United States v. Berkley Reg'l Ins. Co.

Decision Date05 December 2013
Docket NumberCivil Action No. ELH–12–02228.
Citation986 F.Supp.2d 660
PartiesUNITED STATES of America f/b/o Eastern Waterproofing & Restoration Co., Inc., Plaintiff, v. BERKLEY REGIONAL INSURANCE CO., Defendant.
CourtU.S. District Court — District of Maryland

OPINION TEXT STARTS HERE

Christopher A. Taggi, Asmar Schor and McKenna PLLC, Washington, DC, for Plaintiff.

Herman Martin Braude, Braude and Margulies PC, Washington, DC, for Defendant.

MEMORANDUM OPINION

ELLEN LIPTON HOLLANDER, District Judge.

G–W Management Services, LLC (“G–W”), as prime contractor, entered into a contract (“Prime Contract”) with the United States of America (the Government) for a renovation project at the Walter Reed National Military Medical Center in Bethesda (the “Project”).1 Use Plaintiff Eastern Waterproofing & Restoration Company, Inc. (“EWR”) served as a subcontractor on the Project. See Subcontract, Compl. Ex. 1 (ECF 1–2). In accordance with the Miller Act, 40 U.S.C. § 3131 et seq., G–W secured a payment bond, identified as OMB No. 9000–0045, from Defendant Berkley Regional Insurance Company (Berkley). See Bond, Compl. Ex. 6 (ECF 1–7).

The Government subsequently cancelled a portion of the Project and G–W agreed to reduce the price of the Prime Contract. However, G–W and EWR were unable to agree upon the amount by which to reduce the price of the Subcontract. After G–W and Berkley refused to pay EWR the amount of money EWR sought, EWR filed suit under the Miller Act against Berkley for the amount it claimed it was owed by G–W. Complaint, ECF 1.2 G–W is not a party to this action.

On March 21, 2013, Berkley filed a Motion for Summary Judgment (“Motion,” ECF 16), supported by a Memorandum (“Memo,” ECF 16–1) and exhibits. EWR filed an Opposition (“Opp.,” ECF 17), and Berkley filed a Reply (ECF 19). No hearing is necessary to resolve the Motion. See Local Rule 105.6. For the reasons that follow, I will deny the Motion.

Factual Summary

G–W, the prime contractor, entered into Contract no. N40080–10–D0498–0009 with the Government for the Project.3 As noted, pursuant to the Miller Act, 40 U.S.C. § 3131 et seq., G–W secured a payment bond from Berkley. The bond provides protection to subcontractors who provide labor and material in connection with the Project.

EWR was a subcontractor to G–W on the Project under Subcontract 10–009–01, which was executed on February 2, 2011. EWR was initially tasked with the renovation and reconstruction of two parking garages, referred to as Building 54 and Building 55 (“Garage Renovation”). See Subcontract at 1. The Subcontract was a fixed price contract; G–W agreed to pay EWR $1,394,843.00 for its work. Id. According to EWR, G–W later issued change orders that increased the price of the Subcontract to $3,008,074.75. See Demand Letter, Compl. Ex. 5 (ECF 1–6) at 2; but see Reply at 5 n. 3 (stating that G–W disputes that the total price of the Subcontract was $3,008,074.75).

On September 30, 2011, the Government and G–W executed a modification of the Prime Contract, which reduced the scope of the Garage Renovation by deleting portions of the planned work on Building 54 and all of the planned work on Building 55 (the “Modification Agreement”). See Compl. Ex. 4 (ECF 1–5) at 2. For the reductions in work on Building 54, G–W and the Government agreed to reduce the Prime Contract price by $133,429. Id. For the deletion of work on Building 55, G–W and the Government agreed to reduce the Prime Contract price by $1,126,325. Id. The Modification Agreement also established an “accelerated construction schedule” for the remaining work on Building 54, and the Government agreed to pay G–W an extra $316,810 for compliance with that schedule. In all, the Modification Agreement reduced the price of the Prime Contract by $942,944.

EWR was not involved in the negotiations between G–W and the Government regarding these price modifications, nor was it given the opportunity to consent or object to the Modification Agreement. See Demand Letter at 1. Nevertheless, G–W sought to adjust the Subcontract to account for the change in scope of the work.

The Subcontract contained three provisions that allowed G–W either to modify or to terminate the Subcontract if the Government changed the scope of the Project. See Subcontract ¶¶ 14, 15, 25. The first, titled “Extra Work,” provides, id. ¶ 14:

The Contractor may at any time direct the Subcontractor to perform extra work or changes under this Subcontract. Only extra work authorized by the Contactor as an extra or change in writing shall be paid for by the Contractor. If the extra work direction does not originate from Owner's direction and there is no prior agreement on price, then Subcontractor shall be paid for the actual direct costs of said work plus fifteen percent....

The second, titled “Owner Changes,” provides, id. ¶ 15:

Changes ordered by the [Government] shall be performed and paid for in accordance with the terms of the Prime Contract.... [P]ayment for Owner changes shall not be due the Subcontractor as a specific condition precedent until the Contractor [receives payment from the Government].

The third, titled “Termination for Convenience,” provides, id. ¶ 27:

Contractor shall have the right to terminate this Agreement for its own convenience for any reason by giving notice of termination effective upon receipt thereof by Subcontractor.... Settlement with the Subcontractor shall be accomplished in accordance with the provisions of the Termination for Convenience clause in the Prime Contract. If the Termination for Convenience clause in the Prime Contract is not applicable, the Subcontractor shall only be paid either the actual cost for work and labor in place, plus fifteen percent (15%), or a pro rata percentage of the Subcontract amount equal to the percentage of completion for the Subcontractor's work as approved by the Contractor, whichever is less. Subcontractor shall not be entitled to anticipated profits on unperformed portions of the work.

Prior to August 30, 2011, G–W appears to have notified EWR as to the change in scope. See Demand Letter at 1. However, the record does not reflect the nature of that communication or the Subcontract provision on which G–W relied to adjust the Subcontract.

In any event, G–W and EWR agreed that the Modification Agreement reduced the amount of work EWR was to perform, and thus reduced the price of the Subcontract between G–W and EWR. However, they disagreed about the manner in which that reduction should be calculated. Although G–W's methodology is not entirely apparent from the record, it is clear that G–W issued two “Change Orders” that, in total, reduced by $975,968 the sum owed to EWR. See Change Order 11, Compl. Ex. 2 (ECF 1–3); Change Order 15, Compl. Ex. 3 (ECF 1–4). In EWR's view, “the proper measure of the deductive change order is the amount it ‘would have cost’ EWR to perform the deleted work.” Demand Letter at 1 (citation omitted). According to EWR, the cost to perform the deleted work would have been $504,450.72.4 Demand Letter at 1. Thus, EWR maintained that it was entitled to the total subcontract price of $3,008,074.75, less $504,450.72, for a total amount of $2,503,624.03. EWR provided this calculation to G–W on August 30, 2011. See Demand Letter at 1.

The parties agree that G–W has already paid EWR the sum of $1,993,974. EWR, believing itself to be entitled to a total payment of $2,503,624.03, demanded payment from G–W for the difference of $509,649.65. See Demand Letter. G–W has not paid EWR the demanded sum. Compl. ¶ 34. EWR also sent its Demand Letter to Berkley, which also refused to pay the demanded sum. Compl. ¶ 49.

On July 7, 2012, EWR, in the name of the United States, filed suit against Berkley under the Miller Act, alleging that Berkley has “breached its obligations to EWR under the Bond by failing to pay the balance due pursuant under [sic] the Subcontract.” Compl. ¶ 49. The parties engaged in discovery and proceeded toward trial to resolve the question of how properly to calculate the reduction in the subcontract price. See Joint Status Report, ECF 14 (noting that neither party intended to file a dispositive pretrial motion).

On March 19, 2013, EWR sent to G–W its job cost records for the Garage Renovation. Those records reflect that EWR expended a total of $1,339,140.94 for its equipment, material, labor, subcontract, and “other” costs on the Garage Renovation. Memo Ex. B (ECF 16–3). The report was attached to an email from counsel for EWR, which explained, Opp. Ex. 1 (ECF 17–1): “Please note that this only reflects EWR's direct out-of-pocket costs. It does [sic] include G & A costs,5 which are subject to an audited rate of 13.9%. With G & A added in, the grand total comes to $1,525,281.53.”

Two days later, Berkley moved for summary judgment, claiming the Miller Act does not permit EWR to recover from Berkley any amount in excess of EWR's actual costs on the Garage Renovation, and that because EWR's costs have already been met, Berkley is entitled to summary judgment.

Additional facts will be included in the Discussion.6

Standard of Review

Summary judgment is governed by Rule 56 of the Federal Rules of Civil Procedure. It provides, in part: “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a); see Celotex Corp. v. Catrett, 477 U.S. 317, 322–24, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). A fact is “material” if it “might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

The non-moving party must demonstrate that there are disputes of material fact so as to preclude the award of summary judgment as a matter of law. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). The Supreme Court has clarified that this does not mean that any...

To continue reading

Request your trial
5 cases
  • United States v. Leebcor Servs.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • August 18, 2022
    ...base contract work and approved change orders for non-remedial tasks. See United States ex rel. E. Waterproofing & Restoration Co. v. Berkley Reg'l Ins. Co., 986 F. Supp. 2d 660, 665 (D. Md. 2013) (explaining that if "a subcontractor fully performs its contractual obligations, but the prime......
  • Level Heating & Air Conditioning Co. v. Patriot Constr.
    • United States
    • U.S. District Court — District of Maryland
    • December 7, 2021
    ...on the payment bond for the amount unpaid” at that time. 40 U.S.C. § 3133(b)(1); see also United States v. Berkley Reg'l Ins. Co., 986 F.Supp.2d 660, 661 (D. Md. 2013). Its purpose is to “protect[] those who furnish labor or material for substantial federal public works contracts” by “provi......
  • United States v. Leebcor Servs.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • January 12, 2022
    ...the cost of labor, materials, and overhead.'" United States ex rel. E. Waterproofing & Restoration Co. v. Berkley Reg'l Ins. Co., 986 F.Supp.2d 660 (D. Md. 2013) (quoting United States ex rel. Woodington Elec. Co., v. United Pac. Ins. Co., 545 F.2d 1381, 1383 (4th Cir. 1976)). However, "whe......
  • Maguire-O'hara Constr., Inc. v. Cool Roofing Sys., Case No. 5:19-cv-705-R
    • United States
    • U.S. District Court — Western District of Oklahoma
    • September 28, 2020
    ..."Two lines of cases governing a subcontractor's recovery from a Miller Act surety are of import here." United States v. Berkley Regional Ins. Co., 986 F. Supp. 2d 660, 665 (D. Md. 2013). One arises when a contractor breaches its contract with a subcontractor. In that event, the Miller Act o......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT