United States v. Gunnar I. Johnson & Son, Inc.
Decision Date | 28 January 1963 |
Docket Number | No. 17074.,17074. |
Citation | 310 F.2d 899 |
Parties | UNITED STATES of America for the use of GENERAL ELECTRIC COMPANY, a corporation, Appellant, v. GUNNAR I. JOHNSON & SON, INC., a corporation, and St. Paul Fire and Marine Insurance Company, a corporation, Appellees. |
Court | U.S. Court of Appeals — Eighth Circuit |
Harold Jordan, St. Paul, Minn., made argument for appellant and filed brief.
George X. Connor, Hopkins, Minn., made argument for appellee and filed brief.
Before MATTHES and BLACKMUN, Circuit Judges, and REGISTER, District Judge.
This is an action commenced under the provisions of the Miller Act, 40 U.S.C.A. § 270b, for the recovery of a certain sum alleged to be due the appellant for materials furnished the appellee Gunnar I. Johnson & Son, Inc., a corporation. The sole issue is whether the written notice of claim given by the use plaintiff (appellant) to the prime contractor, Gunnar I. Johnson & Son, Inc., (appellee) was given within ninety days from the date on which said appellant furnished the last of the material for which such claim is made, as required by said statute.1
This case was submitted on a written Stipulation of Facts, which facts, as so stipulated, constitute the sole evidence herein. On June 29, 1959, the appellee, Gunnar I. Johnson & Son, Inc., as prime contractor, entered into a written contract with the United States of America, Department of the Army, for the construction of certain facilities at the United States Air Force Base at Willmar, Minnesota. The bond required by the Miller Act (40 U.S.C.A. § 270a) was executed by the prime contractor, as principal, and by St. Paul Fire and Marine Insurance Company, as surety. The electrical work was subcontracted to John M. Schroeder, Inc. Said subcontractor entered into a contract with the appellant (use-plaintiff) wherein appellant agreed with subcontractor to supply various items of electrical materials to such job. It will be helpful to quote specific portions of the Stipulation which are of vital importance to the disposition hereof.
Attached to, and constituting a part of such Stipulation, is a correct statement of the entire account for said job taken from plaintiff's records, copies of all of said purchase orders, and a table showing dates on which the materials called for in such purchase orders were shipped to the job sites.
The amount of the claim here in suit is $7,383.73. This claim is comprised of the sum of $7,003.71 as balance unpaid on the main purchase order, and of the sum of $380.02 balance remaining unpaid on four small purchase orders for miscellaneous items, on April 6, 1960, which respective balances remained after the proper allocation of payments and credits to which the subcontractor was entitled at that time on the purchase price of items previously purchased and furnished. The shipping dates of such four miscellaneous items were October 21, November 21, December 15, and December 30, 1959, respectively. The shipping dates and amounts of the shipments of component parts of the entire electrical system (main purchase order) here involved are:
November 10, 1959 ............... $ 210.25 December 3, 1959 ................ 4899.00 December 23, 1959 ............... 2014.00 Total ....................$ 7123.25 on which there is a credit of ... 119.54 leaving balance of such claim of ..........................$ 7003.71
The only notice served or given by appellant was dated and mailed on April 6, 1960, and was received by the prime contractor, Gunnar I. Johnson & Son, Inc., (appellee) on April 7, 1960. No question is raised herein as to the adequacy of the contents of the notice or of the validity of its service.
From the stipulated facts it is apparent that the main purchase order covered an entire electrical distribution system which was to be engineered, manufactured and prepared at appellant's factory for this job and delivered to the job site; that said main purchase order constituted one entire contract; that the component parts making up the entire system were delivered in sections over a period of several months; that on April 6, 1960, not all of the component parts had been shipped; that on April 6, 1960, the performance of such contract was incomplete, and that the remainder of the component parts were shipped subsequent to the date on which the notice of claim was made. The record discloses that the component parts of such system which were furnished after April 7, 1960, were furnished pursuant to a direct contractual relationship then existing between the appellant and said appellee Gunnar I. Johnson & Son, Inc., that the cost of all thereof was paid by the said appellee, and that no part thereof is included in the claim here involved. Such direct contractual relationship between the appellant and said appellee Gunnar I. Johnson & Son, Inc., was created on April 7, 1960, and related only to materials furnished on and after that date.
This direct contractual relationship arose from said appellee's express promise to appellant, made on April 7, 1960, that it "would guarantee payment for all materials thereafter to be delivered by plaintiff for completion of said contracts". See "Bonds of Contractors on Federal Public Works — Miller Act", Boston University Law...
To continue reading
Request your trial-
U.S. v. Fidelity and Deposit Co. of Maryland
...would be able to bring a valid contractual claim against the general contractor. See United States for Use of General Elec. Co. v. Gunnar I, Johnson & Son, Inc., 310 F.2d 899, 903 (8th Cir.1962). Claims may be brought once the requirements of the original subcontract have been performed, de......
-
US ON BEHALF OF & FOR USE OF BALF v. Casle Corp.
...ex rel. State Elec. Supply Co. v. Hesselden Constr. Co., 404 F.2d 774, 776 (10th Cir.1968); United States ex rel. General Elec. Co. v. Gunnar I. Johnson & Son, Inc., 310 F.2d 899, 903 (8th Cir.1962); United States ex rel. Raymond A. Bergen, Inc. v. DeMatteo Constr. Co., 467 F.Supp. 22, 23-2......
-
United States ex rel. Am. Civil Constr., LLC v. Hirani Eng'g & Land Surveying, P.C.
...United States ex rel. Austin v. W. Elec. Co. , 337 F.2d 568, 572–73 (9th Cir. 1964) (same); United States ex rel. Gen. Elec. Co. v. Gunnar I. Johnson & Son, Inc. , 310 F.2d 899, 903 (8th Cir. 1962) (same). At least two courts in this District have followed that approach. See Highland Renova......
-
Insurance Co. of North America v. Genstar Stone Products Co.
...notice period. A condensed survey demonstrates the proposition. At one end of the spectrum is United States ex rel. General Elec. Co. v. Gunnar I. Johnson & Son, Inc., 310 F.2d 899 (8th Cir.1962). In December 1959 the supplier of electrical parts and equipment shipped two bus duct elbows to......