U.S. for Use and Benefit of Williams Elec. Co., Inc. v. Metric Constructors, Inc.

Decision Date20 November 1996
Docket NumberNo. 24551,24551
Citation325 S.C. 129,480 S.E.2d 447
CourtSouth Carolina Supreme Court
PartiesU.S. f/u/b/a WILLIAMS ELECTRIC COMPANY INC., Plaintiff, v. METRIC CONSTRUCTORS, INC., et al., Defendant. . Heard

George Papaioanou, Bert R. Oastler and Charles W. Surasky, all of Smith, Currie & Hancock, Atlanta, and Timothy W. Bouch of Young, Clement, Rivers & Tisdale, Charleston, for plaintiff.

James L. Bruner and Brian P. Robinson of Bruner, Powell & Robbins, Columbia, for defendant.

WALLER, Justice:

The following question has been certified to this Court by the United States District Court for the District of South Carolina:

Under the facts of this case, what exceptions, if any, to an unambiguous no-damages-for-delay clause in a construction contract would the South Carolina Supreme Court recognize?

FACTS

Metric, general contractor for construction of a new federal prison in Estill, S.C., hired Williams Electric Company as the major electrical subcontractor. The contract, written by Metric, contains the following no-damages-for-delay clause:

7. Extensions of Time.... In the event the Subcontractor's performance of this Subcontract is delayed or interfered with by acts or omissions of the Owner, Contractor or other subcontractors, Subcontractor may request an extension of time for the performance of this Subcontract as hereinabove provided, but shall not be entitled to any increase in the subcontract Price or to damages or additional compensation as a consequence of such delays or interference except to the extent that the Contract entitles Contractor to compensation therefor and then only to the extent of any amounts that Contractor, on behalf of Subcontractor, recovers from Owner for such delays or interference.

During construction of the prison, Williams suffered delays caused primarily by Metric's failure to properly coordinate and manage the subcontractors. As a result, Williams incurred more labor and material costs than anticipated and was required to remain on the project for months after its scheduled completion date. Subsequent to completion of the prison, Williams brought this action in the Federal District Court under the Miller Act 1 for additional expenses caused by the delays. Metric answered and sought summary judgment, contending it is not liable by virtue of the no-damages-for-delay clause.

DISCUSSION

Generally, no-damage-for-delay provisions are valid and enforceable so long as they meet ordinary rules governing the validity of contracts. See Annot., Validity and Construction of "No Damage Clause" with Respect to Delay in Building or Construction Contract, 74 A.L.R.3d 187, § 2[a] (1976). A majority of jurisdictions, however, recognize certain exceptions to such clauses. Id. Among the recognized exceptions are (a) delay caused by fraud, misrepresentation, or other bad faith; (b) delay caused by active interference; (c) delay which has extended such an unreasonable length of time that the party delayed would have been justified in abandoning the contract; (d) delay that was not contemplated by the parties; and (e) delay caused by gross negligence.

We premise our discussion by recognizing that, in South Carolina, there exists in every contract an implied obligation of good faith and fair dealing. Adams v. Creel, 320 S.C. 274, 465 S.E.2d 84 (1995); Parker v. Byrd, 309 S.C. 189, 420 S.E.2d 850 (1992); Tharpe v. G.E. Moore, 254 S.C. 196, 174 S.E.2d 397 (1970). Accordingly, to the extent these exceptions give rise to a violation of this obligation, we find them to be a logical extension of South Carolina law. We address the exceptions seriatim.

a. Delay caused by fraud, misrepresentation, or other bad faith.

The most widely recognized exception to the enforceability of a no-damage-for delay clause is fraud, misrepresentation or bad faith. 74 A.L.R.3d at 215-216, § 7(b). Of those cases addressing this exception, it appears to have been adopted in all but one jurisdiction. See Owen Constr. Co. v. Iowa State Dept. of Transp., 274 N.W.2d 304 (Iowa 1979); Jensen Constr. Co. v. Dallas County, 920 S.W.2d 761 (Tex.App.1996); Newberry Square Development Corp. v. Southern Landmark, Inc., 578 So.2d 750 (Fla.1991); J & B Steel Contractors, Inc. v. Iber & Sons, 162 Ill.2d 265, 205 Ill.Dec. 98, 642 N.E.2d 1215 (1994); White Oak Corporation v. Department of Transportation, 217 Conn. 281, 585 A.2d 1199 (Conn.1991); State Highway Admin. v. Greiner, 83 Md.App. 621, 577 A.2d 363 (1990) (all recognizing exception for fraud or bad faith). But see Marsch v. Southern N.E.R. Corp, 230 Mass. 483, 120 N.E. 120 (1918) (declining to adopt fraud exception).

Clearly, fraud, misrepresentation and bad faith in performance of one's contractual duties would give rise to a violation of the implied obligation of good faith and fair dealing. See O'Quinn v. Beach Associates, 272 S.C. 95, 249 S.E.2d 734 (1978) (recognizing that a contract may be avoided on grounds of fraud). Accordingly, we find that adoption of this exception is a logical extension of South Carolina law and join the majority of jurisdictions in adopting this exception.

b. Delay caused by active interference

A majority of courts also adopt an exception to a no-damage-for-delay clause in cases of direct, active, willful interference with the work of the contractor. 74 A.L.R.3d at 219-221, § 7(e). See also Newberry Square Development v. Southern Landmark, supra; Owen Constr. Co. v. Iowa State Dept. of Transp., supra; Green Plumbing & Heating Co. v. Turner Constr. Co., 500 F.Supp. 910 (E.D.Mich.1980) (applying Mich. law); Christiansen Bros., Inc. v. State, 90 Wash.2d 872, 586 P.2d 840 (1978). This Court has recognized that where performance of a contract by the vendor is prevented by the vendee, the vendee may not take advantage of the delay. 2 See Shannon v. Freeman, 117 S.C. 480, 109 S.E. 406 (1921). Such active interference effectually violates the implied obligation of fair dealing. Accordingly, we find this exception to be a logical extension of South Carolina law. 3

c. Unreasonable delay justifying abandonment of the contract

A number of courts recognize an exception to a no-damage clause where delays are so unreasonable in length or duration that they amount to an abandonment of the contract, or would justify the contractor's abandonment. 74 A.L.R.3d at 226-230, § 7(i). Both this Court and the Court of Appeals have recognized that a contract may be abandoned. Quality Concrete Products, Inc. v. Thomason, 253 S.C. 579, 172 S.E.2d 297 (1970); Ro-Lo Enterprises v. Hicks Enterprises, 294 S.C. 111, 362 S.E.2d 888 (Ct.App.1987). An abandonment need not be express but may be inferred from the conduct of the parties and attendant circumstances. Quality Concrete, supra. Abandonment of contract by one party is the giving up of the right to a benefit due from the other party. Ro-Lo, supra. As with the above-mentioned exceptions, an abandonment of the contract involves a breach of the implied obligation of good faith and fair dealing. Accordingly, we adopt this exception and find that if a party abandons the contract, they also abandon their right to rely on a no damage for delay clause.

d. Delays not contemplated by the parties.

The most contested of the exceptions is that for "delay not contemplated by the parties." Under this exception, a number of courts find that a "no damage" provision will not bar claims resulting from delays caused by the contractee if the delays "were not within the contemplation of the parties at the time they entered into the contract." Corinno Civetta Const. v. City of New York, 67 N.Y.2d 297, 502 N.Y.S.2d 681, 686, 493 N.E.2d 905, 910 (1986). The rationale for this exception, as stated by the Corinno Civetta court, is that "[i]t can hardly be presumed ... that the contractor bargained away his right to bring a claim for damages resulting from delays which the parties did not contemplate at the time."

However, this view is not universally accepted and has recently been questioned by a number of courts. See e.g. State Highway Administrator v. Greiner, 83 Md.App. 621, 577 A.2d 363 (1990); Gregory and Son, Inc. v. Guenther and Sons, 147 Wis.2d 298, 432 N.W.2d 584 (1988). These courts hold that a clear, unambiguous clause which precludes a contractor's recovery of damages for "any delays" is binding, notwithstanding uncontemplated delays, absent some allegation of intentional wrongdoing, gross negligence, fraud, ormisrepresentation. Greiner, supra. In Gregory, the Wisconsin Supreme Court stated:

Indeed, the adoption of a no-damage-for-delay clause shows that the parties realize that some delays cannot be contemplated at the time of the drafting of the contract.... The parties can deal with delays they contemplate by adjusting the start and completion dates or by including particular provisions in the contract. "[I]t is the unforeseen events which occasion the broad language of the clause since foreseeable ones could be readily provided for by specific language." City of Houston v. R.F. Ball Constr. Co., Inc., 570 S.W.2d 75, 78 (Tex.Civ.App.1978).

432 N.W.2d at 587.

It has long been the law in this State that when a contract is unambiguous, clear and explicit, it must be construed according to the terms the parties have used, to be taken and used in their plain, ordinary sense. See C.A.N. Enterprises v. S.C. Health and Human Services, 296 S.C. 373, 373 S.E.2d 584 (1988). "A party to a written contract, where there is no ambiguity or indefiniteness in the essentials, cannot say their minds did not meet." Arant v. Mack, 204 S.C. 287, 294, 28 S.E.2d 846, 849 (1944). This Court has routinely refused to engage in re-writing the terms of the parties' contract. See e.g. C.A.N. Enterprises v. S.C. Health and Human Services supra (duty of a court is to enforce contract as written, regardless of the wisdom or folly, apparent unreasonableness, or the parties' failure to guard their rights carefully). We find that it...

To continue reading

Request your trial
23 cases
  • Zachry Constr. Corp. v. Port of Hous. Auth. of Harris Cnty.
    • United States
    • Texas Supreme Court
    • August 29, 2014
    ...Inc. v. Cranston Hous. Auth., No. C.A. 74–2897, 1975 WL 174130, at *2–5 (R.I.Super. Nov. 24, 1975); U.S. v. Metric Constructors, Inc., 325 S.C. 129, 480 S.E.2d 447, 448–451 (1997) ; Thomas & Assoc. v. Metro. Gov't of Nashville, No. M2001–00757–COA–R3–CV, 2003 WL 21302974, at *14 (Tenn.Ct.Ap......
  • Tupelo Redevelopment Agency v. Gray Corp., 2006-CA-00218-SCT.
    • United States
    • Mississippi Supreme Court
    • October 18, 2007
    ...to which the clause applies." Id. (citing Green Int'l, Inc. v. Solis, 951 S.W.2d 384, 387 (Tex.1997); United States v. Metric Constructors, Inc., 325 S.C. 129, 480 S.E.2d 447, 448 (1997); J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc., 162 Ill.2d 265, 205 Ill.Dec. 98, 642 N.E.2d 1215......
  • JA Jones Constr. v. Lehrer McGovern Bovis
    • United States
    • Nevada Supreme Court
    • May 19, 2004
    ...or fraud, and (4) delays caused by the other party's active interference. As the South Carolina Supreme Court recognized in United States v. Metric Constructors, Inc.,5 these exceptions give rise to a violation of the duty of good faith and fair dealing and are therefore a logical extension......
  • C&H Elec., Inc. v. Town of Bethel
    • United States
    • Connecticut Supreme Court
    • August 5, 2014
    ...Inc. v. New York, 58 N.Y.2d 377, 384–85, 448 N.E.2d 413, 461 N.Y.S.2d 746 (1983); United States ex rel. Williams Electric Co. v. Metric Constructors, Inc., 325 S.C. 129, 133–34, 480 S.E.2d 447 (1997); cf. White Oak Corp. v. Dept. of Transportation, supra, at 289, 585 A.2d 1199. Apart from t......
  • Request a trial to view additional results
10 books & journal articles
  • Chapter V Claims Arising Out of Contract or Quasi Contract
    • United States
    • SC Construction Law Desk Book (SCBar)
    • Invalid date
    ...subcontractor is entitled to rely upon contractor's schedule for performance).[62] See Williams Elec. Co. v. Metric Constructors, Inc., 325 S.C. 129, 480 S.E.2d 447 (1997). In practice, the implied duty of good faith and fair dealing is similar to the contractor's implied promise not to pre......
  • C. The Process of Tort Litigation
    • United States
    • The South Carolina Law of Torts (SCBar) Chapter 1 Introduction: the Subject Matter, Policies, and Process of Tort Law
    • Invalid date
    ...cause pending before the federal court. See, e.g., United States for Use and Benefit of Williams Elec. Co., Inc. v. Metric Constr., Inc., 325 S.C. 129, 480 S.E.2d 447 (1997). For discussion of state law and federal law in this context, see R. FELIX & R. WHITTEN, AMERICAN CONFLICTS LAW 328-6......
  • A. Duty and Breach of Duty
    • United States
    • The South Carolina Law of Torts (SCBar) Chapter 2 Negligence and Similar Breaches of Duty
    • Invalid date
    ...and Desirability, 60 NOTRE DAME L. REV. 510 (1985).[320] See, e.g., U.S., f/u/b/a Williams Elec. Co., Inc. v. Metric Constr. Inc., 325 S.C. 129, 133, 480 S.E.2d 447, 448 (1997) ("[T]here exists in every contract an implied obligation of good faith and fair dealing."); Parker v. Byrd, 309 S.......
  • § 19-14 Contract - Breach of Contract - General Defenses
    • United States
    • South Carolina Requests to Charge - Civil (SCBar) Chapter 19 General Contract
    • Invalid date
    ...v. Loris Indus. Dev., Inc., 271 F. Supp. 551 (D.S.C. 1967); U.S. for Use and Benefit of Williams Elec. Co. v. Metric Constructors, Inc., 325 S.C. 129, 480 S.E.2d 447 (1997)(finding that if a party abandons contract, they also abandon their right to rely on "no damage for delay" clause); Qua......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT