United States v. John Gleason 23, 24 1899

Decision Date06 November 1899
Docket NumberNo. 59,59
Citation20 S.Ct. 228,175 U.S. 588,44 L.Ed. 284
PartiesUNITED STATES, Appt. , v. JOHN R. GLEASON and George W. Gosnell. Argued October 23, 24, 1899. Ordered for reargument
CourtU.S. Supreme Court

In the first suit, upon findings of fact and law, there was a judgment in favor of the plaintiffs for retained percentage in the sum of $3,011.99, and for net profits which they would have made if they had been allowed to complete the work in the sum of $60,537.50. In the second suit there was a judgment for retained percentage in the sum of $2,401, and for net profits, if the contract had been carried on to completion, in the sum of $2,827.50. The aggregate judgment in the two cases was for the sum of $68,777.99.

There was a motion for a new trial, which was overruled, and also for an amendment of the findings of fact, which was granted in part. Thereupon this appeal was taken.

The findings of fact in the suit upon the first contract were as follows:

'I. On August 4, 1885, Lieutenant Colonel William E. Merrill, Corps of Engineers, United States Army, for and on behalf of the United States, party of the first part, and John R. Gleason and George W. Gosnell, partners, of the second part, entered into the contract and specifications set out in full, with and made a part of the petition herein, whereby the claimants agreed to commence work on or before August 20, 1885, and make '110,000 cubic yards, more or less, of rock excavation in the enlargement of the Louisville & Portland Canal,' as therein provided for, at the rate of 85 cents per cubic yard, and to complete the same on or before December 31, 1886.

'Said contract further, and among other things, provided that —

"If, in any event, the party of the second part shall delay or fail to commence with the delivery of the material or the performance of the work on the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then in either case the party of the first part, or his successor legally appointed, shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party or parties (or either of them) of the second part, and upon the giving of such notice all money or reserved per- centage due or to become due to the party or parties of the second part by reason of this contract shall be and become forfeited to the United States; and the party of the first part shall be thereupon authorized, if an immediate performance of the work or delivery of the materials be, in his opinion, required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in § 3709 of the Revised Statutes of the United States; provided, however, that if the party or parties of the second part shall, by freshets, ice, or other force or violence of the elements, and by no fault of his or their own, be prevented either from commencing or completing the work or delivering the materials at the time agreed upon in this contract, such additional time may in writing be allowed him or them for such commencement or completion as, in the judgment of the party of the first part or his successor, shall be just and reasonable; but such allowance and extension shall in no manner affect the rights or obligations of the parties under this contract, but the same shall subsist, take effect, and be enforcible precisely as if the new date for such commencement or completion had been the date originally herein agreed upon.'

'II. The season from August, 1885, to December 31, 1886, was favorable in the main for the character of work provided for by the contract, though the claimants were compelled by reason of high water and freshets to suspend their operations a number of times, and by reason of these difficulties, coupled with an insufficient force of men and other means necessary for the performance of the work, they only 'completed 14 per cent of their entire work' during the contract period, 1 1/2 per cent of which was done in 1885.

'III. In consequence of the claimants' inability to complete the work within the contract period, as aforesaid, they requested an extension of their contract to December 31, 1887, which was granted on conditions stated in a supplemental contract, as follows:

"Articles of Agreement.

"Supplemental articles of agreement entered into this 21st day of January, eighteen hundred and eighty-seven (1887) between Major Amos Stickney, Corps of Engineers, U. S. Army, of the first part, and John R. Gleason and George W. Gosnell, partners, doing business under the firm name of Gleason & Gosnell, of Louisville, of the county of Jefferson, state of Kentuckey, of the second part.

"This agreement witnesseth that the said Major Amos Stickney, for and in behalf of the United States of America, and the said Gleason & Gosnell, for themselves, their heirs, executors, and administrators, have mutually agreed, and by these presents do mutually covenant and agree, to and with each other as follows:

"That the time for completing the contract signed by the said Gleason & Gosnell, August 4th (fourth), eighteen hundred and eighty-five (1885), for rock excavation in the enlargement of the Louisville and Portland Canal, be extended to December 31st (thirty-first), eighteen hundred and eighty-seven (1887), upon the following conditions, viz.:

"First. That the said Gleason & Gosnell shall so arrange their excavation on the line common to sections 2 (two) and 3 (three) as not to interfere with the government work of contractor Molloy or the work of the contractor for the new wall of the said Louisville 3 Portland Canal.

"Second. That should the said Gleason & Gosnell fail to employ a sufficient force, not less than three hundred (300) men, or its equivalent in machinery, to finish their work in the required time, then the officer in charge shall be authorized to perform any of the work in his discretion, and deduct the cost from any monye due or to become due the said Gleason & Gosnell.'

'The foregoing agreement was made subject to approval of the Chief of Engineers, United States Army, and was thereafter duly approved by the acting Secretary of War.

'IV. The claimants not having completed their contract during the year's extension thereof as aforesaid, they, on December 31, 1887, requested a second extension of said contract to December 31, 1888, for the reasons set forth in their communication of that date, which is as follows "Louisville, Ky., Dec. 31st, 1887.

"Major Amos Stickney,

Corps of Engineers, U. S. A.

"Dear Sir: We respectfully ask an extension of time on our contract for enlarging the Louisville & Portland Canal at the head of the Falls of the Ohio river until the 31st of December, 1888, for the following reasons, to wit:

"There was so much work being done upon railroads during the last year throughout the state that labor was very hard to get.

"We used every effort to secure the required amount of labor on our contracts, but found it impossible to do so. We even employed agents in New York and other cities to procure and ship labor to us here, and then found it very difficult to hold the labor we obtained, although we paid more than contractors paid for labor on railroads. Besides, the summer season was excessively hot; so very hot that for sixty to ninety days in many instances, the men would work only two or three hours a day.

"We propose to provide not less than ninety cars of the same capacity as those now used, and a sufficient number of carts and teams in addition, if necessary, to move not less than 640 cubic yards (measured in place) of excavated rock per day of ten hours.

"We propose to build an additional incline for depositing excavated material, the minimum actual working capacity of both inclines to be not less than 640 cars per day of ten hours.

"We propose to provide, maintain, and operate not less than ten steam drills on the work and to provide and operate a sufficient force of men to excavate and handle at least 640 cubic yards of rock (measured in place) per day of ten hours.

"The method of carrying on the work will be such as will be approved by the officer in charge.

"When practicable, during the summer season, we propose to provide and operate an adequate force at night.

"All additional plant will be obtained and available for use by the time rock excavation can be commenced, and we pro- pose to bear all extra cost to the United States occasioned by the extension of time for completing our contract.'

'Which letter was forwarded to the Chief of Engineers with the following communication:

"U. S. Engineer Office,

Louisville, Ky., December 31st, 1887.

"The Chief of Engineers, U. S. Army,...

To continue reading

Request your trial
149 cases
  • R. T. Clark & Co. v. Miller, State Revenue Agent
    • United States
    • Mississippi Supreme Court
    • 20 Mayo 1929
    ... ... War before United States participated therein ... Courts ... v. Sartorious, 46 Miss. 56; John S. Penrice v. Wallis et ... al., 37 Miss. 172 ... 880, 64 P. 1027; ... Seaton v. Heath (1899), 1 Q. B. 782; Dane v ... Mortgage Ins. Corp, ... United ... States v. Gleason, 175 U.S. 588, 602, 44 L.Ed. 284, ... 289, 20 ... ...
  • Sheldon v. Chi. Bonding & Sur. Co.
    • United States
    • Iowa Supreme Court
    • 8 Febrero 1921
    ...Co. v. Ferguson, 233 Ill. 88, 79 N. E. 35;Keachie v. Starkweather Drainage District, 168 Wis. 298, 170 N. W. 236;U. S. v. Gleason, 175 U. S. 588, 20 Sup. Ct. 228, 44 L. Ed. 284;Seim v. Karuse, 13 S. D. 530, 83 N. W. 583;Ruch v. York City, 233 Pa. 36, 81 Atl. 891; Kilmer v. U. S., 48 Court o......
  • McCullough v. Clinch-Mitchell Const. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • 22 Mayo 1934
    ...governing disputes arising in construction and similar contracts have been generally upheld. As said in United States v. Gleason, 175 U. S. 588, 602, 20 S. Ct. 228, 233, 44 L. Ed. 284, "* * * It is competent for parties to a contract, of the nature of the present one construction contract, ......
  • 31 658 Contractors, Inc v. United States 8212 88
    • United States
    • U.S. Supreme Court
    • 21 Octubre 1971
    ...his decision in favor of the contractor 'was conclusive upon the company.' Id., at 292, 14 S.Ct., at 345. United States v. Gleason, 176 U.S. 588, 20 S.Ct. 228, 44 L.Ed. 284 (1900), involved a Government official's disputes decision adverse to the contractor. The Court again affirmed the rul......
  • Request a trial to view additional results
1 books & journal articles
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • 1 Abril 2021
    ...United States v. Callahan Walker Constr. Co., 317 U.S. 56 (1942); Ripley v. United States, 223 U.S. 695 (1912); United States v. Gleason, 175 U.S. 588 (1900). 67. Gleason , 175 U.S. at 602. 68. United States v. Moorman, 338 U.S. 457 (1950). 69. Id. at 461. 70. Id. at 462. 71. United States ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT