U.S. v. Johnson
Decision Date | 03 August 1994 |
Docket Number | No. 93-55971,93-55971 |
Citation | 43 F.3d 1308 |
Parties | 40 Cont.Cas.Fed. (CCH) P 76,736 UNITED STATES of America, Plaintiff-Appellee, v. Richard W. JOHNSON; Ruth E. Johnson, Defendants-Appellants. |
Court | U.S. Court of Appeals — Ninth Circuit |
Richard W. Johnson and Ruth E. Johnson, in pro per, defendants-appellants.
Michael E. Quinton, Asst. U.S. Atty., San Diego, CA, for plaintiff-appellee.
Appeal from the United States District Court for the Southern District of California.
Before: WALLACE, Chief Judge, HUG, and RYMER, Circuit Judges.
The appellee's request for publication is granted. The memorandum disposition filed August 9, 1994 is redesignated as a per curiam opinion.
Richard W. Johnson appeals pro se the district court's summary judgment for the United States in the government's action seeking specific performance of a purchase option contained in a lease agreement between Johnson and the government. 1 Johnson contends the district court erred because the terms of the purchase option are ambiguous and the district court should have considered parol evidence regarding the ambiguity and related evidence of fraud. We have jurisdiction pursuant to 28 U.S.C. Sec. 1291. We affirm.
We review de novo the district court's summary judgment. United States v. King Features Entertainment, Inc., 843 F.2d 394, 397 (9th Cir.1988). "Viewing the evidence in the light most favorable to the non-moving party, we must determine whether there are any genuine issues of material fact and whether the district court correctly applied the relevant law." Id.
Johnson contends the terms of the purchase option are ambiguous and, therefore, the district court should have considered parol evidence to resolve the ambiguity. This contention lacks merit.
"In interpreting a contract, a court determines the existence of an ambiguity as a matter of law." Bauhinia Corp. v. China Nat'l Mach. & Equip. Import & Export Corp., 819 F.2d 247, 249 (9th Cir.1987). The purchase option contained in the original 1967 lease agreement provided that the government could exercise the option at specified intervals and at specified prices. 2 Under the 1981 lease amendment, Johnson granted the government an option to purchase the property at any time during the remaining term of the lease. This option provided that "[t]he purchase price will be at the fair market value of the premises at the date of the exercise of the option, unencumbered by the Postal Service lease, as determined by Postal Service appraisal."
Johnson argues that an ambiguity exists because the interrelationship of the purchase options in the 1967 lease agreement and 1981 lease amendment is unclear. We disagree.
As Johnson recognizes, " '[a] written contract must be read as a whole and every part interpreted with reference to the whole.' " Kennewick Irrigation Dist. v. United States, 880 F.2d 1018, 1032 (9th Cir.1989) (quoting Shakey's Inc. v. Covalt, 704 F.2d 426, 434 (9th Cir.1983)). The 1981 lease amendment provided in conjunction with the purchase option contained therein that "[t]his option is in addition to any other purchase options available under the lease of this property." Declaration of Michael E. Quinton, Exhibit 5 at 2 (emphasis added). In our view, the plain meaning of this language is that the purchase option in the 1981 lease amendment did not supersede the original purchase option in the 1967 lease, but, rather, was an additional option available to the government. Thus, the government was entitled to exercise either the original purchase option under the terms specified in the 1967 lease agreement or the second purchase option under the terms specified in the 1981 lease amendment. To read these provisions in any other manner would fail to give meaning to the explicit language that the 1981 purchase option was in addition to the government's 1967 purchase option. See Kennewick Irrigation Dist., 880 F.2d at 1032. We therefore conclude that the district court did not err by determining that the purchase-option terms are clear and unambiguous. See Bauhinia Corp., 819 F.2d at 249.
We reject Johnson's contention that the district court should have considered parol evidence to clarify the intent of the parties with regard to the 1981 purchase option. Extrinsic evidence of the parties' intent with regard to language in a contract is admissible only if the language is ambiguous. Arizona Laborers, Teamsters & Cement Masons Local 395 Health & Welfare Trust Fund v. Conquer Cartage Co., 753 F.2d 1512, 1517 (9th Cir.1985). We have already concluded that the purchase-option provisions at issue are not ambiguous.
Johnson contends that the district court erred by not considering evidence that the government fraudulently induced him to enter into the 1967 lease agreement. This contention lacks merit.
Johnson asserts that an unidentified government contracting agent verbally assured him at the time the 1967 lease agreement was entered into that the purchase option was a mere formality and would never be exercised by the government. These oral statements directly contradict the clear, unambiguous, written provision in the 1967 lease agreement giving to the government the right to exercise a purchase option. Thus, the district court did not err by determining that Johnson's evidence was barred by the parol evidence rule. See United States v. Triple A Mach. Shop, Inc., 857 F.2d 579, 585 (9th Cir.1988) ( ).
Johnson also contends that the government should...
To continue reading
Request your trial-
Williams v. Precision Coil, Inc.
...that " '[i]n interpreting a contract, a court determines the existence of an ambiguity as a matter of law.' " United States v. Johnson, 43 F.3d 1308, 1310 (9th Cir.1995), quoting Bauhinia Corp. v. China Nat'l Mach. & Equip. Import & Export Corp., 819 F.2d 247, 249 (9th Cir.1987).Although so......
-
HN Corp. v. Cyprus Kanawha Corp.
...that " '[i]n interpreting a contract, a court determines the existence of an ambiguity as a matter of law.' " United States v. Johnson, 43 F.3d 1308, 1310 (9th Cir.1995), quoting Bauhinia Corp. v. China Nat'l Mach. & Equip. Import & Export Corp., 819 F.2d 247, 249 (9th We note that the de n......
-
San Luis & Delta Mendota Water Auth. v. U.S. Dep't of the Interior
...(9th Cir.1999) (“Whenever possible, the plain language of the contract should be considered first.”); also see United States v. Johnson, 43 F.3d 1308, 1310–11 (9th Cir.1995) (absent an irreconcilable ambiguity in a contract, there is no basis for a court to consider parol evidence to clarif......
-
Rivera v. U.S.A. Dep't of Ed.
...Talley-Bey v. Knebl, 168 F.3d 884, 885 (6th Cir. 1999); Carter v. Stalder, 60 F.3d 238, 239 (5th Cir. 1995); United States v. Johnson, 43 F.3d 1308, 1310 n.1 (9th Cir. 1995); Lewis v. Lenc-Smith Mfg. Co., 784 F.2d 829, 830-31 (7th Cir. 1986); Covington v. Allsbrook, 636 F.2d 63, 63-64 (4th ......