U.S. ex rel. Leno v. Summit Const. Co., 88-4122

Decision Date19 December 1989
Docket NumberNo. 88-4122,88-4122
Citation892 F.2d 788
Parties36 Cont.Cas.Fed. (CCH) P 75,774 UNITED STATES of America, ex rel., Thomas G. LENO, Dorothy Leno dba T & D Construction, Plaintiffs-Appellants, v. SUMMIT CONSTRUCTION COMPANY, et al., Defendants-Appellees.
CourtU.S. Court of Appeals — Ninth Circuit

Jeffrey J. Hepworth, Hepworth, Nungester & Lezamia, Twin Falls, Idaho, for plaintiffs-appellants.

Lloyd J. Walker, Twin Falls, Idaho, for defendants-appellees.

Appeal from the United States District Court for the District of Idaho.

Before NELSON, BOOCHEVER and TROTT, Circuit Judges.

NELSON, Circuit Judge:

Appellants Thomas and Dorothy Leno dba T & D Construction ("Leno") challenge a denial of attorneys' fees and the amount of damages awarded by the trial court. Leno argues that its claims against appellees Wausau and Summit Construction were pendent state claims and that as the prevailing party under Idaho law it is entitled to attorneys' fees. The district court refused to award fees on the ground that the action arose under the Miller Act, 40 U.S.C. §§ 270a-270b (1982), which does not allow fee awards. Because we agree with the district court that Leno's claims were brought pursuant to the Miller Act, we affirm the lower court's denial of fees. In addition, appellant argues that the district court arbitrarily calculated damages and failed to consider the equities. We find that the district court did not err in calculating the damages, and we affirm the court's judgment.

FACTUAL AND PROCEDURAL BACKGROUND

Appellee, Summit Construction Company (Summit) was awarded a contract by the United States Forest Service to build nine timber access roads in the Targhee National Forest. As required by the Miller Act, 40 U.S.C. § 270a(a), Summit filed a payment bond issued by appellee, Employers Insurance of Wausau (Wausau).

To construct the road, Summit needed subcontractors to survey the road, clear all the timber, and then excavate. Clearing a road includes removing timber remnants. Timber remnants, known as slash, are removed by raking them into piles and then burning or burying them. After the clearing, a road is excavated by cutting the dirt from the high areas and pushing it into the low areas.

In April or May 1986, Appellant, T & D Construction, a sole proprietorship owned by Thomas and Dorothy Leno (Leno), entered into an oral contract with Garth Aslett, a superintendent for Summit Construction. Under the oral contract Leno agreed to excavate anything he could cut and rip with his D-8h Caterpillar (CAT) tractor for Leno and Summit did not have an agreement to clear the roads. Summit had contracted with Gordon Smith to do the clearing work; however, Smith never completed the clearing on Lucky Dog Road. Because Summit had failed to have the roads cleared completely, Leno raked, piled, and buried the slash on Lucky Dog Road. Leno repeatedly complained about having to clear the roads before excavating because his CAT was not well suited to raking and piling slash.

                $1 per yard on three roads, Lucky Dog, Warm River Road and Warm River Ridge Road.   Leno excavated 46,562 cubic yards of dirt on the three roads and was entitled to $46,562.00 under the oral contract
                

After leaving the site, Leno was paid $39,000. On March 31, 1987, Leno filed this lawsuit. Federal jurisdiction was obtained pursuant to the Miller Act. 40 U.S.C. § 270b (1982). In the district court, Leno alleged that Summit had failed to pay for work performed under the contract and for extra work and services done on the project. 1 Leno also requested attorneys' fees.

At the trial Leno recovered a judgment against Summit, Phillip Aslett, and Wausau. 2 The trial court found that Leno was entitled to $46,562 pursuant to the contract, offset by the $39,000 Summit had already paid. The court also found that Summit owed Leno $18,841 under the theory of quantum meruit minus $4,617 for goods and services Summit provided to Leno.

In deciding the quantum meruit award, the court calculated the reasonable value of Leno's raking and piling of the slash on Lucky Dog Road at $200 per acre. Gordon Smith had agreed to do the clearing work less the grubbing for $1,200 per acre or to do the clearing for $800 per acre excluding grubbing and raking and piling slash. The district court calculated from these figures that the value of raking and piling slash was $400 per acre. However, the district court also considered Leno's testimony that he did a poor job raking and piling slash because his CAT was not well suited for the job. The court then concluded "[f]rom the totality of the evidence" that the reasonable value of Leno's raking and piling of the slash on Lucky Dog Road was only $200 per acre for a total of $2400.

After the district court issued the judgment, Leno moved to amend the Judgment and Findings of Fact on five different issues. Leno also petitioned the court for an award of attorneys' fees pursuant to Idaho Code §§ 12-120(3), 12-121, and 41-1839. On June 28, 1988, the trial court denied Leno's Petition for Award of Attorney Fees because attorneys' fees are "ordinarily not recoverable" under the Miller Act. The district court also refused to amend its Findings of Fact. Leno filed a timely appeal on August 26, 1988. On appeal Leno moved to amend the Judgment and Findings of Fact on only one issue, the damage award for work on Lucky Dog Road, and also appealed the denial of attorneys' fees.

DISCUSSION
I. Attorneys' Fees
A. Standard of Review

While awards of attorneys' fees generally are reviewed for abuse of discretion, Mitchell v. Keith, 752 F.2d 385, 392 (9th Cir.), cert. denied, 472 U.S. 1028, 105 S.Ct. 3502, 87 L.Ed.2d 633 (1985), the issue in this case is the district court's application of law to the fees request. The trial court's application of the correct legal standard is reviewed de novo. United States ex rel. Reed v. Esto, Inc., 884 F.2d 1180, 1184 (9th Cir.1989).

B. Attorneys' Fees under the Miller Act

In the complaint, Leno alleged breach of contract and quantum meruit claims. Both claims were "brought pursuant to the Miller Act." In oral argument, appellant admitted that it brought suit solely under the Miller Act. Even in its request for attorneys' fees, Leno did not mention Idaho Code § 12-120, which would mandate attorneys' fees if the contract or quasi-contract claims had arisen under state law.

On appeal, Leno argued that it now considered the basis for federal jurisdiction to be not the Miller Act but pendent state jurisdiction under United Mine Workers v. Gibbs, 383 U.S. 715, 86 S.Ct. 1130, 16 L.Ed.2d 218 (1966). Both the breach of contract and quantum meruit claims are permitted under the Miller Act. See United States v. Western Casualty and Surety Co., 498 F.2d 335, 338 (9th Cir.1974); Central Steel Erection Co. v. Will, 304 F.2d 548, 551 (9th Cir.1962). Thus, it was within the discretion of the trial court to find that the quantum meruit claim arose as a pendent state claim rather than under the Miller Act. See United Mine Workers, 383 U.S. at 726, 86 S.Ct. at 1139. However, when Leno did not mention the pendent basis for jurisdiction during the trial, it is not surprising that the district court found only Miller Act jurisdiction. Liberal pleading rules do not extend to finding a wholly new basis for jurisdiction after the trial.

Because we find that Leno's claims arose under the Miller Act, no attorneys' fees are available. See F.D. Rich Co. v. Industrial Lumber Co., 417 U.S. 116, 127, 94 S.Ct. 2157, 2164, 40 L.Ed.2d 703 (1974). Under federal law the American rule of fees applies. Each party bears its own legal costs absent an enforceable contract provision or evidence that an opponent has acted "in bad faith, vexatiously, wantonly, or for oppressive reasons." F.D. Rich Co., 417 U.S. at 126, 94 S.Ct. at 2163. 3 Congress did not intend to incorporate state law governing the award of attorneys' fees into the Miller Act and saw no compelling reason to create a Miller Act exception to the general American rule. Id. at 129-31, 94 S.Ct. at 2165-66. Therefore, unless there is a separate state claim at the trial level attorneys' fees are not available in a Miller Act suit even when state law provides for such an award. 4

II. Damages for Work Done on Lucky Dog Road
A. Standard of Review

Leno presents a challenge to the findings of fact of the trial court. "Findings of fact ... shall not be set aside unless clearly erroneous...." Fed.R.Civ.P. 52(a) "A finding is 'clearly erroneous when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.' " United States v. U.S. Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746 (1948).

B. Calculation of Damages on Lucky Dog Road

Leno claims the court erred in calculating damages because it "failed to consider the equities involved and the monetary effect on the parties." On the basis of the trial court's award, Leno believes that it will lose money and "Summit will actually increase its profit on Lucky Dog as a result of its bad faith and incompetence." As the district court noted, this argument is misguided.

The district court calculated the damage...

To continue reading

Request your trial
31 cases
  • Schutts v. Bentley Nevada Corp.
    • United States
    • U.S. District Court — District of Nevada
    • May 7, 1997
    ... ... Wabash R.R. Co., 370 U.S. 626, 630-31, 82 S.Ct. 1386, 1388-89, ... United States ex rel. Leno v. Summit Constr. Co., 892 F.2d 788 (9th ... ...
  • U.S. ex rel. Maris Equipment Co. v. Morganti, Inc.
    • United States
    • U.S. District Court — Eastern District of New York
    • September 20, 2001
    ... ... Leno v. Summit Constr. Co., 892 F.2d 788, 791 (9th Cir.1989) ...         Q: Ms. Hoover, can you tell us please what the contemplated profit was for the original ... ...
  • U.S.A For The Use And Benefit Of Wfi Ga. Inc v. The Gray Ins. Co.
    • United States
    • U.S. District Court — Northern District of Georgia
    • March 24, 2010
    ... ... F.D. Rich Co., Inc. v. United States ex rel. Indus. Lumber Co., Inc., 417 U.S. 116, 121-22, ... United States ex rel. Leno v. Summit Constr. Co., 892 F.2d 788, 789-90 (9th ... ...
  • U.S. ex rel. Metric Elec. v. Enviroserve, Inc.
    • United States
    • U.S. District Court — District of Massachusetts
    • November 24, 2003
    ... ... , Inc., National Union Fire Insurance Co., Pittsburgh, Defendants ... letter and "request[ed] that [Metric] provide us with any information or documentation that you ... E.g., United States ex rel. Leno v. Summit Constr. Co., 892 F.2d 788, 792 (9th ... ...
  • Request a trial to view additional results
1 books & journal articles
  • When Counsel Screws Up: the Imposition and Calculation of Attorney Fees as Sanctions
    • United States
    • Seattle University School of Law Seattle University Law Review No. 33-02, December 2009
    • Invalid date
    ...v. United States, 889 F.2d 973, 986, reh'gdenied897 F.2d 537 (11th Cir. 1989). 99. United States ex rel . Leno v. Summit Constr. Co., 892 F.2d 788, 791 n.4 (9th Cir. 1989). 100. Cooter and Gell, 496 U.S. at 393. 101. Foster v. Michelin Tire Corp., 108 F.R.D. 412, 415 (C.D. Ill. 1985). 102. ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT