United States v. Fleisher Engineering & Const. Co.
Decision Date | 13 November 1939 |
Docket Number | No. 75.,75. |
Citation | 107 F.2d 925 |
Parties | UNITED STATES, for Use and Benefit of HALLENBECK, v. FLEISHER ENGINEERING & CONSTRUCTION CO. et al. |
Court | U.S. Court of Appeals — Second Circuit |
Gibbons, Pottle & Pottle, of Buffalo, N. Y. (Frank Gibbons, of Buffalo, N. Y., of counsel), for defendants-appellants.
Edwin J. Culligan, of Buffalo, N. Y., for plaintiff-appellee.
Before L. HAND, SWAN, and AUGUSTUS N. HAND, Circuit Judges.
George S. Hallenbeck, doing business under the name of Hallenbeck Inspection & Testing Laboratory, performed certain work during the months of March, April and May, 1937, in inspecting and testing materials on the Kenfield Housing Project No. H-6703 at Buffalo under an agreement with Easthom-Melvin Co., Inc., whereby he was to be paid by the latter $1,012.87.
The United States acting through the Federal Administrator of Public Works entered into a contract with Fleisher Engineering & Construction Co. and Joseph A. Bass (doing business as Joseph A. Bass Co.) whereby the latter were to furnish all the labor and materials and perform all work required for the construction of the superstructure for the Housing Project. The Easthom-Melvin Co., Inc., was a subcontractor of these concerns, and the labor performed by Hallenbeck under his agreement with the Easthom-Melvin Co., Inc., was required to be performed by Fleisher Engineering & Construction Co. and Bass under their contract with the United States and actually was performed with the knowledge, consent and approval of the main contractors. The Easthom-Melvin Co., Inc., neglected to pay Hallenbeck the amount which was admittedly owing to him. Thereupon, within ninety days after the date when payment became due, he wrote to the project engineer who represented the government in superintending the performance of the contract a letter notifying the engineer of his claim and of the default of Easthom-Melvin Co., Inc., in paying it and sent a copy of the letter by mail in a postpaid envelope to Fleisher Engineering & Construction Co. Each notification was received, but the letter sent to Fleisher Company was sent by ordinary, and not by registered, mail. A copy of the letter of notification was not mailed to Bass. The notice showed on its face the amount claimed by Hallenbeck, that his contract was with the Easthom-Melvin Co., Inc., and that the items were for inspection and testing work.
The United States brought the present suit on behalf of Hallenbeck to recover upon a payment bond furnished by Fleisher Engineering & Construction Co. and Joseph A. Bass, the contractors, and by Royal Indemnity Company and Maryland Casualty Company as sureties. Under this bond, which was in standard government form, the contractors and the sureties bound themselves in the amount of $79,988 jointly and severally as follows: "If the principal shall promptly make payment to all persons supplying labor and material in the prosecution of the work provided for in said contract, and any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the surety being hereby waived, then this obligation to be void; otherwise to remain in full force and virtue."
The plaintiff moved for a summary judgment upon the claim of Hallenbeck which was granted by Judge Knight. From that judgment an appeal was taken to this court.
The Miller Act, 40 U.S.C.A. § 270a (2), requires persons entering into a contract for the construction of any public work of the United States to furnish "a payment bond with a surety or sureties * * * for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person." The bond upon which this suit was brought was furnished in pursuance of the Act.
The Act, 40 U.S.C.A. § 270b, subdivisions (a) and (b), defines the rights of persons furnishing labor or materials for a public contract in respect of which a payment bond has been furnished as follows:
The only question for consideration is whether in view of the provisions of Section 270b, subdivision (a) of the Miller Act, Hallenbeck, called in the briefs "the use plaintiff", gave sufficient notice to the original contractors to enable him to bring suit on the payment bond.
We feel no doubt that the notice complied with the statute as to its contents. It was not, however, sent by registered but only by ordinary mail and therefore did not conform to the provisions of Section 270b (a) in respect to method of mailing. Furthermore, it was...
To continue reading
Request your trial-
Citicorp Mortg., Inc. v. Porto
...joint obligors conveys notice to the other with respect to matters affecting the joint obligation. United States v. Fleisher Engineering & Construction Co., 107 F.2d 925, 929 (2d Cir.1939). In this case, the defendant concedes that Joanne Porto received actual notice of acceleration by virt......
-
Appeal of Harris, 526
...61 S.Ct. 81, 85 L.Ed. 12, and United States for the Use and Benefit of Hopper Bros. v. Peerless Casualty Company, 8 Cir., 255 F.2d 137. In Fleisher the action was instituted by the United States of America for the use and benefit of one George S. Hallenbeck upon a payment bond given by the ......
-
Deutsche Bank Nat'l Trust Co. v. Ponger
...joint obligors conveys notice to the other with respect to matters affecting the joint obligation. United States v. Fleisher Engineering & Construction Co. , 107 F.2d 925, 929 (2d Cir. 1939)." (Emphasis added.) Citicorp Mortgage, Inc. v. Porto , supra, 41 Conn. App. at 603–604, 677 A.2d 10.......
-
Fleisher Engineering Construction Co v. United States Hallenbeck
...270b, 40 U.S.C.A. § 270b. Plaintiff obtained a summary judgment (D.C., 30 F.Supp. 964) which the Circuit Court of Appeals affirmed. 2 Cir., 107 F.2d 925. The applicable provision of the Miller Act is set forth in the margin.1 The question is whether the giving of the required written notice......