Unicon Management Corp. v. City of Chicago
Decision Date | 20 December 1968 |
Docket Number | No. 16831.,16831. |
Citation | 404 F.2d 627 |
Parties | UNICON MANAGEMENT CORP., Plaintiff-Appellee, v. CITY OF CHICAGO, Defendant-Appellant. |
Court | U.S. Court of Appeals — Seventh Circuit |
Raymond F. Simon, Brendan Q. O'Brien, Chicago, Ill., for defendant-appellant.
Herbert Morton, Richard A. Greig, John O. Snook, Chicago, Ill., for plaintiff-appellee.
Before SWYGERT, FAIRCHILD and CUMMINGS, Circuit Judges.
This is an interlocutory appeal taken under Section 1292(b) of the Judicial Code (28 U.S.C. § 1292(b)) from the district court's denial of a motion to dismiss the complaint, filed by the defendant City of Chicago. This diversity action was brought by Unicon Management Corp., formerly the Malan Construction Corp., a New York corporation, to recover damages assertedly caused by the City's delays in approving wall panels and doors for the Eastern Airlines hangar built by Unicon at O'Hare International Airport in Chicago.
In April 1960, Unicon and the City executed a contract for the construction of this hangar for $3,794,000. The contract required Unicon to complete its work by May 16, 1961. The complaint alleged that the City notified Unicon to proceed with its work even though the essential site work and grading had not yet been completed. The complaint also charged that the City failed to approve wall panels for the hangar for 10 months and doors for 4 months.1 Count I claimed that these delays caused Unicon to incur $525,000 in additional costs and expenses in the performance of its contract work. Count II is a quantum meruit claim for the same amount. The complaint labeled the City's failure to approve these items promptly as "arbitrary, capricious, and unjustified procrastination."
The City's motion to dismiss relied on Section GC120 of the contract as relieving it of any liability for these delays. That Section provides:
The district court construed this provision as exonerating the City from liability only for unavoidable delays. The court was influenced by the introductory clause of GC120 and considered the body of the Section to be too ambiguous to immunize the City from paying damages for any delays. The motion to dismiss was denied on the ground that under GC120, Unicon did not waive its right to damages for delay. In view of the Illinois cases construing similar contractual language, we are compelled to disagree with this disposition.
In our view, this case is controlled by Herlihy Mid-Continent Co. v. Sanitary District, 390 Ill. 160, 60 N.E.2d 882 (1945). Article 30 of the contract between Herlihy and the Sanitary District was the forerunner of Section GC120 of the instant contract. Although Article 30 was entitled "Unavoidable Delays," the Illinois Supreme Court held that the title was "a mere recital and can not be construed as limiting or controlling matters covered by clearly expressed stipulations" (390 Ill. at p. 165, 60 N.E.2d at p. 885). Similarly here, the introductory clause of GC120 must be disregarded in view of the unlimited title and the subsequent language of paragraph 1 of GC120 referring to "any act or delay of the City."
Moreover, since, as the trial judge realized, the term "unavoidable" in the first paragraph of GC120 is used to mean unavoidable by the contractor itself, it is immaterial whether the delay could have been avoided by the City or a third party. The word "unavoidable" is used to describe certain contingencies and not others. Thus, war, riot, insurrection and acts of God are grounds for extension of time without regard to whether they could somehow have been avoided. Delays in transportation, on the other hand, or delays in obtaining materials due to government priorities or controls will excuse timely performance only if the contractor could not have avoided the delay. The final proviso of paragraph 1 of GC120 requires that as a prerequisite to relief from the deadlines, the "Purchasing Agent shall determine that any of such causes or delays were entirely beyond the control of the Contractor." This same meaning must be applied to the word "unavoidable" in the introductory paragraph lest the interpretation of the word in the introduction render the use of the...
To continue reading
Request your trial-
Chicago College of Osteopathic Medicine v. George A. Fuller Co.
...this interpretation of the delay provision yields a fair result, Illinois case law is to the contrary. Unicon Management Corp. v. City of Chicago, 404 F.2d 627 (7th Cir.1968) (Illinois law applied); 2 Herlihy Mid-Continent Co. v. Sanitary Dist., 390 Ill. 160, 60 N.E.2d 882 (1945); Undergrou......
-
A Kan. Corp.. v. Mohawk Constr.
...may arise.” Underground Constr. Co. v. Sanitary Dist. of Chicago, 367 Ill. 360, 11 N.E.2d 361 (1937); See also Unicon Management Corp. v. Chicago, 404 F.2d 627, 631 (7th Cir.1968). It is clear from the terms of the contract that Supplemental Condition 12.5 protects Lake Forest from damages ......
-
Gust K. Newberg, Inc. v. Illinois State Toll Highway Authority
...(1937), 367 Ill. 360, 371 ('the parties themselves have provided' the answer to delay-damages claim); Unicon Management Corp. v. City of Chicago (7th Cir.1968), 404 F.2d 627, 631 ('The City bargained for the right to delay * * *')." 109 Ill.2d 225, 231, 93 Ill.Dec. 369, 486 N.E.2d As stated......
-
Bates & Rogers Const. Corp. v. Greeley & Hansen
...360, 371, 11 N.E.2d 361 ("the parties themselves have provided" the answer to the delay-damages claim); Unicon Management Corp. v. City of Chicago (7th Cir.1968), 404 F.2d 627, 631 ("The City bargained for the right to delay * * * "). This holding is consistent with the decisions of other c......