Unadilla Silo Co., Inc. v. Hess Bros., Inc.

Decision Date28 February 1991
Citation123 N.J. 268,586 A.2d 226
PartiesUNADILLA SILO CO., INC., a New York corporation, in its own name and as Assignee of Eco Bridge, Inc., and/or B & W Contractors, Inc., Plaintiff-Appellant, v. HESS BROTHERS, INC., North American Reinsurance Company, a New York corporation, Fidelity and Deposit Company of Maryland, a Maryland corporation, and Skandia America Reinsurance Company, a Delaware corporation, Defendants-Respondents, and State of New Jersey, Defendant.
CourtNew Jersey Supreme Court

Ronald Reichstein, West Caldwell, for plaintiff-appellant.

Jeffrey M. Garrod, for defendants-respondents (Orloff, Lowenbach, Stifelman & Siegel, attorneys; Jeffrey M. Garrod and Daniel R. Guadalupe, Roseland, on the brief).

Paul P. Mathews, Ringwood, submitted a letter in lieu of brief, on behalf of defendant-respondent Hess Bros., Inc., in defense of Fourth Count of Complaint. (Gennet and Kallmann, attorneys, Roseland).

The opinion of the Court was delivered by

STEIN, J.

The sole issue before us is whether a supplier of specially-fabricated goods is a "subcontractor" on a public-works project pursuant to the New Jersey Bond Act (the Bond Act), N.J.S.A 2A:44-143 to -147, thereby entitling those who supply labor or materials to that supplier to recover under the bond for sums not received.

Hess Brothers, Inc. (Hess), the general contractor on a public construction project, contracted with Eco Bridge, Inc. (Eco) for Eco to supply noise-barrier panels. Unadilla Co., Inc. (Unadilla) fabricated the noise-barrier panels and supplied them to Eco. Hess paid Eco, but Eco failed to pay Unadilla. Unadilla sought recovery under the payment bond, contending that Eco was a "subcontractor" under the Bond Act, entitling Unadilla to payment under the bond as a supplier to a subcontractor. In granting defendants' motion for summary judgment, the trial court concluded that Eco was merely a materialman and not a subcontractor, because it did not perform work at the job site. Consequently, the trial court held that Unadilla, as a supplier of materials to a materialman, could not recover under the payment bond. The Appellate Division affirmed in an unpublished opinion.

We granted Unadilla's petition for certification, 118 N.J. 180, 570 A.2d 950 (1989).

I.

The material facts in this case are undisputed. In February 1983, the State of New Jersey, Department of Transportation (the "State" or "DOT"), entered into an agreement with Hess concerning the construction of an interstate roadway.

Pursuant to the provisions of the Bond Act, N.J.S.A. 2A:44-143 to -147, Hess secured a payment bond from Fidelity and Deposit Company of Maryland, North American Reinsurance Corporation, and Skandia America Reinsurance Corporation (the sureties), for the respective amounts of $8,577,800, $3,509,159, and $3,509,159. The Bond Act requires that the bond obligate the sureties to pay all unpaid claims for labor and materials incurred by the contractor, and all subcontractors, in connection with the work. N.J.S.A. 2A:44-143. The language of the bond was substantially similar to the form set forth in N.J.S.A. 2A:44-147, providing that it was "for the benefit of any subcontractor, materialman, laborer, person, firm, or corporation having a just claim." The sureties' liability would not be triggered unless Hess failed to

pay all lawful claims of subcontractors, materialmen, laborers, persons, firms or corporations, for labor performed or materials, provisions, provender or other supplies, or teams, fuels, oils, implements or machinery furnished, used or consumed in the carrying forward, performing or completing of the agreement.

Pursuant to the terms of the bond, Hess and the sureties were obligated to indemnify the State fully for "all suits and actions of any kind or character."

In February 1984, Hess entered into an agreement to purchase from Eco 81,060 noise-barrier panels and accompanying materials for the price of $580,505. The agreement stated that the materials were to be made in strict accordance with the specifications for the project and other specifications promulgated by DOT. In turn, Eco contracted to purchase the noise-barrier panels from Unadilla. Hess subsequently hired B & W Contractors, Inc. (B & W) to install the noise barriers along the side of the roadway.

DOT's normal practice was to inspect the fabrication and treatment of noise-barrier panels. Because of Unadilla's qualifications and membership in the American Institute of Timber Construction (AITC), DOT agreed to waive the inspection requirement if Unadilla filed a certificate of compliance with DOT specifications.

Moreover, DOT's regulations then provided that when a general contractor sought to "sublet" work with a contract value of $25,000 or more, that "proposed subcontractor" had to be "properly classified" in accordance with N.J.A.C. 16:44-1.1 to -1.7. See N.J.A.C. 16:33-1.1(c) (repealed by R. 1989, d. 505). Specifically, the general contractor must furnish a statement to DOT concerning the subcontractor's "financial ability, adequacy of plant and equipment, organization and prior experience, and such other pertinent and material facts as may be desirable." N.J.A.C. 16:44-1.2(a). DOT did not require Hess to furnish such a statement regarding either Unadilla or Eco.

Pursuant to its agreement with Eco and the project specifications, Unadilla fabricated glue-laminated panels for the sound wall. The panels were custom made to fit the contours of the ground along the highway, each panel consisting of at least three layers of one- or two-inch random-width lumber. Unadilla glued the individual layers into panels approximately twenty-two to twenty-three inches wide. The layers were staggered so that the exterior layers overlapped the interior layers. In addition, reinforcing boards had to be glued horizontally at the ends of all three-ply panels. Cross bands were added to panels over fifteen feet high. Because the work required a substantial amount of routing and planing on the panels, Unadilla purchased a machine at a cost of $35,000 for that purpose, which it allegedly used for work only on that job. After the panels had been glued, Unadilla shipped them to Sherburne, New York, for preservative treatment.

The treated panels were then either delivered to or picked up by Eco, who assembled the twenty-two to twenty-three-inch panels into sections eight-feet wide by mechanically attaching the panels to each other and adding laminated wooden posts to each end of the sections. Eco then delivered the panels to the job site in New Jersey. At no time did either Eco or Unadilla perform work on the job site.

In February 1984, Eco and Hess executed a Release of Liens, in which Eco released Hess from liens associated with the materials provided. Under its contract with Hess, DOT required the release of liens before it would pay Hess for the materials. Eco sent Hess a letter dated April 9, 1984, acknowledging Eco's indebtedness to Unadilla for the noise-barrier panels. The letter further specified that Eco was solely responsible for satisfying that indebtedness and that Hess was not contractually obligated to Unadilla.

On April 10, 1984, without verifying that Unadilla had been paid, Hess paid a total of $492,872 for the noise-barrier panels, paying $315,478 to Eco and $177,392 to Lincoln First Bank, Eco's assignee. The remainder of the $580,505 purchase price was never paid. Eco subsequently became insolvent and failed to pay Unadilla.

The noise-barrier panels had been stored at the job site awaiting installation, but B & W never installed them. In June 1984, the noise-barrier panels were destroyed by fire; thereafter, Hess secured new noise-barrier panels elsewhere.

In May 1985, B & W and Eco assigned to Unadilla any claims they had against Hess, in the approximate amount of $100,000.

Unadilla duly filed notices of claims against the State and the sureties under the Bond Act, see N.J.S.A. 2A:44-145, and notices of liens against the State under the Municipal Mechanics' Lien Law. See N.J.S.A. 2A:44-132. In December 1987, Unadilla filed a complaint against Hess, the sureties, and the State for monies due for the labor and materials furnished in connection with the manufacture of the noise-barrier panels. Unadilla alleged that the State was contractually liable; that Hess and the sureties were liable under the payment bond to Unadilla directly, and as assignee of Eco and B & W; that Hess and the State were liable under the Municipal Mechanics' Lien Law to Unadilla directly, and as assignee of Eco and B & W; and demanded an accounting concerning Hess's dealings with Eco and B & W and judgment on any amounts found to be due under the accounting.

The State moved for summary judgment, arguing that the Bond Act obligated Hess and the sureties to indemnify the State. The trial court granted the State's motion, which Unadilla did not oppose. Subsequently, Hess and the sureties moved for summary judgment. The motion was supported by references to a deposition of John F. Van Cott, president of Unadilla, in which Van Cott stated that he considered both Unadilla and Eco to be materialmen. The trial court dismissed all counts arising out of the assignments from Eco and B & W, because Eco had released Hess from all liens and Unadilla conceded that Hess owed B & W no money. Relying on Morris County Industrial Park v. Thomas Nicol Co., 35 N.J. 522, 173 A.2d 414 (1961), and West Bank Oil v. Hartford Accident and Indemnity Co., 205 N.J.Super. 56, 500 A.2d 32 (App.Div.1985), the trial court also dismissed the remaining counts. It held that because neither Unadilla nor Eco had performed work at the job site, Unadilla was a supplier to a materialman, and as such not entitled to protection under the Bond Act, N.J.S.A. 2A:44-143 to -147. Unadilla appealed, and the Appellate Division affirmed substantially on the basis of the Law Division's opinion.

II.
A....

To continue reading

Request your trial
6 cases
1 books & journal articles
  • Chapter 5 - § 5.4 WHO CAN BRING MILLER ACT CLAIMS
    • United States
    • Colorado Bar Association Liens and Claims in Colorado (2022 ed.) (CBA) Chapter 5 The Miller Act
    • Invalid date
    ...avoid possible issues arising down the road. --------Notes:[30] 40 U.S.C. § 3131(b)(1). [31] Unadilla Silo Co., Inc. v. Hess Bros., Inc., 586 A.2d 226, 233 (N.J. 1991).[32] Id.[33] Faerber Elec. Co. v. Atlanta Tri-Com, Inc., 795 F. Supp. 240, 243 (N.D. Ill. 1992).[34] United States ex rel. ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT