U.S. for Use of John D. Ahern Co., Inc. v. J. F. White Contracting Co., 80-1384

Decision Date15 May 1981
Docket NumberNo. 80-1384,80-1384
Citation649 F.2d 29
Parties28 Cont.Cas.Fed. (CCH) 81,395 UNITED STATES of America for Use of JOHN D. AHERN COMPANY, INC., Plaintiff-Appellant, v. J. F. WHITE CONTRACTING COMPANY, The Travelers Indemnity Company, J. L. Caputo Construction Company, Inc., Joseph Caputo and Builders Iron Works, Inc., Joint Venturers, Defendants-Appellees.
CourtU.S. Court of Appeals — First Circuit

Peter J. Gagne, Boston, Mass., with whom Corwin & Corwin, Boston, Mass., was on brief, for plaintiff-appellant.

Kieran B. Meagher, Boston, Mass., with whom Robert D. City and Robert J. Owens Associates, P.C., Boston, Mass., were on brief, for defendants-appellees.

Before COFFIN and CAMPBELL, Circuit Judges, NELSON, * District Judge.

NELSON, District Judge.

Plaintiff, John D. Ahern Co., Inc. ("Ahern") appeals from a district court order dismissing its complaint for failure to meet the ninety day notice requirement of the Miller Act, 40 U.S.C. § 270b(a) (1970). For the reasons stated below, we affirm the district court opinion.

On February 22, 1974 J. F. White Contracting Company ("White") entered into a contract with the Army Corps of Engineers to build the Charles River Dam in Boston, Massachusetts. White, the principal contractor, subcontracted the furnishing and installation of the lock gates to Joseph Caputo and Builders Iron Works, Inc. ("Caputo") on May 10, 1974. Caputo, in turn, subcontracted the sandblasting and painting of the lock gates to Ahern on November 24, 1975. Pursuant to 40 U.S.C. § 270a, White executed a payment bond with its surety, the Traveler's Indemnity Company ("Travelers"), to protect the investment of those supplying labor and materials in connection with the project.

Ahern commenced its work on June 15, 1976. On November 28, 1976, after having completed between 40% and 60% of its subcontracted work, the plaintiff withdrew its people and equipment from the construction site to await further installation of the lock gates by Caputo. All parties agree that the plaintiff performed no work after November 28, 1976. On February 25, 1977, White and Caputo executed an amendment to their subcontract which served to terminate Caputo's subcontract with the plaintiff. Plaintiff received written notice from Caputo of its termination on March 1, 1977.

Plaintiff notified White of its claim for the fair value of the work it had performed on April 27, 1977. This was within ninety days of the termination of its subcontract with Caputo, but some one hundred fifty days after the suspension of its work. Plaintiff subsequently brought suit against White and Caputo to enforce its claim. The defendants moved to dismiss on the ground that plaintiff had not complied with the Miller Act's requirement that written notice of a claim be given to the principal contractor within ninety days of the date on which the claimant "performed the last of the labor." 40 U.S.C. § 270b(a) (1970). The district court granted the motion, ruling that plaintiff had "performed the last of the labor" on November 28, 1976. On appeal, plaintiff advances the single argument that the ninety day period did not commence until the date its subcontract was terminated, and, as a result, its complaint was in fact timely filed.

The Miller Act, 40 U.S.C. § 270b, provides a federal cause of action for persons supplying labor and materials to recover upon a payment bond secured by the principal contractor of a federal government project. In pertinent part, it reads:

any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed.

40 U.S.C. § 270b(a) (1970) (emphasis added). The requirement that notice must be given to the principal contractor within the ninety-day period is mandatory and is a strict condition precedent to the existence of any right of action upon the principal contractor's bond. Fleisher Engineering & Construction Co. v. United States, 311 U.S. 15, 18-19, 61 S.Ct. 81, 83, 85 L.Ed. 12 (1940). The purpose of the notice requirement is to establish a time after which the principal contractor can pay its subcontractor, certain that it will not be exposed subsequently to the claims of those who have supplied labor and materials to the subcontractor. Bowden v. United States, 239 F.2d 572, 577-8 (9th Cir. 1956), cert. denied sub nom. United States ex rel. Malloy v. Bowden, 353 U.S. 957, 77 S.Ct. 864, 1 L.Ed.2d 909 (1956).

Plaintiff offers three separate grounds on which to reverse the district court's decision. First, plaintiff argues that it has no control over the suspension of its work in November. In March, when it was notified of the termination of its subcontract, it was still available to furnish labor and materials to White. Since plaintiff's inability to perform was the direct result of a termination initiated by White, plaintiff urges us to consider the last date it was available to provide labor and material as the date it "performed the last of the labor" for the purpose of determining when the ninety-day notice period commenced. Second, plaintiff states that, until the notice of termination of its subcontract, it had assumed that its work would resume. It argues that a notice of claim under its subcontract when it temporarily withdrew its work force would have been premature and ineffective since, until White terminated the subcontract, the subcontract price was not due before completion of the work. Third, plaintiff asserts that, because its claim for the fair value of the work it performed did not come into existence until the termination of the subcontract, it could not have stated its claim "with substantial accuracy," as required by the statute, prior to that date.

With respect to the plaintiff's first...

To continue reading

Request your trial
25 cases
  • Southern Elec. Health Fund v. Kelley
    • United States
    • U.S. District Court — Middle District of Tennessee
    • September 30, 2003
    ... ... Electric, Defendants, ... John W. Cates Construction Co., Inc., Third Party ... associated with the electrical contracting industry, and working dues payable to IBEW Local ... Rental and Supply Co. ("US Rental"), a company wholly owned by Cates, Inc ... John D. Ahern Co., Inc. v. J.F. White Contr. Co., 649 F.2d 29, ... ...
  • U.S. ex rel. Metric Elec. v. Enviroserve, Inc.
    • United States
    • U.S. District Court — District of Massachusetts
    • November 24, 2003
    ... ...         John P. Connelly, Peabody & Arnold LLP, Boston, MA, ... , Inc., National Union Fire Insurance Co., Pittsburgh, Defendants ... letter and "request[ed] that [Metric] provide us with any information or documentation that you ... Ahern Co., Inc. v. J.F. White Contracting Co., 649 ... ...
  • U.S. for B & R, Inc. v. Donald Lane Const., Civ.A. No. 97-198 MMS.
    • United States
    • U.S. District Court — District of Delaware
    • August 14, 1998
    ... ... "), Commercial Industrial Construction & Supply Co., Inc. ("CICS"), and National Surety Corporation ... John D. Ahern Co., Inc. v. J.F. White Contracting ... ...
  • United States v. Travelers Cas. & Sur. Co. of Am.
    • United States
    • U.S. District Court — Northern District of West Virginia
    • September 23, 2014
    ... ... Liberty Lobby, Inc., 477 U.S. 242, 24748, 106 S.Ct. 2505, 91 ... or implied intentions of the contracting parties, if such can be discerned. Truong Xuan ... John D. Ahern Co., Inc. v. J.F. White Contracting Co., ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT