Ultrawall, Inc. v. Washington Mut. Bank

Decision Date05 June 2001
Docket Number No. 26367., No. 26366
Citation25 P.3d 855,135 Idaho 832
PartiesULTRAWALL, INC., an Idaho corporation; and Scott Trepagnier, Defendants-Counterclaimants-Cross Complaints-Appellants, v. WASHINGTON MUTUAL BANK, FSB, a Federal Association, Defendant-Counterclaimant-Cross Claimant-Respondent.
CourtIdaho Supreme Court

Barry Peters, Eagle, argued for the appellants.

Davison, Copple, Copple, Copple & Ludwig, Boise, for respondent. Terri R. Pickens argued.

WALTERS, Justice.

This is an appeal by Ultrawall, Inc. (Ultrawall) from the district court's grant of summary judgment in favor of Washington Mutual Bank (Washington Mutual). The district court ruled that Washington Mutual's mortgage was entitled to be paid prior to Ultrawall's mechanic's lien in a foreclosure action. We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

This case concerns the lien priority for two construction projects undertaken in the Treasure Valley. Washington Mutual entered into two separate loan agreements with New Concepts Developers, Inc. (New Concepts) whereby Washington Mutual agreed to loan New Concepts funds to construct homes in Boise and Meridian and New Concepts agreed to pay monthly installments on the loans. Washington Mutual secured each of the loans with a deed of trust, one of which was recorded on October 28, 1998, and another that was recorded on November 20, 1998.

Anthony M. Gallegos, who provided engineering and design services for the projects, undertook the earliest known work on the Boise residence on May 8, 1998. Mr. Gallegos also provided the earliest known work for the Meridian residence on October 23, 1998. It is notable that Mr. Gallegos' services took place prior to Washington Mutual recording the deeds of trust in this case.

Ultrawall contracted with New Concepts to provide sheetrocking services for both houses, including the supplying of materials, as well as the installation, taping, and texturing of the sheetrock in connection with each home. Ultrawall performed this work on both houses in early January 1999, after Washington Mutual had recorded the deeds of trust. Washington Mutual made several disbursements to New Concepts under the loan agreement, but ceased doing so when New Concepts stopped making monthly installments. Soon thereafter, numerous claims of lien were recorded against the properties by various laborers and materialmen, including Ultrawall, who were not paid by New Concepts for their services or materials.

On June 14, 1999, Anderson Lumber Company, one of the lien claimants, filed complaints to foreclose mechanic's liens with regard to each residence. The complaints named the developer, New Concepts, the construction lender, Washington Mutual, Ultrawall, and all other lien claimants as defendants. Washington Mutual moved for summary judgment in both cases, asserting that it had priority over all of the various lien holders. Ultrawall filed its answers, counterclaims, and cross-claims seeking a declaratory judgment ranking the priority between itself, Washington Mutual, and the other lien holders. Ultrawall contended that the priority for its lien claims, despite being recorded subsequent to Washington Mutual's deeds of trust, related back to the time when Mr. Gallegos first provided the engineering and surveying services for the construction of the houses. After hearing arguments, the district court granted Washington Mutual's motion for summary judgment, holding that the bank had priority over Ultrawall's lien claims. Ultrawall appeals the district court's ruling.

ISSUES

Ultrawall challenges this Court's holding in Pacific States Sav. & Loan & Bldg. Co. v. Dubois, 11 Idaho 319, 83 P. 513 (1905), that Idaho's mechanic's lien statute gives each lien claimant priority based on the time that the lien claimant began to work on the project. Washington Mutual requests an award of attorney fees for responding to the appeal.

DISCUSSION
A. Pacific States Construction of I.C. § 45-506

In 1905, this Court was faced, for the first time, with the question of whether the liens of laborers, materialmen, and contractors relate back to the time of the commencement of a project by any of the lien claimants, or whether the lien attaches in favor of an individual lien claimant from the date on which that particular claimant began to work on the project by commencing to perform labor or furnish material. See Pacific States, 11 Idaho at 319, 83 P. at 513. The question was posited to the Court in a context identical to this case: although some of the lien claimants began to work on the project before the lender's deed of trust was recorded, many of them did not. In this case, Washington Mutual concedes that if all the liens relate back to the time of the commencement of the project, "irrespective of the time when the labor was commenced to be performed or the material was commenced to be furnished," then every lien claimant would have a superior priority under I.C. § 45-506. The Court in Pacific States, however, held in construing Idaho's mechanic's lien statute that:

"[a]ll liens for labor commenced and materials commenced to be furnished prior to recording [the] mortgages are prior and superior liens to said mortgages, and the liens of all laborers for labor commenced, and materialmen for materials commenced to be furnished, subsequent to the recording of said mortgages, are subordinate to said mortgages ...."

Id. at 325, 83 P. at 514 (emphasis added).

Ultrawall asks the Court to revisit and overrule the Court's Pacific States opinion. Ultrawall asserts that the Court in Pacific States contradicted the terms of the statute by reassembling the statute into separate parts and concluding that the priority of each lien is determined by the category into which the lien claimant fell, be the claimant a laborer, material supplier, or one who commenced the project.

Although Ultrawall's argument has merit, we conclude that the Court's construction of the mechanic's lien statute in Pacific States, while not the only possible construction, should nevertheless be left undisturbed. The Court in Pacific States broke down the first sentence of the statute into three separate parts that the Court believed illustrated the legislature's intent. By separating those claimants who were involved with "the commencement of the erection of the building" from those who "began after the commencement of the erection of the building" the Court drew a distinction between lien claimants that are entitled to date their lien from the commencement of the construction of a project and those claimants who are entitled to date their lien prior to the recordation of a lender's mortgage but after the commencement of the project. The latter claimants, who the Court described as "persons not theretofore connected with the construction of the building," were thus "entitled to a separate and distinct lien from those who commenced the building." Id. at 325, 83 P. at 514.

The current version of I.C. § 45-506 is nearly identical to the statute analyzed by the Court in Pacific States.1 The statute recites:

The liens provided for in this chapter are preferred to any lien, mortgage or other encumbrance, which may have attached subsequent to the time when the building, improvement or structure was commenced, work done, or materials or professional services were commenced to be furnished; also to any lien, mortgage, or other encumbrance of which the lien holder had no notice, and which was unrecorded at the time the building, improvement or structure was commenced, work done, or materials or professional services were commenced to be furnished.

Read in its entirety, the first sentence of I.C. § 45-506 suggests that the lien claimant could be given priority when either the building, improvement or structure was commenced, some entity or individual began to work on the building, improvement or structure, or when the materials or professional services were first furnished. In other words, whichever of these events occurred first would determine the priority for all liens as against a mortgage lien holder. Justice Alshie recognized this in his dissent in Pacific States, noting that:

It takes both labor and material for the construction of a building, and, when the legislature said that liens for constructing a "building, improvement or structure" should be preferred to any lien, mortgage or other encumbrance which might attach subsequent to the commencement of such building, improvement or structure, it certainly meant to allow liens for every kind of labor and every kind of material which go to the erection and completion of such building, improvement, or structure.

Id. at 337, 83 P. at 519.

Ultrawall argues that Justice Alshie's dissent offers a more logical approach to construing the statute. Under Justice Alshie's approach, each of the statutory lien claimants has a priority date that relates back to the date the project was commenced regardless of when the lien claimant's materials or services were provided. Then, if the value of the project is insufficient to pay all the lien claimants, those claimants are paid according to their rank under I.C. § 45-512.2 Thus, either all of the lien claimants are paid ahead of the construction lender, or none are, depending on whether the lender's mortgage was recorded before or after the project began.

There are problems with Ultrawall's proposed approach, however. We first...

To continue reading

Request your trial
10 cases
  • State v. Pina, Docket No. 34192 (Idaho 3/18/2010)
    • United States
    • Idaho Supreme Court
    • March 18, 2010
    ...Elec. Wholesale Supply Co. v. Nielson, 136 Idaho 814, 825, 41 P.3d 242, 253 (2001); see also Ultrawall, Inc. v. Washington Mut. Bank, FSB, 135 Idaho 832, 836, 25 P.3d 855, 859 (2001) ("The Court must assume that when the statute was amended, the legislature had full knowledge of the existin......
  • State v. Pina, Docket No. 34192 (Idaho 7/8/2009)
    • United States
    • Idaho Supreme Court
    • July 8, 2009
    ...Elec. Wholesale Supply Co., Inc. v. Nielson, 136 Idaho 814, 825, 41 P.3d 242, 253 (2001); see also Ultrawall, Inc. v. Washington Mut. Bank, FSB, 135 Idaho 832, 836, 25 P.3d 855, 859 (2001) ("The Court must assume that when the statute was amended, the legislature had full knowledge of the e......
  • State v. McKean
    • United States
    • Idaho Supreme Court
    • August 20, 2015
  • Credit Suisse AG v. Teufel Nursery, Inc.
    • United States
    • Idaho Supreme Court
    • March 19, 2014
    ...improvement or structure, or when the materials or professional services were first furnished." Ultrawall, Inc. v. Washington Mut. Bank, FSB, 135 Idaho 832, 835, 25 P.3d 855, 858 (2001). In sum, "whichever of these events occurred first would determine the priority for all liens as against ......