United States v. Callahan Walker Const Co

Decision Date09 November 1942
Docket NumberNo. 65,65
Citation87 L.Ed. 49,63 S.Ct. 113,317 U.S. 56
PartiesUNITED STATES v. CALLAHAN WALKER CONST. CO
CourtU.S. Supreme Court

See 317 U.S. 710, 63 mS.Ct. 203, 87 L.Ed. —-.

Messrs. Francis Biddle, Atty. Gen., and Richard S. Salant, of Washington, D.C., for petitioner.

Mr. Robert A. Littleton, of Washington, D.C., for respondent.

ROBERTS, Justice.

This case involves the meaning and application of the terms of a standard form of Government construction contract.

The findings of the Court of Claims may be summarized. In 1931 the War Department asked bids for the construction of a levee on the east side of the Mississippi River. The respondent bid 14.43¢ a cubic yard on a section of the work involving approximately 3,881,600 cubic yards of earthwork. A paragraph of the specifications reserved the right to make such changes in the work contemplated as might be necessary or expedient to carry out the intent of the contract or to meet unanticipated conditions, but added that no such modification would be the basis for a claim for extra compensation except as provided in the regular form of contract to be entered into between the parties.

The respondent began construction at the south end of the project and proceeded northward. The length of the proposed levee was divided by stations one hundred feet apart and numbered from north to south. Sixty-eight per cent. of the construction between Station 5123 and Station 5113 had been completed when portions of the levee already constructed south of Station 5123 were found to have a tendency to subside. For this reason the Government contracting officer, on October 7, 1932, ordered the work stopped between the two stations while he sought to determine the cause of the subsidence. He concluded that the placing of an enlarged false berm, not called for in the original specifications, would prevent subsidence in the sector between the two stations. On October 18th he gave respondent a written order to construct such a berm; the order stated that respondent would be given one hundred per cent. credit for the earth placed south of Station 5123 where the subsidence had occurred and that payment for additional yardage required by the false berm would be made at the contract price per cubic yard. The additional yardage involved was about 64,000 cubic yards. The work covered by the change order was necessary for the completion of the project. The order was issued against the respondent's protest that an extra price should be allowed as the additional work would cost the respondent more than 14.43¢ per cubic yard, and that the order was not within the terms of the contract. The respondent asserted it would later present a claim for extra cost occasioned it by the additional work.

Article 3 of the standard form of construction contract signed by the parties provides:

'Article 3. Changes.—The contracting officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause an increase or decrease in the amount due under this contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified in writing accordingly. * * * Any claim for adjustment under this article must be asserted within ten days from the date the change is ordered, unless the contracting officer shall for proper cause extend such time, and if the parties can not agree upon the adjustment the dispute shall be determined as provided in Article 15 hereof. But nothing provided in this article shall excuse the contractor from proceeding with the prosecution of the work so changed.'

Article 15 provides:

'Article 15. Disputes. Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days to the head of the department concerned, whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed.'

The respondent did not appeal from the order of the contracting officer to the head of the department concerned. After completion of the work, the acceptance of the...

To continue reading

Request your trial
120 cases
  • Crown Coat Front Co v. United States
    • United States
    • U.S. Supreme Court
    • April 10, 1967
    ...66 S.Ct. 1003. See also United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039 and United States v. Callahan Walker Co., 317 U.S. 56, 61, 63 S.Ct. 113, 115, 87 L.Ed. 49, where the disputes clause procedures are described as the 'only avenue for relief.' 2. Even when the contractu......
  • Tobin Quarries v. Central Nebraska Public P. & I. Dist., Civil Action No. 57.
    • United States
    • U.S. District Court — District of Nebraska
    • January 8, 1946
    ...86 Ct. Cl. 665; Callahan Construction Co. v. United States, 91 Ct. Cl. 538. And see discussion in United States v. Callahan Walker Construction Co., 317 U.S. 56, 63 S.Ct. 113, 87 L.Ed. 49, though there the issue was clearly one of The court is satisfied, after a comprehensive study of the a......
  • Fett Roofing & Sheet Metal Co. v. Seaboard Surety Co.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • October 10, 1968
    ...to matters arising under the contract. United States v. Blair, supra, 321 U.S. 735, 64 S.Ct. 823; United States v. Callahan Walker Const. Co., 317 U.S. 56, 61, 63 S.Ct. 113, 115, 87 L.Ed. 49. And in the absence of some clear evidence that the appeal procedure is inadequate or unavailable, t......
  • Edwin J. Dobson, Jr., Inc. v. Rutgers, State University
    • United States
    • New Jersey Superior Court
    • January 12, 1978
    ...in the amount due under the contract or in the amount of time allowed for performance. See United States v. Callahan Walker Constr. Co., 317 U.S. 56, 58, 63 S.Ct. 113, 114, 87 L.Ed. 49, 51 (1942). In that case the contract is "equitably adjusted" and the contractor recompensed for additiona......
  • Request a trial to view additional results
1 books & journal articles
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • April 1, 2021
    ...notes 28–35. 66. See, e.g ., United States v. Joseph A. Holpuch Co., 328 U.S. 234 (1946); United States v. Callahan Walker Constr. Co., 317 U.S. 56 (1942); Ripley v. United States, 223 U.S. 695 (1912); United States v. Gleason, 175 U.S. 588 (1900). 67. Gleason , 175 U.S. at 602. 68. United ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT