U.S. Nat. Bank of Portland v. Erickson
Citation | 300 P.2d 449,208 Or. 141 |
Parties | The UNITED STATES NATIONAL BANK OF PORTLAND (Oregon), Respondent, v. R. L. ERICKSON, d/b/a R. L. Erickson Company, Respondent, J. A. Terteling & Sons, Inc., a corporation, and J. H. Wise & Son, Inc., a corporation, Appellants. |
Decision Date | 31 July 1956 |
Court | Supreme Court of Oregon |
Koerner, Young, McColloch & Dezendorf, Portland, and James H. Clarke, Portland, for appellants.
Hugh L. Biggs, Portland, Hart, Spencer, McCulloch, Rockwood & Davies, Cleveland C. Cory, and John E. Huisman, Portland, for respondent, United States Nat. Bank of Portland (Oregon).
The plaintiff The United States National Bank of Portland commenced a suit against the defendants R. L. Erickson, dba R. L. Erickson Company, J. A. Terteling & Sons, Inc., and J. H. Wise & Son, Inc. The trial court at the close of the evidence determined that the matter was triable as an action at law. No objection to the trial court's ruling was made, and all parties waived the right to a jury trial. Findings of fact were made and a judgment entered for the plaintiff against the defendants for the sum of $22,800, together with attorney's fees and costs and disbursements. From this judgment the defendants J. A. Terteling & Sons, Inc., and J. H. Wise & Son, Inc., have appealed. The defendant R. L. Erickson, dba R. L. Erickson Company, has made no appearance in this court.
For the purposes of this opinion we will refer to the defendant R. L. Erickson, dba R. L. Erickson Company, as 'Erickson', and to the defendants J. A. Terteling & Sons, Inc., and J. H. Wise & Son, Inc., as 'defendants.'
The defendants J. A. Terteling & Sons, Inc., and J. H. Wise & Son, Inc., as joint ventures, entered into a contract June 6, 1951, with the United States Government to rehabilitate 229 buildings situated at the Mountain Home Air Force Base, Mountain Home, Idaho. On June 12, 1951, these defendants entered into a 'subcontract agreement' with the defendant R. L. Erickson, dba R. L. Erickson Company, to do the roofing, sheet metal, and felt siding work called for in the original contract.
On June 16, 1951, the date work was commenced on the subcontract, Erickson, being unable to finance the construction work, displayed to the plaintiff his copy of the subcontract agreement and a copy of the prime contract, and asked of the plaintiff a loan for the purpose of obtaining the necessary finances to carry on the subcontract agreement. The loan application was refused by the plaintiff. The testimony of Mr. Prideaux, an officer of the bank, on this point is as follows:
No bond of any kind was given by Erickson to the defendants.
Before approaching the bank, and after receiving the subcontract, Erickson talked with a Mr. Carter, secretary of the defendant J. A. Terteling & Sons, Inc., Erickson's testimony being as follows:
On June 15, 1951, Mr. Carter wrote the following letter to the plaintiff:
'Gentlemen:
'The R. L. Erickson Co. of Portland is negotiating a subcontract with our company and J. H. Wise & Son, Inc., a joint venture, under the U. S. Army contract DA-45-164-eng-1136 at Mountain Home Air Force Base, Mountain Home, Idaho, which subcontract will be for roofing and felt siding.
'I trust this information will be sufficient for you to handle necessary arrangements with the R. L. Erickson Co. as they desire.'
On July 2, 1951, Erickson again made application for a loan from the plaintiff, and at this time presented a progress report and request for payment from the defendants showing he had completed, under his subcontract, work of the value of $38,063.31. The progress report was confirmed as substantially correct by a Mr. Matelich, the project manager for the defendants. On July 6, 1951, the plaintiff loaned Erickson the sum of $22,800 for a period of 30 days, and as of that date by airmail notified the defendants of the loan made and the assignment to the plaintiff of the moneys due Erickson under the progress report, requesting defendants, if there were any irregularities found, to so advise. Plaintiff was never notified of any irregularities.
On or about July 11, 1951, the defendants began advancing Erickson money, which advances continued until Erickson had completed the subcontract.
After several requests had been made by plaintiff of defendants as to why payment was not forthcoming, defendants on November 21, 1951, through Mr. Carter, advised the plaintiff by letter as follows:
'Gentlemen:
'In reply to your letter of November 2 regarding the status of the R. L. Erickson Co. contract with the joint venture of J. H. Wise & Son and our company at Mountain Home, Idaho, I wish to advise that the following steps have been taken in this regard and which I trust will give you the information which you desire.
'In reviewing the history of the subcontract with Mr. Matelich, the following information was furnished:
'That Mr. Matelich had received a phone call from Mr. Pardeau of your bank to substantiate the correctness of an estimate due for work that R. L. Erickson had performed, which was indicated as being substantially correct by Mr. Matelich;
...
To continue reading
Request your trial-
Oregon Farm Bureau v. Thompson
...prayed for its construction and for general equitable relief. The following is taken from United States National Bank of Portland v. Erickson and Terteling & Sons, 208 Or. 141, 300 P.2d 449: 'Objections relating to whether the cause is triable at law or in equity should be made in the trial......
-
Schmeck v. Bogatay
...Or. at 416--417, 100 P. 1103; Marshall v. Wilson, 175 Or. 506, 518, 154 P.2d 547 (1944). See also United States Nat. Bank of Portland v. Erickson et al., 208 Or. 141, 152, 300 P.2d 449 (1956). In this case, however, as previously noted, plaintiffs gave notice by letter dated August 6, 1965,......
-
Transamerica Ins. Co. v. U.S. Nat. Bank of Oregon
...406 P.2d 556, 13 A.L.R.3d 1 (1965); United Finance Co. v. Anderson, 212 Or. 443, 454, 319 P.2d 571 (1958); United States Nat. Bank v. Erickson, 208 Or. 141, 151, 300 P.2d 449 (1956). Defendant cites cases from other jurisdictions in which it has been held that similar agreements protected b......
-
United Finance Co. v. Anderson
...but if it were, having been prepared by plaintiff, it should be construed most favorably to defendants. United States Nat. Bank of Portland v. Erickson, 208 Or. 141, 300 P.2d 449 and Herrold v. Hartley, 144 Or. 368, 24 P.2d In International Finance Corp. v. Philadelphia Wholesale Drug Co., ......