U.S. v. Newport News Shipbuilding and Dry Dock Co.

Decision Date19 January 1988
Docket NumberNo. 87-3832,87-3832
Citation837 F.2d 162
Parties, 34 Cont.Cas.Fed. (CCH) 75,422 UNITED STATES of America, Plaintiff-Appellant, v. NEWPORT NEWS SHIPBUILDING AND DRY DOCK COMPANY, Defendant-Appellee, The Shipbuilders Council of America, Amicus Curiae, The Chamber of Commerce of the United States, Amicus Curiae.
CourtU.S. Court of Appeals — Fourth Circuit

Peter Rolf Maier, U.S. Dept. of Justice (Richard K. Willard, Asst. Atty. Gen., Washington, D.C., Henry E. Hudson, U.S. Atty., Alexandria, Va., Leonard Schaitman, U.S. Dept. of Justice, Washington, D.C., John J. Quill, Kirk Moberley, Defense Contract Audit Agency on brief), for appellant.

John G. DeGooyer (K. Martin Worthy, Maureen Duignan, Theodore A. Howard, Helen Marie Lardner, Hamel & Park, Washington, D.C., Shannon T. Mason, Jr., Mason, Gibson, Cowardin & Martin, Newport News, Va., on brief), Washington, D.C., for appellee.

(Clarence T. Kipps, Jr., Robert K. Huffman, Alan C. Brown, Miller & Chevalier, Chartered, Washington, D.C., W. Patrick Morris, Vice President & Gen. Counsel Shipbuilders Council of America on brief), for amicus curiae Shipbuilders Council of America.

(Herbert L. Fenster, Thomas C. Papson, David M. Eppsteiner, Matthew J. McGrath, McKenna, Conner & Cuneo, Washington, D.C., Robert S. Conrad, National Chamber Litigation Center, Inc. on brief), for amicus curiae The Chamber of Commerce of the U.S. in support of Affirmance.

Before CHAPMAN and WILKINSON, Circuit Judges, and BOYLE, United States District Judge for the Eastern District of North Carolina, sitting by designation.

WILKINSON, Circuit Judge:

This case concerns the scope of the subpoena power of the Defense Contract Audit Agency, which seeks to subpoena the internal audits of Newport News Shipbuilding and Dry Dock Company, a large defense contractor. We hold that the statutory subpoena power of the DCAA extends to cost information related to government contracts, but that the DCAA does not have unlimited power to demand access to all internal corporate materials of companies performing cost-type contracts for the government. Because the materials sought by DCAA are not within the scope of its statutory authority, we affirm the order of the district court denying enforcement of the subpoena in this case.

I.

The DCAA was established by administrative order in 1965 as a separate agency in the Department of Defense. Its function is to assist DOD with audits, primarily of cost-type contracts, during the negotiation, administration, and settlement of the contracts. As a part of the audits, DCAA has the power to subpoena and inspect the books and records of contractors. It is the scope of DCAA's statutory authority to subpoena that is at issue here.

DCAA's subpoena authority is set forth in 10 U.S.C. Sec. 2313(d)(1), which reads:

The Director of the Defense Contract Audit Agency (or any agency) may require by subpoena the production of books, documents, papers or records of a contractor, access to which is provided by subsection (a) or by section 2306(f) of this title.

Sections 2313(a) and 2306(f) provide in relevant part:

Sec. 2313.

(a) An agency named in section 2303 of this title is entitled, through an authorized representative, to inspect the plant and audit the books and records of--

(1) a contractor performing a cost or cost-plus-a-fixed-fee contract made by that agency under this chapter; and

(2) a subcontractor performing any subcontract under a cost or cost-plus-a-fixed-fee contract made by the agency under this chapter.

Sec. 2306.

(f)(5) For the purpose of evaluating the accuracy, completeness, and currency of cost or pricing data required to be submitted by this subsection, any authorized representative of the head of the agency who is an employee of the United States Government shall have the right, until the expiration of three years after final payment under the contract or subcontract, to examine all books, records, documents and other data of the contractor or subcontractor related to the proposal for the contract, the discussions conducted on the proposal, pricing or performance of the contract or subcontract.

It is under these statutes that DCAA issued the subpoena that gave rise to this dispute. 1

Also relevant to this case is the function of the DOD Inspector General. The DOD Inspector General was created in 1982. Congress had previously created Inspectors General in fifteen departments in the Inspector General Act of 1978. In those departments, the investigative and audit functions that had existed in other branches were transferred to the Inspector General. In DOD, however, the DCAA retained auditing and investigative functions, and the establishment of the Inspector General did not change DCAA's authority to obtain the records of contractors. The DOD Inspector General was, however, given broad subpoena powers to investigate waste, fraud, and other abuse, and the authority to set policy for audits and investigations. The Inspector General was also authorized to request help in performing its tasks from the other DOD auditing units such as DCAA. It has been held, and both parties appear to agree, that the Inspector General does have the power to subpoena the internal audits at issue here. See United States v. Westinghouse Electric Corp., 788 F.2d 164 (3d Cir.1986).

II.

Newport News Shipbuilding and Dry Dock Company (NNS) performs shipbuilding and repair, primarily for the United States Navy. Approximately ninety-eight percent of its work is performed for the United States government. Many of NNS's contracts with the government are "cost" or "cost-plus" contracts, in which NNS's compensation is based on its cost or its cost plus a set fee.

NNS has since 1946 had an internal audit department. The nine auditors of the department function as an "independent management control" and conduct periodic reviews of the soundness and efficiency of various NNS departments. As the district court noted, the internal audit department serves NNS's corporate management by evaluating these departments and making recommendations for improving efficiency and safeguarding corporate assets. The auditors perform this function by reviewing employee time cards, subcontractor invoices, vouchers, summary cost records, and other evidence of direct and indirect costs. On completion of an audit, the auditors prepare a final report of their conclusions and recommendations for corporate management.

The internal audits are not conducted with regard to individual contracts, but address department performance over time on a number of projects. The costs of internal audits are charged as "general and administrative" overhead, which is allocated to government contracts in the same way as other overhead charges such as executive salaries. The costs of operating the internal audit department, including employee timesheets and other cost documentation from the department are all made available to the DCAA, which maintains a staff at Newport News Shipbuilding. Prior to this case, however, the DCAA had not sought to gain access to the actual work product of the internal audit department.

Beginning in mid-1984, the DCAA sought access to NNS Internal Audit materials. In October 1986, DCAA served a subpoena duces tecum on NNS pursuant to 10 U.S.C. Sec. 2313(d) demanding:

Schedules of internal audits performed or expected to be accomplished, working papers generated during any audit, written summary reports on the results of audit, followup action taken by NNS in response to internal audit recommendations and any time-charging records of the employees assigned to the audit department for the period 1 January 1986 to present.

NNS refused to surrender the work product of the Internal Audit department, and filed a declaratory judgment action to have the subpoena declared unlawful. The government responded by moving to dismiss the NNS action and by seeking summary enforcement of the subpoena. The district court heard oral argument on March 9, 1987, and requested supplemental filings by the parties. On March 20, the court denied enforcement of the subpoena, holding under Sec. 2306(f) that the Internal Audit materials were not related to the negotiation, pricing or performance of a particular defense contract, and were thus beyond the scope of DCAA's subpoena power. The court stated that the DOD Inspector General was the proper branch through which DOD could get access to the audits. See Newport News Shipbuilding and Dry Dock Co. v. Reed, 655 F.Supp. 1408, 1414-15 (E.D.Va.1987). From this ruling, the government appeals.

III.

Federal courts will enforce an agency subpoena if (1) the inquiry is within the authority of the agency and is for a proper purpose; (2) the matter requested is reasonably relevant to the inquiry; and (3) the demand is not unreasonably burdensome or broad. E.g., United States v. Powell, 379 U.S. 48, 57-58, 85 S.Ct. 248, 254-55, 13 L.Ed.2d 112 (1964). Here, the subpoena is deficient because it exceeds the proper scope of DCAA's statutory authority.

DCAA suggests that it is entitled to the NNS internal audits simply because NNS does ninety-eight percent of its business with the government. Although this argument has a certain common sense appeal, it has no basis in the statutes that govern DCAA's access to corporate documents. This argument contains no apparent limit on the records to which DCAA would have access, and no hint of how this justification for access would be workable in the case of a contractor performing a lesser percentage of government work. We therefore turn to the statutory provisions as the only proper source for DCAA's subpoena authority.

Our review of the relevant statutes leads us to reject the government's assertion that they give DCAA practically unlimited access to NNS's internal corporate records. On the contrary, sections 2313(a) and 2306(f)(5) provide DCAA access to corporate records primarily for...

To continue reading

Request your trial
10 cases
  • In re Grand Jury Investigation of Possible Violations of 18 U.S.C. § 1956 and 50 U.S.C. § 1705
    • United States
    • U.S. District Court — District of Columbia
    • 18 Marzo 2019
    ...may be enforced." United States v. Apodaca , 251 F.Supp.3d 1, 8 (D.D.C. 2017) ; see also United States v. Newport News Shipbuilding & Dry Dock Co. , 837 F.2d 162, 165–66 (4th Cir. 1988) ("Here, the subpoena is deficient because it exceeds the proper scope of DCAA's statutory authority."). Y......
  • Reich v. Great Lakes Indian Fish and Wildlife Com'n
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 9 Diciembre 1993
    ...are ripe for determination at that stage. EEOC v. Cherokee Nation, 871 F.2d 937 (10th Cir.1989); United States v. Newport News Shipbuilding & Dry Dock Co., 837 F.2d 162, 165-66 (4th Cir.1988); EEOC v. Ocean City Police Dept., 820 F.2d 1378 (4th Cir.1987); FTC v. Shaffner, 626 F.2d 32, 36 (7......
  • Bryant v. U.S. Dep't of Educ.
    • United States
    • U.S. District Court — District of South Carolina
    • 5 Octubre 2018
    ...of a federal agency or to seek enforcement of the Inspector General's subpoenas. See, e.g., United States v. Newport News Shipbuilding and Dry Dock, Co., 837 F.2d 162, 165 (4th Cir. 1988) (discussing statutory authorization for audits and subpoena power of the Defense Contract Audit Agency)......
  • Director of OTS v. Ernst & Young
    • United States
    • U.S. District Court — District of Columbia
    • 3 Marzo 1992
    ...that OTS lacks the authority to issue this subpoena, Ernst & Young cites two cases, United States v. Newport News Shipbuilding and Dry Dock Co., 837 F.2d 162 (4th Cir.1988) ("Newport News") and United States v. Frontier Airlines, 563 F.2d 1008 (10th Cir.1977). The court finds that neither c......
  • Request a trial to view additional results
3 firm's commentaries
  • The Cost Corner: Government Contracts Cost and Pricing – DCAA Audits
    • United States
    • LexBlog United States
    • 29 Junio 2023
    ...52.232-32(i). [46] FAR 52.230-2(c). [47] DCAM ¶ 1-504.1.b (Apr. 2023). [48] United States v. Newport News Shipbuilding and Drydock Co., 837 F.2d 162 (4th Cir. 1988). [49] Newport News, 837 F.2d at 164. [50] Newport News, 837 F.2d at 168. [51] Compare 10 U.S.C. § 3841(b) and 41 U.S.C. § 4706......
  • How To Survive A DCAA Audit
    • United States
    • Mondaq United States
    • 17 Julio 2012
    ...DCAA's authority to penalize a contractor for denial of access is further limited by U.S. v. Newport News Shipbuilding & Dry Dock Co., 837 F.2d 162 (4th Cir. 1988) and 862 F.2d 464 (4th Cir. 1988), which held that the DCAA may subpoena the objective data underlying an audit, but not sub......
  • The Cost Corner: Government Contracts Cost And Pricing ' DCAA Audits
    • United States
    • Mondaq United States
    • 4 Julio 2023
    ...FAR 52.232-32(i). 46. FAR 52.230-2(c). 47. DCAM ' 1-504.1.b (Apr. 2023). 48. United States v. Newport News Shipbuilding and Drydock Co., 837 F.2d 162 (4th Cir. 49. Newport News, 837 F.2d at 164. 50. Newport News, 837 F.2d at 168. 51. Compare 10 U.S.C. ' 3841(b) and 41 U.S.C. ' 4706(b) with ......
1 books & journal articles
  • Making sense out of secondary sources in environmental law: a research primer.
    • United States
    • Environmental Law Vol. 25 No. 1, January 1995
    • 1 Enero 1995
    ...opposite to decisions in other areas of the law of privileges. See United States v. Newport News Shipbuilding & Dry Dock Co., 837 F.2d 162, 168-170 (4th Cir. 1988) (defense contractor's internal audit materials were beyond the subpoena powers of the Defense Contract Audit Agency). Furth......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT