thus, the trial court should not have granted summary judgment to the architect firm. We reverse and remand to the trial court.

Background

In February 2005, TWB Architects, Inc., through its president and sole owner, Timothy W. Burrow, signed an agreement ("Architect Agreement") with Progress Capital Partners, LLC, through its sole member and chief manager, John Rankin. Under the Architect Agreement, TWB Architects agreed to provide design services for the construction of a condominium complex, known as "The Braxton," in Ashland City. Progress Capital Partners agreed to pay TWB Architects a fee for its design services based on two percent of the construction costs for the project, with progress payments based on an hourly rate billed monthly before construction.1

Progress Capital Partners failed to obtain sufficient financing for the project. In early May 2005, Mr. Rankin advised Mr. Burrow that the construction budget could not cover TWB Architects' fee. Mr. Rankin proposed that Mr. Burrow accept a condominium in the project as payment for the architect firm’s fee. Mr. Burrow, with the consent of TWB Architects, agreed.

Later, Progress Capital Partners deeded the property on which the project was located to The Braxton, LLC ("Braxton"), a company formed by Mr. Rankin.2 On February 16, 2006, Braxton and Mr. Burrow agreed in writing ("Condominium Agreement") for Mr. Burrow to buy Penthouse P6 for "$0 in consideration of design fees owed in contract for architecture design" between Progress Capital Partners and TWB Architects dated February 17, 2005. Mr. Burrow, with TWB Architects' consent, signed as purchaser and Mr. Rankin signed as seller for Braxton.3 Attached and incorporated into the Condominium Agreement was a copy of the Architect Agreement, showing that TWB Architects' fee supported the zero dollar purchase price. Under the Condominium Agreement, the closing of the sale would be on or before August 4, 2008, with an option for Braxton to extend that date for up to ninety days.

After June 2005, TWB Architects stopped sending Braxton monthly invoices for progress payments. By May 2006, TWB Architects had substantially completed its design work. During construction of the project, Mr. Rankin routinely submitted Loan Advance Requisition forms and Sworn Owner’s Statements to the bank financing the project. Mr. Rankin signed the Sworn Owner’s Statements, verifying that there were no unpaid architect fees because he understood there were no fees owed to TWB Architects based on the Condominium Agreement.

During construction of the project, Mr. Burrow spent nearly $40,000 for upgrades to Penthouse P6, which he referred to as "my penthouse." He corresponded with the general contractor and with Mr. Rankin about specific upgrades to customize Penthouse P6, which included cabinets, granite, tile, lighting, mantles, hearths, doors, wiring, and a unique floorplan.

On November 3, 2008, the day before the extended closing deadline under the Condominium Agreement, Mr. Burrow wrote to Mr. Rankin demanding to close the next day. In addition, Mr. Burrow stated that if Braxton failed to meet the closing deadline, then Mr. Burrow would treat the Condominium Agreement "as continuing in full force and effect, and require specific performance of [Braxton] to deliver a deed." He mentioned neither the Architect Agreement nor the design fee.

A week later, Mr. Burrow wrote to Mr. Rankin to clarify "instead of TWB Architects, Inc. receiving cash for the design fee of 2 percent of construction cost as set forth in the ... [Architect Agreement], I will be given Penthouse P6 and the boat slip." He asked Mr. Rankin to sign at the bottom of the letter to confirm the terms stated in the letter, but Mr. Rankin did not do so.

On November 11, 2008, Mr. Burrow emailed Mr. Rankin, asking whether he had told the bank that the proceeds from the condominium sale to Mr. Burrow would be zero dollars. Mr. Rankin replied that he had told the bank that Mr. Burrow would need to be paid two percent or receive his condominium unit, and that Mr. Burrow had invested tens of thousands of dollars in the condominium. Mr. Rankin later admitted in a 2010 deposition that he told the bank something different—that Mr. Burrow was "our design architect, and he’s getting this unit for his fees."

On November 25, 2008, Mr. Burrow wrote to Robert Holland, an attorney for Braxton, stating that Mr. Burrow had entered into a Condominium Agreement for Penthouse P6 that was set to close on December 8, 2008, and that he was concerned about the incomplete swimming pool at the condominium complex. On December 12, 2008, Mr. Burrow wrote again to Mr. Holland explaining that he had rented his home to a tenant who planned to move in on December 18, 2008. In that letter, Mr. Burrow stated that in the Condominium Agreement, Braxton had granted its rights to Penthouse P6 to Mr. Burrow and thus Braxton had "no rights to the condominium to grant, as security for a loan or otherwise, and any attempt to do so would be voidable."

On December 27, 2008, Mr. Burrow moved into Penthouse P6 although there had been no closing. He later advertised it for rent "by owner" and leased it for a short time before moving back in and using the condominium as his personal residence. On January 2, 2009, Mr. Burrow wrote to Mr. Holland stating that he had moved into his penthouse and that "it [was] beautiful." He also expressed concern that sales of other units had not closed, the condominium complex looked like a "ghost town," and potential buyers might back out. Mr. Burrow offered his services as an attorney to assist with the situation, stating he would "invest my time to protect my investment in my penthouse."4

On January 6, 2009, Mr. Burrow emailed Mr. Rankin asking if there was any reason why he should not send a letter to Mr. Holland again requesting to close on the condominium and stating that "[t]he condo is my payment for architectural work done on The Braxton, and until closing occurs, I have insufficient security for being paid." Mr. Burrow did not send the proposed letter; instead, the next day he wrote Mr. Holland asking when Braxton intended to complete his condominium, emphasizing that he wanted to close on it as soon as possible. Mr. Burrow gave Mr. Holland until Friday, January 9, 2009, to provide a date for closing or to provide a reason why closing could not occur by the end of the following week, January 16, 2009.

On January 13, 2009, Mr. Burrow, suspecting that Braxton would not deed the condominium to him, notified Mr. Holland in writing that TWB Architects had retained Mr. Burrow’s firm to represent it concerning services provided by TWB Architects under the Architect Agreement. Mr. Burrow stated that TWB Architects had a claim against the owner of the project for $882,526.14, which was two percent of the construction cost.5 Mr. Burrow also stated that if the claim was satisfied by January 19, 2009, or if Braxton provided proper assurances it would be satisfied, then TWB Architects would not file a mechanic’s lien. Mr. Burrow further noted that Braxton could satisfy the claim by transferring ownership of Penthouse P6 to him. This letter, written on Mr. Burrow’s law firm letterhead, was the first time that Mr. Burrow mentioned the Architect Agreement or the fee in his communications with Mr. Holland.

On January 22, 2009, Mr. Burrow wrote Mr. Rankin purporting to state their understanding when they entered into the Condominium Agreement. This letter differs significantly from the letter Mr. Burrow had written on November 10, 2008, for the same stated purpose. In the January 2009 letter, Mr. Burrow said that the Condominium Agreement was intended to provide an additional means to pay for the services of TWB Architects. He further claimed that if for any reason Braxton did not comply with the Condominium Agreement, Mr. Burrow could unilaterally decide whether to seek specific performance under the Condominium Agreement or payment of the design fee under the Architect Agreement. Mr. Burrow asked Mr. Rankin to sign at the bottom of the letter confirming its accuracy, and this...

To continue reading

Request your trial
83 cases
  • Highlands Physicians, Inc. v. Wellmont Health Sys.
    • United States
    • Tennessee Court of Appeals
    • 25 Septiembre 2020
    ... ... " TWB Architects, Inc. v. The Braxton, LLC , 578 S.W.3d 879, 889 (Tenn. 2019) (quoting Rye , 477 S.W.3d at 265 ). Pursuant to Tennessee Rule of Civil Procedure ... ...
  • Phi Air Med., LLC v. Corizon, Inc.
    • United States
    • Tennessee Court of Appeals
    • 5 Marzo 2021
    ... ... TWB Architects, Inc. v. Braxton, LLC , 578 S.W.3d 879, 887 (Tenn. 2019). Summary judgment is appropriate if no genuine issues of material fact exist, and the ... ...
  • Tenn. State Bank v. Mashek
    • United States
    • Tennessee Court of Appeals
    • 21 Mayo 2020
    ... ... Motion, reflects that the Deed was executed to secure the obligations of "Breaking Bread, Inc.[,"] an entity that the Masheks had never heard of nor had any interest in. Additionally, the ... " TWB Architects, Inc. v. The Braxton, LLC , 578 S.W.3d 879, 889 (Tenn. July 22, 2019) (quoting Rye , 477 S.W.3d ... ...
  • Franke v. Clinton William Holland Revocable Trust Uad Aug. 9, 2010
    • United States
    • Arkansas Court of Appeals
    • 1 Septiembre 2021
    ... ... Bennett v. Graves & Assocs., Inc. , 2019 Ark. App. 99, 571 S.W.3d 528. Because the question of what duty is owed is one of law, we ... See TWB Architects, Inc. v. Braxton, LLC , 578 S.W.3d 879 (Tenn. 2019) (citing Celotex Corp. v. Catrett , 477 U.S ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT