United States v. Dickinson

Decision Date04 January 1946
Docket NumberNo. 5419,5420.,5419
Citation152 F.2d 865
PartiesUNITED STATES v. DICKINSON. SAME v. WITHROW.
CourtU.S. Court of Appeals — Fourth Circuit

Roger P. Marquis, Atty., Department of Justice, of Washington, D. C. (J. Edward Williams, Acting Head, Lands Division, Department of Justice, of Washington, D. C., and Leslie E. Given, U. S. Atty., of Charleston, W. Va., on the brief), for appellant.

Ernest K. James, of Charleston, W. Va., for appellees.

Before SOPER, Circuit Judge, and COLEMAN and BARKSDALE, District Judges.

SOPER, Circuit Judge.

These appeals were taken by the United States from judgments against it in two suits brought by landowners under the Tucker Act, 28 U.S.C.A. § 41 (20), to recover compensation for the taking of their lands and for the erosion and intermittent flooding thereof caused by raising the water level of the Kanawha River in South Charleston, West Virginia, by the erection and operation of the Winfield Lock and Dam.

Dickinson's land consisted of a tract 3.1 acres in extent which bounded on the low-water mark of the river for a distance of 411 feet. Dickinson acquired the land on August 16, 1937, and between that date and September 22, 1938, which the court found to be the date of the taking, he made substantial improvements thereon in the form of grading and filling, construction of sewers, water and gas lines, the installation of a gasoline filling station and the erection of a large residence near the top of the river bank. By reason of raising the level of the river and the operation of the dam 0.22 acre of land was permanently submerged and 0.10 acre thereof lying between the elevation of 566 feet and 574 feet above mean sea level will be subject to intermittent flooding. The court found that on September 22, 1938, the 0.22 acre permanently flooded had a fair market value of $400 and the flowage easement to flood intermittently the 0.10 acre a fair market value of $75.

The court also found that during the latter raises in the stage of the river, and after the attainment of the present permanent level of 566 feet, considerable erosion of the residue of the plaintiff's property at the river bank occurred which was caused by the saturation and softening of the soil and the wave action thereon that resulted from the permanent flooding of the 0.22 acre of the plaintiff's land. For the damages caused by this erosion the District Judge allowed the property owner the sum of $4,245.63 on the theory that for this sum appropriate protective work along the river bank to prevent the erosion, consisting of a rock toe wall and stone riprapping up to an elevation of 569 feet, could have been installed.

Withrow's property is a tract of land, containing a number of city lots, and fronting on the river approximately 180 feet. The District Court found that 0.11 acre thereof was permanently submerged and 0.04 acre will be subject to intermittent flooding as the result of the raising of the level of the river and the operation of the dam. The court found that the land was taken on September 22, 1938, and that then the fair market value of the land permanently submerged was $200 and the fair market value of the flowage easement to flood intermittently the 0.04 acre was $35.

The court also found that, during the latter stages in the rise of the river and after the attainment of the permanent pool stage of 566 feet above mean sea level, considerable erosion to the residue of the property at the river bank was caused by the saturation and softening of the soil and the wave action thereon which was the direct and proximate result of the taking of the 0.11 acre permanently flooded. For the damages caused by the erosion the court allowed the sum of $1,859.40 on the theory that for this sum of money the owner could have erected a rock toe wall and stone riprapping to an elevation of 569 feet above sea level which would have protected the property from erosion.

The first important contention raised by the United States is that both suits were barred by limitations under the Tucker Act because they were not instituted until the month of April, 1943, the complaint of Dickinson on April 1 and the complaint of Withrow on April 10, more than six years after the rights of action accrued. The decision of this question depends upon the date upon which the taking of the plaintiffs' properties occurred and for this purpose it is necessary to consider the several steps which took place leading to the construction and completion of the dam and the raising of the river from time to time as the pool was filled. The improvement of the river to support a 9 foot channel by substituting four new locks and dams for those previously in place was authorized by the Acts of July 3, 1930, 46 Stat. 918, 928, and August 30, 1935, 49 Stat. 1028, 1035. The Winfield Lock and Dam was constructed under the authority of these Acts, and on July 1, 1936, notice was given to the holders of War Department permits in the area that the water elevation would be raised, and shrubbery and vegetation along the river banks were cut by the government. By October 21, 1936, construction of the dam had proceeded far enough to raise the elevation in the pool of a previous dam downstream from the plaintiffs' properties which, however, were not affected thereby. Subsequently the river was raised by the operation of the Winfield Dam at the plaintiffs' properties by gradual stages from a previous elevation of 554.65 to the present elevation of 566 feet above mean sea level, namely, on May 30, 1937, to 556 feet; on October 20, 1937, to 558 feet; on January 6, 1938, to 563.15 feet; on August 26, 1938 to 565 feet; on September 1, 1938, to 565.5 feet and on September 22, 1938, to 566 feet. The dam was officially inspected and accepted by the federal government on August 20, 1937.

The District Judge held that the cause of action in each case accrued on September 22, 1938, when the pool was filled and the river was finally raised to the contemplated new level of 566 feet, an increase of 11.35 feet over the former normal level, whereby the lands of the plaintiffs were permanently submerged as above described. Under this holding the suits of the plaintiffs instituted in April, 1943, were not barred by limitations. The United States, however, contends that the taking occurred and the right of action accrued on October 21, 1936, before the lands of the plaintiffs were actually invaded, but when the construction of the dam had proceeded far enough to raise the level of the pool downstream below the lands of the plaintiffs. Alternatively the government suggests that the taking occurred on May 30, 1937, when the level of the river opposite the plaintiffs' lands was first raised by the operation of the dam from 554.65 to 566 feet and plaintiffs' lands were first partially submerged. It will be observed that if the earlier date is accepted as correct, the pending suits were barred; but if the later date is accepted, the pending suits were brought in due time. In either event it is important to fix the precise date because it is said that the cases at bar were selected as tests to determine the legal principles to be applied in similar suits now pending in the District Court.

It is conceded by both parties that although the use of the lands by the United States was continuous, only one cause of action accrued; and this position is sustained by the decisions which hold that when a permanent structure erected by government authority results in the invasion of or damage to land, only one right of action arises and this accrues upon the completion of the structure and the happening of the injury, and in this action, all damages, past, present and prospective are recoverable. Suehr v. Chicago Sanitary District, 242 Ill. 496, 90 N.E. 197; Carpenter v. Lancaster, 212 Pa. 581, 61 A. 1113; King v. Board of Council of City of Danville, 128 Ky. 321, 107 S.W. 1189; 4 Sutherland on Damages, 4 Ed., § 1039; 1 Am.Jur., Actions, § 117.

The contention of the United States that the pending suits are barred by limitations rests primarily upon the decisions of the Court of Claims in County Court of Marion County, W. Va., v. United States, 53 Ct. Cl. 120, and Dooner et al. v. United States, 95 Ct. Cl. 392. In the first of these cases it was suggested that it might be said that the statute of limitations begins to run in cases of this kind when the dam is completed and put in operation, or when the first damage is suffered, or at some subsequent time when the taking is to be deemed complete. The case before the court concerned certain county roads which were occasionally invaded by intermittent floods alleged to be caused by the erection of a government dam which was completed and began to fill on November 3, 1903. The suit was not brought until November 5, 1911. The landowner claimed that the taking did not occur until 1911, contending that the statute did not begin to run until the cause of action was complete and the roads had been abandoned. But the evidence showed that all the roads were subject to intermittent flooding as soon as the pool filled and the court therefore rejected the landowner's contention and, without stating that the right of action accrued when the dam was finished or when the water first began to submerge the land, held that so far as there was any taking, it was complete when the water had reached pool level. The point was emphasized that the time of accrual of the right of action did not depend on the time when the county decided to abandon the use of the roads. Again, in the second cited case from the Court of Claims, Dooner et al. v. United States, 95 Ct.Cl. 392, 397, 399, it was held that the owner of permanently flooded lands was entitled to interest from the date when the land was completely submerged.

We think that this is the rule to be applied in the cases now under consideration. The taking occurred in the course of the exercise by the United...

To continue reading

Request your trial
23 cases
  • Owen v. U.S., 87-1405
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • July 18, 1988
    ...to be damaged from erosion as a direct and proximate cause of taking of the land permanently flooded. The Fourth Circuit affirmed. 152 F.2d 865 (4th Cir.1946). Before the Supreme Court, inter alia, the government in Dickinson challenged the award of damages based on the erosion to land outs......
  • Banks v. United States
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • December 22, 2011
    ...Vaizburd v. United States, 384 F.3d 1278, 1286 (Fed. Cir. 2004) (alterations in original) (quoting United States v. Dickinson, 152 F.2d 865, 870 (4th Cir. 1946), aff'd, Dickinson, 331 U.S. 745). The court must therefore determine whether it was "sound economy" for plaintiffs to construct th......
  • Banks v. United States
    • United States
    • U.S. Claims Court
    • December 22, 2011
    ...Vaizburd v. United States, 384 F.3d 1278, 1286 (Fed. Cir. 2004) (alterations in original) (quoting United States v. Dickinson, 152 F.2d 865, 870 (4th Cir. 1946), aff'd, Dickinson, 331 U.S. 745). The court must therefore determine whether it was "sound economy" for plaintiffs to construct th......
  • Vaizburd v. U.S., 03-5154.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • October 1, 2004
    ...pre-taking condition ... [and for] clearing and restoring the property in the condition for rebuilding"). Similarly, the Supreme Court in Dickinson upheld the Fourth Circuit's damages decision "based on the cost of protective measures which the landowners might have taken to prevent the los......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT