U.S. v. W.H. Moseley Co.

Decision Date26 March 1984
Docket NumberNo. 83-1227,83-1227
Parties32 Cont.Cas.Fed. (CCH) 72,685 The UNITED STATES, Appellant, v. W.H. MOSELEY COMPANY, Appellee. Appeal
CourtU.S. Court of Appeals — Federal Circuit

Sara V. Greenberg, Washington, D.C., argued for appellant. With her on the brief were J. Paul McGrath, Asst. Atty. Gen., David M. Cohen, Director and Thomas W. Petersen, Washington, D.C.

John L. Runft, Boise, Idaho, argued for appellee.

Before RICH, BENNETT and SMITH, Circuit Judges.

BENNETT, Circuit Judge.

The government appeals from an order of the Armed Services Board of Contract Appeals (board), No. 27370-18 (Jan. 13, 1983), directing the contracting officer to issue a decision on W.H. Moseley Company's (Moseley) certified claim, pursuant to the authority granted to the board under section 6(c)(4) of the Contract Disputes Act of 1978 (CDA) (codified at 41 U.S.C. Sec. 605(c)(4) (Supp. V 1981)). The government asserts that the board erred in treating Moseley's claim as one arising under the CDA, as an earlier decision by the United States Court of Claims in this case, W.H. Moseley Co. v. United States, 677 F.2d 850, cert. denied, --- U.S. ----, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982), allegedly held that Moseley could not proceed under the CDA after the case was dismissed for lack of proper certification. Moseley asserts that this court does not have jurisdiction over this appeal because it is interlocutory, and, alternatively, the board correctly determined that Moseley could pursue its claim under the CDA and that the government has confused retroactive certification

with resubmission of the claim for a new decision. We hold that we do not have jurisdiction over this appeal, and dismiss on that basis.

BACKGROUND

Moseley, a commodity supplier in Boise, Idaho, suggested certain changes in a procurement contract of January 31, 1978, with the Defense Logistics Agency (agency), to supply it with French fried potatoes. The agency adopted these changes, and Moseley asserted that it was entitled to an award based upon the savings the agency realized from implementation of these changes. Moseley's claim for over $1,000,000 was submitted to the contracting officer, who issued her final decision denying the claim on February 15, 1980. In her final decision, the contracting officer advised Moseley that it could appeal the denial of the claim either under the disputes clause of the contract or under the CDA.

Moseley chose to appeal the decision under the CDA, and brought a "direct action" suit in the Court of Claims on October 9, 1980. See 41 U.S.C. Sec. 609(a)(1) (Supp. V 1981). The government moved to dismiss on the ground that Moseley had failed to certify its claim as required by the CDA, 41 U.S.C. Sec. 605(c)(1). Moseley attempted to cure the jurisdictional defect by retroactively certifying its claim to the contracting officer, but it did not resubmit the certified claim for a new decision.

The Court of Claims dismissed the appeal on the grounds that the certification requirement was a jurisdictional prerequisite and Moseley's attempt to satisfy this requirement retroactively was unavailing. The court stated:

Finally, plaintiff argues that now that it has gone back to the contracting officer and certified the pertinent claim, it should be able to gain direct access to the court. However, Lehman [673 F.2d 352 (Ct.Cl.1982) ] implicitly rejects that argument. The court in Lehman directed the plaintiff to a relevant board of contract appeals, with the right to subsequent judicial review in this court. And, as Lehman concluded, plaintiff cannot be heard to complain about this result since "[a]lthough the plaintiff's trial de novo will be before the Board rather than before this court, that is the consequence of the plaintiff's own default in failing to certify its claim, as the Act requires."

677 F.2d at 852 (footnote omitted).

Following the dismissal of its claim by the Court of Claims, Moseley resubmitted its now certified claim to the contracting officer for the issuance of a new final decision. The contracting officer refused to accept the resubmitted claim, contending that her prior decision was a valid final decision under the disputes clause of the contract. On July 15, 1982, Moseley appealed this refusal to the board, requesting it to direct the contracting officer to issue a decision within a specified time period as authorized by the CDA, 41 U.S.C. Sec. 605(c)(4).

In an order dated January 13, 1983, the board directed the contracting officer to issue a decision on Moseley's certified claim within 30 days. The board noted that none of the Court of Claims cases cited by the parties regarding certification, viz, Paul E. Lehman, Inc. v. United States, 673 F.2d 352 (1982), Moseley, and Skelly & Loy v. United States, 685 F.2d 414 (1982) 1, dealt with the issue before it--namely, whether the board had the authority to direct the contracting officer to issue a new decision on the resubmitted claim. The board largely focused on the prejudicial effect of the contracting officer's advice to Moseley that it could appeal the adverse decision either under the disputes clause or under the CDA. As a result of this erroneous advice the board refused to recognize the contracting officer's earlier decision as a procedurally valid final decision for purposes of appeal. The board therefore granted Moseley's request that it direct the contracting officer to issue a new decision Subsequent to the board's order, the contracting officer still refused to issue a new decision, and in an order dated April 14, 1983, the board treated the contracting officer's failure to issue a new decision as a denial of the claim appealable to the board. See 41 U.S.C. Sec. 605(c)(5). Moseley was thereby authorized to commence its appeal to the board under the CDA.

under the CDA. As previously noted, it is this order which forms the basis of the government's present appeal.

DISCUSSION

At first glance, this appeal clearly appears to be interlocutory, and thus beyond our jurisdiction, as no board or court has yet even reached the merits of Moseley's contract claim. It is well established that this court, as an appellate tribunal, may only review "final decisions." Gould v. Control Laser Corp., 705 F.2d 1340 (Fed.Cir.1983), cert. denied, 52 U.S.L.W. 3336 (Oct. 31, 1983) (No. 83-247); Aleut Tribe v. United States, 702 F.2d 1015 (Fed.Cir.1983); Veach v. Vinyl Improvement Products Co., 700 F.2d 1390 (Fed.Cir.1983); Wagner Shokai, Inc. v. Kabushiki Kaisha Wako, 699 F.2d 1390 (Fed.Cir.1983). See also section 127(a)(10) of the Federal Courts Improvement Act of 1982 (FCIA), Pub.L. No. 97-164, 96 Stat. 25, 38 (to be codified at 28 U.S.C. Sec. 1295(a)(10)), which restricts an appeal to a "final decision" of an agency board of contract appeals. The Supreme Court in Catlin v. United States, 324 U.S. 229, 233, 65 S.Ct. 631, 633, 89 L.Ed. 911 (1945), stated that a "final decision" for purposes of appellate review is one "which ends the litigation on the merits and leaves nothing for the court to do but execute the judgment." (Citation omitted.) See also Firestone Tire & Rubber Co. v. Risjord, 449 U.S. 368, 373-74, 101 S.Ct. 669, 672, 66 L.Ed.2d 571 (1981). Clearly the order appealed from cannot be construed as a final disposition of Moseley's claim. Furthermore, the government concedes that the statutory exceptions for interlocutory appeals, section 125(b) of the FCIA, 96 Stat. 36-37 (to be codified at 28 U.S.C. Secs. 1292(c) & (d)), are inapplicable to this case.

The government, however, presents two novel arguments in support of its position that the board's order in this case is ripe for review: (1) the appeal is not interlocutory, as the CDA contemplates direct appeals from board orders directing a contracting officer's decision under 41 U.S.C. Sec. 605(c)(4); and (2) even if the appeal is interlocutory, this court has jurisdiction under the "collateral order" doctrine. Each of these arguments will be discussed in turn.

DIRECT APPEALS FROM BOARD ORDERS UNDER SECTION 605(c)(4)

According to the government, there exists a right of direct appeal from an order of the board rendered under section 605(c)(4). That section states:

A contractor may request the agency board of contract appeals to direct a contracting officer to issue a decision in a specified period of time, as determined by the board, in the event of undue delay on the part of the contracting officer.

The government asserts that since there is no express limitation in the CDA concerning board decisions that are subject to appellate review, "it is apparent that Congress intended board decisions rendered under both 41 U.S.C. Sec. 605, as in this case, and 41 U.S.C. Sec. 606 [sic, Sec. 607] to be subject to judicial review."

We reject the government's contention that a board's order directing a contracting officer's decision confers a right of direct appellate review. Certainly we reject the notion that the lack of explicit statutory language barring direct review gives rise to the inference that direct review was intended. Read in context, the statutory scheme of the CDA leaves no doubt that Congress did not envision the type of piecemeal review proposed by the government.

Section 605, "Decision by contracting officer," is solely concerned with the requirements and procedures for the submission of a claim and a decision on that claim by Furthermore, the provision of the CDA providing for appellate review of board decisions, section 607(g), clearly contemplates an appeal of a final decision by the board regarding the merits of a claim, and not of a preliminary procedural order by a board pursuant to section 605(c)(4). This court's jurisdiction is not to be derived from implication, as the government would have it here. "In dealing with problems of interpretation and application of federal statutes, we have no power to change deliberate choices of legislative policy that Congress has...

To continue reading

Request your trial
7 cases
  • Dewey Electronics Corp. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • October 1, 1986
    ...28 U.S.C. Sec. 1295(a)(10) (1982) is to review only final decisions of agency boards of contract appeals. United States v. W.H. Moseley Co., 730 F.2d 1472, 1474 (Fed.Cir.1984). The classical doctrine of finality generally requires that the order below "[end] the litigation on the merits and......
  • Fairchild Republic Co. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • January 23, 1987
    ...this court has repeatedly held that, as an appellate tribunal, it may only review "final decisions." See United States v. W.H. Moseley Co., 730 F.2d 1472, 1474 (Fed.Cir.1984), and cases cited therein. The Supreme Court, in Catlin v. United States, 324 U.S. 229, 233, 65 S.Ct. 631, 633, 89 L.......
  • Teledyne Continental Motors, General Products Div. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • July 2, 1990
    ...have jurisdiction under section 1295(a)(10) to review only final decisions of the boards of contract appeals. United States v. W.H. Moseley Co., 730 F.2d 1472, 1474 (Fed.Cir.1984). A final decision is one which " 'ends the litigation on the merits and leaves nothing for the court to do but ......
  • United Pacific Ins. Co. v. Roche
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • June 27, 2002
    ...under 28 U.S.C. § 1295(a)(10) is to review only final decisions of agency boards of contract appeals. United States v. W.H. Moseley Co., 730 F.2d 1472, 1474 (Fed.Cir.1984); see also 28 U.S.C. § 1295(a)(10). A final order is generally one that "`ends the litigation on the merits and leaves n......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT