United States Plywood Corp. v. Continental Cas. Co.

Decision Date12 January 1960
Docket NumberNo. 2434.,2434.
Citation157 A.2d 286
PartiesUNITED STATES PLYWOOD CORPORATION, a corporation, Appellant, v. CONTNENTAL CASUALTY COMPANY, a corporation Appellee.
CourtD.C. Court of Appeals

Philip Shinberg, Washington, D. C., for appellant.

Walter M. King, Jr., Washington, D. C., for appellee.

Before ROVER, Chief Judge, and HOOD and QUINN, Associate Judges.

ROVER, Chief Judge.

In October of 1956, Cannon Construction Corporation and Eugene Simpson & Brother, general contractors, entered into contracts with the school board of Fairfax County, Virginia, for the construction of additions to two of its schools. Continental Casualty Company, the defendant, was the surety on the labor and material payment bonds executed by both of the contractors. The present suit was brought by plaintiff against the surety to recover the unpaid sum of $2,304 for building materials sold and delivered to Collins Millwork Company for use in the performance of its subcontract with Simpson and Cannon the general contractors on the two projects.

Judgment was entered in favor of the defendant surety and the only question raised in this appeal concerns a provision common to both bonds which reads in part:

"3. No suit or action shall be commenced hereunder by any claimant,

"(a) Unless claimant shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant * * furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished * * *."

Plaintiff concedes that notice was not given until 32 days after the expiration of the 90-day period, but contends that the trial court erred in ruling that these provisions were "conditions precedent with which plaintiff was required to comply."

These claims arise out of contracts executed and performed in Virginia. Under the laws of that state, a contractor is required to enter into a bond with a surety on public works contracts in excess of $2500. Code of Virginia 1950, § 11-23 (1956 Replacement Volume).1 Of this statute the Supreme Court of Appeals of Virginia has said:

"* * * the intent of the statute is to protect those who furnish supplies, material and labor in and about the construction of the public buildings and improvements mentioned in the act, whether they be furnished to the principal contractor or to a subcontractor; of this a general contractor and his surety must take cognizance. * * *"2

The court in that case further added that § 11-23 is remedial in character and should be liberally construed in favor of the materialmen and subcontractors for whose protection it was enacted.

The previous statement essentially reflects the argument advanced here by the plaintiff. It contends that inasmuch as the bond was executed for its benefit, an tinequity would result if the surety were permitted to escape liability on a technicality. Plaintiff's position is not without some support. The courts of several states have held that the failure to give notice or a delay in giving notice will discharge the surety only to the extent of the losses it may have incurred by reason of the creditor's action; it will not operate as a total discharge of the surety.3 In so ruling, these courts have chosen to construe the notice provision of a suretyship contract as a promise not going to the essence of the contract rather than as a condition precedent to a right of action. This conclusion is reached by the application of a rule of construction and frequently it is erroneously employed for no other reason than to prevent one in the business of insuring risks from avoiding liability. The rule that the obligation is to be construed against the surety and in favor of the beneficiaries of the bond is one of construction only. In the absence of ambiguity it should not be invoked to circumvent the plain language and intent of the contracting parties.4

A suretyship contract is basically a promise by the surety to the owner of the building that the debts of the contractor will be paid. The extent of the surety's undertaking is measured by the terms of the bond and the statute requiring its execution.5 The creditor is not a party to the contract, but he is a donee of the promise and by the agreement and the statute he acquires a direct right of action against the surety. Since the foundation of any rights of the donee or creditor is the promisor's contract, it follows that his rights are restricted by the terms of the promise and any conditions, express or implied, affecting them.6 A stipulation for notice of default is a condition of liability which may always be imposed.7 The weight of authority holds that where the notice provision is reasonable and is stated as a condition precedent to the right of instituting legal action, failure to observe it will discharge the surety.8 This proposition has the approval of at least two noted authors on the subject.9

The bond in the present case is of a standard type in use. Section 3(a) of the bond, quoted in full earlier, which provides that no action may be brought by a claimant until notice is given is prefaced by the following:

"Now, Therefore, The Condition Of The Obligation is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions * * *."

It is manifest from the instrument itself that the notice of default is a condition precedent to a right of...

To continue reading

Request your trial
7 cases
  • Perez v. C.R. Calderon Constr., Inc.
    • United States
    • U.S. District Court — District of Columbia
    • 22 Diciembre 2016
    ...of the bond.’ " A–J Marine, Inc. v. Corfu Contractors, Inc., 810 F.Supp.2d 168, 188 (D.D.C. 2011) (quoting U.S. Plywood Corp. v. Cont'l Cas. Co., 157 A.2d 286, 288 (D.C.1960) ); Revere Copper & Brass, Inc. v. Overseas Private Inv. Corp., 628 F.2d 81, 82–83 (D.C. Cir. 1980) (noting rule of c......
  • Conesco Industries, Ltd. v. Conforti and Eisele, Inc., D. C.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 17 Abril 1980
    ...the notice provision controls the rights of the parties and favored the strict doctrine as enunciated in U. S. Plywood Corp. v. Continental Cas. Co., 157 A.2d 286 (D.C.Mun.App.1960), a case decided on Virginia law. We are of the general opinion that it is not the function of the courts to r......
  • Dow-Par, Inc. v. Lee Corp., DOW-PA
    • United States
    • Indiana Appellate Court
    • 12 Diciembre 1994
    ...be disregarded or nullified by construction." 17 Am.Jur.2d Contractor's Bond Section 70 (1990); United States Plywood v. Continental Casualty (1960), D.C.Mun.App., 157 A.2d 286, 288. It is undisputed that during the course of the project, Lee paid $208,480.00 to CDI and also incurred additi......
  • GOLDBERG. MARCHESANO v. OLD REPUBLIC
    • United States
    • D.C. Court of Appeals
    • 25 Marzo 1999
    ...of ambiguity it should not be invoked to circumvent the plain language of the contracting parties. United States Plywood Corp. v. Continental Casualty Co., 157 A.2d 286, 288 (D.C.1960). 2. While granting a stay without a supersedeas bond is within the discretion of the judge, the exercise o......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT