U.S. for Use and Ben. of Union Bldg. Materials Corp. v. Haas & Haynie Corp.

Decision Date26 June 1978
Docket NumberNo. 75-3078,75-3078
Citation577 F.2d 568
Parties27 UCC Rep.Serv. 32 UNITED STATES of America for the Use and Benefit of UNION BUILDING MATERIALS CORP., Plaintiff-Appellee, v. HAAS AND HAYNIE CORPORATION and the Aetna Casualty and Surety Company, Defendants-Appellants.
CourtU.S. Court of Appeals — Ninth Circuit

Warren Price, III, Honolulu, Hawaii, for plaintiff-appellee.

Jerry A. Ruthruff, Honolulu, Hawaii, for defendants-appellants.

Appeal From the United States District Court for the District of Hawaii.

Before WRIGHT and SNEED, Circuit Judges, and RENFREW, * District Judge.

SNEED, Circuit Judge:

This case, brought pursuant to the Miller Act, 40 U.S.C. § 270b, requires us to review the district court's interpretation of a contract between the prime contractor and a subcontractor. The parties gave differing meanings to the payment clause of their contract and the issue presented to this court is the determination of whose meaning should prevail. We find that the contract was ambiguous and that the district court was not clearly erroneous in finding that the contract should be interpreted in favor of appellee, Union Building Materials Corp. Accordingly, we affirm.

I.

The Facts.

In December 1972, appellant Haas and Haynie Corporation (hereinafter H & H) entered into a contract with the United States for the construction of the United States Courthouse and Federal Office Building in Honolulu, Hawaii. H & H, as prime contractor, soon began the process of lining up subcontractors. In February 1974, H & H entered into a subcontract with appellee Union Building Materials Corporation (hereinafter UBM) for the acquisition and installation of padding and carpeting for the building.

UBM was a new business at the time it entered into this agreement. The primary focus of the business was the sale of lumber products, but approximately 20% of sales came from carpet products. UBM's owner, Keith Kranz, had previously worked for a similar company, but this was his first independent venture as a carpeting subcontractor. During the initial negotiations leading to the signing of this contract, Kranz stated repeatedly that UBM's financial condition was not yet strong and that an immediate cash flow from this project would be necessary. Despite these discussions the standard form subcontract documents normally used by H & H were also used to evidence this contract.

Article XXX of the Subcontract Agreement provides that the subcontractor shall be paid monthly for the aggregate value of the work performed less a 10% retention. Section 12.4 of the Specifications and Bid Forms, which were incorporated into the contract, provides that "material delivered that will be incorporated into the structure will be taken into consideration in computing progress payments . . . . Before each such payment is made . . . the Contractor shall furnish to the Contracting Officer such evidence as he may require as proof of the quantity and value of such materials". Section 12.2 provides that a breakdown of the contract price must be made. "The values in the breakdown will be used for determining progress payments. The Contractor's overhead, profit and cost of bonds shall be prorated through the life of the contract." The specific issue presented by this case is whether the payment made to the subcontractor for materials delivered but not yet installed should include a proportion of the total overhead and profit for the job.

H & H requested a breakdown of the total contract price from UBM soon after the contract was signed. In that breakdown UBM allocated $125,000 to the carpet padding. UBM proceeded to order the carpet padding from General Felt Corporation. The manufacturer's price for the padding allocated to the federal project was approximately $68,000. UBM nevertheless submitted to H & H an invoice for the full $125,000 which it had originally allocated to the padding. H & H accepted this invoice and forwarded it to the government for payment in late May of 1974. H & H received full payment from the government in June.

There was conflicting testimony as to when H & H discovered that the invoice was for more than the manufacturer's price for the padding. The district court found that H & H did not notify the government of any problem and that the General Services Administration (GSA) did not discover the problem until October 1974, as a result of an investigation instigated by Senator Fong as to why UBM had not received any payment at all. In November 1974, the government withdrew credit for all but $60,000 of the contested payment. Meetings were held during the summer and fall in an effort to resolve the dispute. At a meeting on August 31 there was discussion of a compromise payment of $92,000 to UBM. These negotiations failed and this lawsuit was filed in late October 1974.

After a non-jury trial the district court found in favor of plaintiff UBM. The findings of fact and conclusions of law entered by the court reflect some confusion as to the legal basis for that holding. Initially the court concluded that the contract was ambiguous and should be interpreted against the draftsman, H & H. The court then went on to conclude further that UBM was unilaterally mistaken about the contract's meaning and should be granted relief from that mistake because of H & H's failure to inform UBM of that mistake. H & H's appeal from that decision brings the case before this court. Although the district court appears to have considered unilateral mistake as a ground of relief distinct from that available through proper interpretation of an ambiguous contract, no such distinction exists under the circumstances of this case. The focus, in any event, must be upon a failure of communication between the parties. The prevailing understanding where communication fails is that which was known, or ought to have been known, by the other. General contract interpretation principles, not unilateral mistake, is the form in which we think our analysis is better cast. 1

II.

Contract Interpretation.

We start by noting that we are dealing with a written document which contains an express integration clause. It is thus necessary to determine whether the district court properly admitted extrinsic evidence in the process of interpreting the contract, a determination that requires a finding with respect to the ambiguity of the writing. Extrinsic evidence is properly admitted to help ascertain the intended meaning of ambiguous writings. Restatement (Second) of Contracts, § 238; U.C.C. § 2-202; Haw.Rev.Stat. § 490:2-202. 2

A. Was the Contract Ambiguous?

Appellant challenges the district court's determination that the contract was ambiguous in regard to the method of payment for materials delivered but not yet installed. Such a finding presents a question of law, freely reviewable by this court. United States ex rel. White Masonry, Inc. v. F. D. Rich Co., 434 F.2d 855, 858 (9th Cir. 1970); Clayman v. Goodman Properties, Inc., 171 U.S.App.D.C. 88, 96, 518 F.2d 1026, 1034 (1973). Reviewing the written documents which comprise the contract, we are unable to determine whether any payment for profit and overhead was intended to be included in the payment made for materials delivered but not yet installed. The contract merely specifies that payments relating to such material can be made only after proof of the quality and value of such materials is presented. There is no further specification of how value is to be computed. Neither price to the subcontractor nor price to the prime contractor are unreasonable definitions of value. The general reference to profit and overhead being prorated throughout the life of the contract is also ambiguous as to whether payments made prior to beginning work on the contract are to include allowance for profit and overhead. Thus, we find that the contract is ambiguous as to the amount of the payment due on delivery of material. 3 In this situation it was therefore proper for the district court to hear extrinsic evidence to determine the intent of the parties regarding this issue.

B. Interpreting an Ambiguous Contract.

The interpretation of an ambiguous contract is a mixed question of fact and law. United States v. Lewiston Lime Co., 466 F.2d 1358, 1359, fn. 1 (9th Cir. 1972). The factual findings by the lower court as to what the parties said and did must be accepted unless clearly erroneous. Saturn Oil and Gas Co. v. Northern Natural Gas Co., 359 F.2d 297, 302 (8th Cir. 1966). The principles of contract interpretation to be applied to those facts, however, are legal issues which this court can review. Cf. Restatement (Second) of Contracts, § 228; McClung v. Thompson, 401 F.2d 253, 257-58 (8th Cir. 1968) (interpretation of ambiguity is "a question for the jury, under proper instructions, to resolve").

A threshold question where the parties attached different meanings to an ambiguous clause is whether the parties have made a binding contract on this issue at all. 4 If neither party knows or has reason to know the meaning attached by the other, or if both parties know or have reason to know the meaning attached by the other, then there is no contract. Restatement (Second) of Contracts, § 21A(1). However, if only one party knows or has reason to know of the conflict in meaning, the contract will be interpreted in favor of the party who does not know of the conflict. Restatement (Second) of Contracts, §§ 21A(2), 227(2) and 238. Therefore the crucial factual issue in this case is whether either party knew or had reason to know of the meaning given to the contract by the other. Emor, Inc. v. Cyprus Mines Corp., 467 F.2d 770, 775 (3rd Cir. 1972).

1. Knowledge or Reason to Know of Other's Interpretation.

The district court found that neither side had actual knowledge of the expectation of the other at the time the contract was entered into; but the lower court made no explicit findings with respect to whether either had reason to know of the...

To continue reading

Request your trial
50 cases
  • U.S. v. Manarite
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • March 15, 1995
    ... ... were conspiracy to distribute obscene materials and extortion. Just before he was sentenced for ... ...
  • 82 Hawai'i 226, Brown v. KFC National Management Co.
    • United States
    • Hawaii Supreme Court
    • July 19, 1996
    ... ... KFC manual, handbook, or other written materials shall constitute an implied or expressed contract ... Textile Workers Union v. Lincoln Mills of Alabama, 353 U.S. 448, 466, ... is applicable to disputes such as that before us. The issues raised on appeal--in particular, the ... P.2d 634, 639 (1992) (citing Allis-Chalmers Corp. v. Lueck, 471 U.S. 202, 208, 105 S.Ct. 1904, ... Union Bldg. Materials Corp. v. Haas & Haynie Corp., 577 F.2d ... ...
  • Westlands Water Dist. v. Patterson
    • United States
    • U.S. District Court — Eastern District of California
    • August 9, 1995
    ... ... Waller v. Financial Corp. of Am., 828 F.2d 579, 583 (9th Cir. 1987); ... Union Bldg. Materials Corp. v. Haas & Haynie Corp., ... ...
  • U.S. v. City of Twin Falls, Idaho
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • December 15, 1986
    ... ... Potlatch Corp. v. United States, 679 F.2d 153, 157 (9th ... Union Building ... Page 870 ... Materials Corp. v. Haas & Haynie Corp., 577 F.2d 568, 572 (9th Cir.1978) ... The City also asks us to remand for the district court to make a ... --------------- ... * Honorable Ben ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT