U.S. Fidelity and Guar. Co. v. West Point Const. Co., Inc., 87-7160

Decision Date22 February 1988
Docket NumberNo. 87-7160,87-7160
Citation837 F.2d 1507
PartiesUNITED STATES FIDELITY AND GUARANTY COMPANY, a corporation, Plaintiff-Appellant, v. WEST POINT CONSTRUCTION COMPANY, INC., Defendant-Appellee.
CourtU.S. Court of Appeals — Eleventh Circuit

M. Clay Ragsdale, IV, Starnes & Atchison, Birmingham, Ala., for plaintiff-appellant.

J. Littleton Glover, Jr., Glover & Davis, Edwin Vickers Gartin, Newnan, Ga., for defendant-appellee.

Appeal from the United States District Court for the Middle District of Alabama.

Before TJOFLAT and ANDERSON, Circuit Judges, and MOORE *, District Judge.

PER CURIAM:

The primary issue on appeal is whether United States Fidelity and Guaranty Company ("USF & G") is bound to submit to arbitration by virtue of the fact that the performance bond which it issued incorporated by reference the underlying subcontract which in turn contained an arbitration clause. The district court held that USF & G was bound to arbitrate. USF & G appeals. We affirm.

West Point Construction Company, Inc., the defendant-appellee, was general contractor to construct the Lee County Justice Center for the Lee County (Alabama) Commission. West Point attempted to institute arbitration proceedings following the default of the subcontractor, Pruett Brothers Paint Contractors (Pruett). The general contract between West Point and the Lee County Commission contained a general arbitration clause. The subcontract between West Point and Pruett set forth its own arbitration provision, and in a separate article modified that provision by reference to the arbitration provisions of the general contract. The performance bond, issued by USF & G as surety to Pruett, incorporated by reference the subcontract.

USF & G opposed arbitration, arguing that an incorporation by reference clause in the bond did not incorporate the arbitration clause in either the subcontract or the general contract.

The condition of the USF & G bond was proper performance of the subcontract by Pruett. The subcontract was referred to and made a part of the bond. Disputes arising under the contract, including disputes concerning the adequacy of Pruett's performance, were subject to arbitration pursuant to the arbitration provisions of the subcontract. We conclude that the incorporation of the subcontract into the bond expresses an intention of the parties, including USF & G, to arbitrate disputes. Our conclusion is supported by the strong policy favoring arbitration expressed by Congress in the Federal Arbitration Act. 1 J.S. & H. Construction Company v. Richmond County Hospital Authority, 473 F.2d 212, 215 (5th Cir.1973) (taking notice of this Congressional policy favoring arbitration in a context similar to the instant case). See also Exchange Mutual Insurance Company v. Haskell Company, 742 F.2d 274 (6th Cir.1984) (same).

Our holding is consistent with Exchange Mutual, 742 F.2d 274 (1984), in which the Sixth Circuit held under almost identical circumstances that the surety was bound to arbitrate by virtue of the incorporation into the performance bond of a subcontract which itself incorporated an arbitration clause.

USF & G relies upon several cases which limit or deny the effect of clauses which incorporate a contract or subcontract by reference. S. Leo Harmonay, Inc. v. Binks Manufacturing Company, 597 F.Supp. 1014, 1024 (S.D.N.Y.1984); U.S. Steel v. Turner, 560 F.Supp. 871, 874 (S.D.N.Y.1983); Windowmaster Corporation v. B.G. Danis Company, 511 F.Supp. 157 (S.D.Ohio 1981); H.W. Caldwell & Son, Inc., et al. v. John H. Moon & Sons, Inc., 407 F.2d 21 (5th Cir.1969); United States v. Cleveland Electric Company of South Carolina, 373 F.2d 585 (4th Cir.1967). However, the reasoning underlying most 2 of those cases involved the Miller Act 3, in which the federal government is the contract owner and hence the rights and remedies of the parties are limited under the Act. See, e.g. Caldwell, 407 F.2d at 23. The former Fifth Circuit has specifically distinguished such Miller Act cases from cases like the one at bar. In J.S. & H. Construction Co., v. Richmond County Hosp. Auth., 473 F.2d 212 (5th Cir.1973) 4, the general contract between the prime contractor and the owner contained an arbitration clause. The subcontract itself contained no such clause, but it incorporated by reference the provisions of the general contract. In holding that the subcontractor was bound to arbitrate, the former Fifth Circuit explained the "principal basis for skepticism toward incorporation by general reference" of arbitration clauses in Miller Act cases. The skepticism...

To continue reading

Request your trial
57 cases
  • Century Indemnity v. Underwriters, Lloyd's, London
    • United States
    • U.S. Court of Appeals — Third Circuit
    • 15 Octubre 2009
    ...can incorporate the underlying contract's provisions, including its arbitration clause. United States Fidelity & Guaranty Co. v. West Point Constr. Co., 837 F.2d 1507 (11th Cir. 1988) (per curiam); Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274 (6th Cir.1984) (per curiam); Commercial I......
  • Bautista v. Star Cruises
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • 18 Enero 2005
    ...at 449; Kahn Lucas Lancaster, Inc. v. Lark Int'l Ltd., 186 F.3d 210, 218 (2d Cir.1999); cf. United States Fidelity & Guar. Co. v. West Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir.1988) (finding that, under the FAA, the incorporation of an arbitration provision expressed an intent of th......
  • Ggis Ins. Serv. Inc. v. Lincoln Gen. Ins. Co.
    • United States
    • U.S. District Court — Middle District of Pennsylvania
    • 24 Febrero 2011
    ...emphasizing that the decision “relied on the incorporation clause itself”), with id. at 536 (citing U.S. Fid. & Guar. Co. v. W. Point Constr. Co., 837 F.2d 1507 (11th Cir.1988) (per curiam)) (reviewing West Point Construction, in which a performance bond incorporated a subcontract with an a......
  • Schneider Elec. Buildings Critical Sys., Inc. v. W. Sur. Co.
    • United States
    • Court of Special Appeals of Maryland
    • 30 Noviembre 2016
    ...Union Ins. Co. v. Gilbane Building Co. , 992 F.2d 386, 388–89 (1st Cir. 1993) ; United States Fidelity & Guaranty Co. v. West Point Constr. Co. , 837 F.2d 1507, 1508 (11th Cir. 1988) (per curiam); Exchange Mut. Ins. Co. v. Haskell Co. , 742 F.2d 274, 275–76 (6th Cir. 1984) (per curiam); Ras......
  • Request a trial to view additional results
1 books & journal articles
  • The inadvertent waiver of mandatory construction arbitration clauses.
    • United States
    • Florida Bar Journal Vol. 71 No. 9, October 1997
    • 1 Octubre 1997
    ...Inc. v. Roberts Electrical Contractors, Inc., 624 So. 2d 376 (Fla. 1st D.C.A. 1993); USF&G v. Westpoint Construction Co., Inc., 837 F.2d 1507 (11th Cir. 1988). [27] For example, AIA Document 101 incorporates AIA Document 201, General Conditions of the Contract for Construction (1987). [......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT