Union Elec. Co. v. EPA
Decision Date | 16 March 1978 |
Docket Number | No. 78-164C(A).,78-164C(A). |
Citation | 450 F. Supp. 805 |
Parties | UNION ELECTRIC COMPANY, a Missouri Corporation, Plaintiff, v. ENVIRONMENTAL PROTECTION AGENCY, an agency of the United States of America, Defendant. |
Court | U.S. District Court — Eastern District of Missouri |
William H. Ferrell, Schlafly, Griesedieck, Ferrell & Toft, St. Louis, Mo., for plaintiff.
Joseph B. Moore, Asst. U. S. Atty., St. Louis, Mo., for defendant.
The plaintiff, Union Electric Company (hereinafter referred to as UE), has filed a complaint seeking a declaratory judgment and a preliminary injunction and permanent injunction with respect to enforcement proceedings by Environmental Protection Agency (hereinafter referred to as EPA) with regard to emission standards for sulphur dioxide (hereinafter referred to as SO2) and opacity under the Clean Air Act, 42 U.S.C. § 7401 et seq. Plaintiff's prayer seeks equitable relief, a stay of any enforcement proceedings by EPA only so long as UE is actively and in good faith pursuing revisions and/or variance of the applicable regulations contained in the Missouri Implementation Plan before administrative agencies and/or courts of the State of Missouri. Plaintiff seeks no relief beyond the time at which its request for revisions are finally resolved by the administrative agencies and/or courts of the State of Missouri. Plaintiff does not ask the Court to determine the merits of its requests for revisions or the applicability of the Implementation Plan to its present operations.
This matter is before the Court on plaintiff's motion for a preliminary injunction.
The jurisdiction of this Court exists pursuant to 28 U.S.C. § 1331(a) inasmuch as this is an action brought against EPA, an agency of the United States.
There is no dispute between the parties with respect to the facts presented. The pleadings, briefs of the parties, testimony and exhibits before the Court, and prior history, disclose that the plaintiff is an electric utility company serving the metropolitan St. Louis area and parts of Illinois and Iowa. Its three coal-fired generating plants, Labadie, Meramec and Sioux, are subject to the SO2 and opacity restrictions in the Missouri Implementation Plan as approved by EPA.
UE did not seek review of the Administrator's approval of the plan on May 31, 1972, 40 CFR 52.1320, within thirty days, as it was entitled to do under Section 307(b)(1) of the Act, 42 U.S.C. § 1857h-5(b)(1), but rather applied to the appropriate state and county agencies for variances from the emission limitations affecting its three plants. UE received a one-year variance for each of the plants which could be extended upon reapplication. The variances on two of the three plants had expired and plaintiff was applying for extensions when on May 31, 1974, the Administrator notified the plaintiff that SO2 emissions from its plants violated the emission limitations contained in the Missouri Implementation Plan.
On August 18, 1974, UE brought suit against the EPA in the United States Court of Appeals for the Eighth Circuit, contending that they should not have to comply with SO2 emission regulations because of economic reasons and because their SO2 emissions were not interfering with attainment or maintenance of the National Ambient Air Quality Standards (NAAQS) for SO2. Therein, UE contended that a claim or economic or technological infeasibility may be considered upon a petition for review of approval by the Administrator of a state implementation plan. In Union Electric Co. v. EPA, 515 F.2d 206 (8th Cir. 1975), the Court held that questions of economic and technological feasibility do not constitute grounds for review and that the court is without jurisdiction to consider the claim raised by UE in its petition for review. On October 6, 1975, the Supreme Court in UE v. EPA, 427 U.S. 246, 265-67, 96 S.Ct. 2518, 2529, 49 L.Ed.2d 474 (1976) held:
In February, 1975, while the case of UE v. EPA was in the Eighth Circuit Court of Appeals, the U. S. Environmental Protection Agency filed a report titled "Implementation Plan Review as required by the Energy Supply and Environmental Coordination Act (Plff's Ex. 2). On page 4 of the report the EPA had this to say in part:
The report continues on page 5:
"There are currently no indications that SO2 emissions from power plants in the Missouri portion of the St. Louis area are causing violations of SO2 air quality standards."
The Supreme Court handed down its decision in UE v. EPA on June 25, 1976. UE filed a motion for rehearing. On July 22, 1976, following the Supreme Court's decision, Jerome H. Svore, Regional Administrator for EPA, wrote a letter to the Chairman of the Missouri Air Quality Commission (Plff's Ex. 3), which stated in part as follows:
To continue reading
Request your trial-
United States v. West Penn Power Co.
... ... 2. West Penn operates the Mitchell Power Station, a fossil fired electric generating facility located in Courtney, Union Township, Washington County, Pennsylvania ... 3. The station consists of three generating units. Two of these units (Nos. 1 and 2) ... ...
- Union Elec. Co. v. E.P.A., 78-1357