UNITED STATES, ETC. v. Guy H. James Construction Co.
| Decision Date | 05 September 1972 |
| Docket Number | Civ. A. No. 504. |
| Citation | UNITED STATES, ETC. v. Guy H. James Construction Co., 390 F.Supp. 1193 (M.D. Tenn. 1972) |
| Parties | UNITED STATES of America for the Use of E & R CONSTRUCTION CO., INC., Plaintiff, v. GUY H. JAMES CONSTRUCTION CO. and Federal Insurance Company, Defendants. |
| Court | U.S. District Court — Middle District of Tennessee |
COPYRIGHT MATERIAL OMITTED
COPYRIGHT MATERIAL OMITTED
COPYRIGHT MATERIAL OMITTED
COPYRIGHT MATERIAL OMITTED
John K. Maddin, Jr., Nashville, Tenn., Edward Gallagher, Washington, D. C., for plaintiff.
J. Olin White, Nashville, Tenn., Thomas R. Brett, Tulsa, Okl., C. J. Watts, Oklahoma City, Okl., for defendants.
This action was commenced on September 28, 1967, by plaintiffE & R Construction Co., Inc. based upon the provisions of the Miller Act, 40 U.S.C. §§ 270aand270b.The plaintiff is an Ohio corporation.Defendant, Guy H. James Construction Company, is an Oklahoma corporation, and defendantFederal Insurance Company is a New Jersey corporation which is authorized by the United States to write performance and payment bonds under the terms of the Miller Act.
On June 26, 1964, defendantGuy H. James Construction Company(hereinafter "James") entered into a prime contract with the United States Corps of Engineers providing for the construction of a project in Tennessee known as Cordell Hull Lock and Dam, consisting of a lock and dam on the Cumberland River, including items applicable to this action as follows:
The James contract was a successor to earlier contracts held by other parties for the initial excavation and construction of a cellular cofferdam in the dam area, and for road construction and site preparation, and preceded a subsequent contract for the completion of the dam and for construction of the powerhouse.
James, as principal, and Federal Insurance Company(hereinafter "Federal"), as surety, executed to the United States separate bonds, each in a penalty sum of $2,500,000, with performance bond conditioned for faithful performance of the contract, and payment bond conditioned for payment of all labor and material used in prosecution of the contract work.
On July 1, 1964, E & R Construction Company(hereinafter "E & R") entered into a subcontract with James for what may be described generally as the execution of the earth-moving or dirt excavation items under the prime contract.(A copy of the subcontract is included in the Appendix to this Opinion.)
The position of the prime contract undertaken by plaintiff can be more particularly described as follows:
Item Estimated Unit
No. Description Quantity Price Amount
--------------------------------------------------------------------
1 Mobilization &
Preparatory Work Lump Sum $ 17,900
2 Lock Cofferdam 100,000 c.y. 0.64 64,000
5 Clearing & Grubbing Lump Sum 11,000
6 Common Excavation 1,480,000 c.y. 0.64 947,200
15 Filter Drainage Layer 5,200 c.y. 5.28 27,456
16a Compacted Impervious Fill 86,000 c.y. 0.14 12,040
17 Random Fill 103,000 c.y. 0.08 8,240
18 Coarse Rock Fill 8,100 c.y. 2.00 16,200
19 Fine Rock Fill 2,000 c.y. 2.00 4,000
20 12-inch Concrete Pipe 200 l.f. 4.00 1,040
21 15-inch Concrete Pipe 240 l.f. 5.00 1,200
22 Bedding for Riprap 7,500 c.y. 5.28 39,000
23 Riprap 24,500 c.y. 1.50 36,750
__________
$1,187,2661The cofferdam system which was utilized on the project was referred to as being in four parts: the "upstream" 480 dike, meaning an elevation of 480 feet; the "downstream" 480 dike; the downstream 456 dike (sometimes referred to as the 460 dike); and the cross-dike.The terms "upstream" and "downstream" are used in relation to a cellular cofferdam that had been constructed under a preceding contract.Stage I of the project refers to the upstream portion of the work; Stage II refers to the downstream portion of the work.2The removal of the 456 and 480 dikes, which was accomplished during the latter part of the work, is sometimes referred to as Stage III.
During the first part of the job E & R was responsible for the removal or excavation of the overburden on the rock underlying the Stage I area and the construction of the 480 dike; during the second part of the job E & R was responsible for the excavation or removal of the overburden on the rock underlying the Stage II area and the construction of the 456 dike; during the final part of the job E & R was responsible for the general maintenance of the dike system, and the eventual removal of the 456 dike, the 480 dikes, and the cross-dike.
The excavation or removal operations by E & R were planned as a use of certain mobile equipment and a dredge that E & R had purchased for this purpose.Stage I excavation was primarily completed with automotive-type earth-moving equipment, although towards the end of this stage a dredge was used to assist in the disposal of Stage I material.Stage II excavation, although begun at higher elevations with automotive-type equipment, was primarily a dredging operation.Stage III, the removal of cofferdams and dikes, was also primarily done by dredge.Stage II was begun before Stage I was completed, but there was a substantial time interval between the completion of Stage II and the commencement of Stage III.
This action is based on twelve separate claims or "items."Plaintiff claims James materially breached the parties' contract and that plaintiff is entitled to recover in quantum meruit, or, in the alternative, entitled to recover for the damages incurred.
Defendants maintain that several items, i.e., Items (b), (c), (e), (f), (g), (h), (j), and (l) of No. 7 of plaintiff's amended complaint were asserted as claims against defendants for the first time in the amended complaint, filed on September 22, 1971, and they are barred by the one-year statute of limitations, 40 U.S.C. § 270b.Therefore, the threshold question for the court's determination is whether the alleged new claims asserted by plaintiff in the amended complaint are barred by the one-year statute of limitations provision in 40 U.S.C. § 270b which provides, in part:
"(b) . . . no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied . . . ."
Defendants contend that in the original complaint filed in this action on September 28, 1967, plaintiff was proceeding on a theory of breach of contract and sought damages therefor.On September 22, 1971, plaintiff filed a motion to amend the complaint and specifically referred to seeking damages and recovery against the defendants for several items of claim on the basis of quantum meruit in addition to breach of contract.The court did not receive any pleadings in opposition to the plaintiff's motion to amend, and an order granting said motion was entered October 6, 1971.At trial defendants asserted as a defense that the claims based on a theory of quantum meruit were new and consequently time-barred under the Miller Act's one-year statute of limitations.
The court finds that the original complaint in this case covered all the items mentioned in the amended complaint.The amended complaint uses different language in part and is more specific.Additionally, the court finds that the original complaint contained the essential elements of a suit in quantum meruit.The court finds no substantive differences between the allegations in the original complaint and those in the amended complaint.In the original complaint jurisdiction is based on the Miller Act and specifically included are claims in reference to: refusal to pay for work performed, material change in plan of construction of cofferdam, unreasonable interference with performance of subcontract work by placing of shot rock, change in filter drainage material, failure to supply riprap bedding, material, and filter drainage material, change in location of access road, failure to supply coarse rock fill and other rock materials, interference with subcontractor's use of dredge, and failure to pay for additional excavation.
All items growing out of this same contract were mentioned in the original complaint, breach of contract based on interference was claimed, and relief was sought on the basis of work performed but not paid for, all of which can be interpreted as a claim based on quantum meruit.The court finds that the allegations of the original complaint contained the essential elements of a suit in quantum meruit.
The court finds the facts and claims asserted in the amended complaint are not barred by the one-year statute of limitations, but instead they fall within the scope of Rule 15(c) of the Federal Rules of Civil Procedure, which provides:
"Whenever the claim or defense asserted in the amended pleading arose out of the conduct, transaction, or occurrence set forth or attempted to be set forth in the original pleading, the amendment relates back to the date of the original pleading. . . ."(Emphasis supplied.)28 U.S.C.,Fed.R.Civ.P. 15(c).3
Defendants contend...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Wilson v. Volkswagen of America, Inc.
...9 L.Ed.2d 68 (1962); Julius Kayser & Co. v. Textron, Incorporated (4th Cir. 1956) 228 F.2d 783-90; United States, etc. v. Guy H. James Construction Co. (M.D.Tenn.1972) 390 F.Supp. 1193, 1209, aff'd. 6 Cir., 489 F.2d 756 (Table). In James, the Court said:" * * * Existence of usage or custom ......
-
Waste Servs. of Decatur, LLC v. Decatur Cnty.
...are strictly construed under Tennessee law, and "nothing passes by implication." U.S. for Use of E. & R. Const. Co., Inc. v. Guy H. James Const. Co. , 390 F.Supp. 1193, 1206 (M.D. Tenn. 1972) (citing Volunteer Elec. Co-op. v. T.V.A. , 139 F.Supp. 22 (E.D. Tenn. 1954) ).Waste Services' readi......
-
United States v. Hirani Eng'g & Land Surveying, P.C.
...bond even though the equipment may be idle at times during the period of the lease." See U.S. ex rel. E & R Const. Co. v. Guy H. James Const. Co. , 390 F.Supp. 1193, 1245 (M.D. Tenn. 1972). These cases are not on point, however, because ACC seeks not rental value, but the standby costs of i......
-
Military & Fed. Constr. Co. v. Ace Elec., Inc.
...based on . . . delays are not within the legislative intent of [the Miller Act]." United States f/u/o E & R Constr. Co. v. Guy H. James Constr. Co., 390 F. Supp. 1193, 1244 (M.D. Tenn. 1972).3 Although the Fourth Circuit has not addressed this question, more persuasive case law suggests tha......
-
Changes
...Inc. v. City of New York, 215 N.E.2d 490 (N.Y. Ct. App. 1966). 43. See U.S. ex rel. E. & R. Constr. Co. v. Guy H. James Constr. Co., 390 F. Supp. 1193 (M.D. Tenn. 1972), aff’d , 489 F.2d 756 (6th Cir. 1974). 44. A.H.A. General Constr., 699 N.E.2d at 368. 45. Id . 46. See PYCA Indus., Inc. v......
-
Changes
...Inc. v. City of New York, 215 N.E.2d 490 (N.Y. Ct. App. 1966). 43. See U.S. ex rel. E. & R. Constr. Co. v. Guy H. James Constr. Co., 390 F. Supp. 1193 (M.D. Tenn. 1972), aff’d , 489 F.2d 756 (6th Cir. 1974). 44. A.H.A. General Constr., 699 N.E.2d at 368. 45. Id . 46. See PYCA Indus., Inc. v......
-
Table of Cases
...Equal Rights Center v. Archstone Smith Trust, 603 F. Supp. 2d 814 (D. Md. 2009), 155–156 n.16 E. & R. Constr. Co., U.S. ex rel., v. Guy H. James Constr. Co., 390 F. Supp. 1193 (M.D. Tenn. 1972), aff’d, 489 F.2d 756 (6th Cir. 1974), 437 n.43 Erie Railroad Co. v. Tompkins, 304 U.S. 64 (1938),......
-
Changes
...1998); Joseph F. Egan, Inc. v. City of New York, 215 N.E.2d 490 (N.Y. Ct. App. 1966). 43. See U.S. ex rel. E. & R. Constr. Co. v. Guy H. James Constr. Co., 390 F. Supp. 1193 (M.D. Tenn. 1972), aff’d , 489 F.2d 756 (6th Cir. 1974). 44. A.H.A. General Constr. , 699 N.E.2d at 368. 45. Id . 46.......