United States v. Lembke Construction Company

Decision Date20 December 1966
Docket NumberNo. 8595.,8595.
PartiesUNITED STATES of America, for the Use of Harold BRYANT, dba Rio Grande Sand and Gravel, Appellant, v. LEMBKE CONSTRUCTION COMPANY, Inc., and Glens Falls Insurance Company, Appellees.
CourtU.S. Court of Appeals — Tenth Circuit

James A. Womack, Albuquerque, N. M. (Arturo G. Ortega, Albuquerque, N. M., on the brief), for appellant.

Richard G. Cooper, Albuquerque, N. M. (Bryan G. Johnson and Marshall G. Martin, Albuquerque, N. M., on the brief), for appellees.

Before MURRAH, Chief Judge, and HILL and HICKEY, Circuit Judges.

HILL, Circuit Judge.

This Miller Act case was brought in the United States District Court by the use plaintiff-appellant against appellees Lembke Construction Company, Inc., a prime contractor on a government construction contract, and its surety, Glens Falls Insurance Company. The District Court rendered judgment for the appellees.

Appellee Lembke Construction Company contracted to construct certain facilities for the United States Government. As required by the Miller Act,1 a payment bonding agreement was entered into — the bonding company being appellee Glens Falls Insurance Company. Subsequently, Adams Concrete Company entered into a contract with Lembke to supply all of the concrete necessary for the construction job. Appellant Harold Bryant, dba Rio Grande Sand and Gravel, then entered into an oral agreement with Adams whereby appellant agreed to supply Adams with sand and gravel needed in mixing the concrete for the government project. Appellant did perform under this agreement and it is not controverted that Adams owes appellant $2,390.00 for sand and gravel delivered. Appellant, after complying with § 270b(a)'s notice requirement, as use plaintiff, instituted suit under the Miller Act against the prime contractor, Lembke Construction Company, and its bonding company, Glens Falls Insurance Company, to recover on the payment bond the amount due appellant from Adams. The District Court found that appellant could not recover on the bond because Adams was not a "subcontractor" within the meaning of 40 U.S.C. § 270b(a).2

Since appellant Bryant had no contractual relationship with the prime contractor, appellee Lembke, Bryant cannot recover on the payment bond unless he can show that Adams was a "subcontractor" within the meaning of the statute. Thus, we have but one very narrow question to decide: Did the District Court properly conclude that Adams Concrete Company was not a "subcontractor" of the appellee Lembke Construction Company, Inc., within the meaning of the proviso in 40 U.S.C. § 270b(a)?

The Supreme Court in Clifford F. MacEvoy Co. v. United States et al., 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163, addressed itself to an interpretation of "subcontractor" as the word is used in the proviso. In that case, considering the Miller Act's history, the Court rejected a broad generic definition of the word and, instead, found that it was intended to have a "more technical meaning, as established by usage in the building trades * * *."3 Under this construction, the Court held that "a subcontractor is one who performs for and takes from the prime contractor a specific part of the labor or material requirements of the original contract, thus excluding ordinary laborers and materialmen." The appellee asserts that the District Court properly found that Adams was a materialman rather than a subcontractor. Appellant, however, relying on the disjunctive "or" in the language just quoted contends that a person who supplies only materials — as Adams did — can be a subcontractor if he performs for and takes from the prime contractor a "specific part of the * * * material requirements of the original contract." Since Adams contracted to and did, except for a "few bags", supply all the concrete used in the project, appellant contends he qualifies as a subcontractor.

The MacEvoy case does tell us that "The Miller Act * * * is highly remedial in nature. It is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects."4 It also tells us, however: "But such a salutary policy does not justify ignoring plain words of limitation and imposing wholesale liability on payment bonds." We think appellant is reading the language it relies upon in isolation and is ignoring the purpose of the Miller Act and the substance of the MacEvoy case. The ultimate determination of whether a supplier of material such as Adams is a materialman or a subcontractor depends upon a consideration of the extent to which, in matters of substance, the prime contractor delegates to the supplier, and the supplier undertakes to perform for the prime contractor, a specific part of the labor or material requirements of the prime contract.5

In this case, Adams undertook to furnish concrete. There was by this undertaking no substantial delegation of any portion of Lembke's contract. The concrete Adams undertook to deliver was in no way a "customized" material, thus bringing Adams within the purview of those cases holding that a supplier of such "customized" material is a subcontractor, even though he does not perform many services in reference to installation.6 All Adams did was deliver concrete. Admittedly, he was to deliver all the concrete needed for the job and the concrete had to conform to the specifications in the prime contract. This does not, however, change Adams' status from a materialman to a subcontractor. The reference in Adams' contract to the specifications in the prime contract is "merely descriptive of what is to be furnished."7 There was no material delegation of the job the prime contractor was obligated to perform under the prime contract.

We agree with appellant that "subcontractor" must be given a judicial interpretation and that its meaning is not dependent upon how the parties designate themselves.8 However, the Supreme Court has told us that "subcontractor" must be given a "technical meaning, as established by usage in the building trades. * * *."9 Thus we think it significant that Adams furnished concrete under a "Standard Form of Material Contract" but when Adams contracted to prepare some road beds and parking areas for Lembke, that work was done under a "Standard Subcontract Form." The District Court found that "The Contract for materials was treated by all the parties entirely on a different basis than the subcontract."10

We think it would fly in the face of the "practical considerations underlying the Miller Act"11 to accede to appellant's too liberal construction of the MacEvoy case. The Act does not propose to cope "with remote and undeterminable liabilities incurred by an ordinary materialman * * *."12

Affirmed.

2 The statute has been quoted so often in other opinions, we quote only that part necessary for a determination of the question in this case...

To continue reading

Request your trial
22 cases
  • Liberty Mut. Ins. Co. v. Friedman
    • United States
    • U.S. District Court — District of Maryland
    • December 28, 1979
    ...contract which "amounted roughly only to two percent of the total construction cost." Id. at 618. In United States ex rel. Bryant v. Lembke Construction Co., 370 F.2d 293 (10th Cir. 1966), another Miller Act case, the Tenth Circuit held that a supplier of concrete to the prime contractor on......
  • Rich Co Inc v. United States Industrial Lumber Company, Inc 8212 1382
    • United States
    • U.S. Supreme Court
    • May 28, 1974
    ...1967); Basich Bros. Construction Co. v. United States for Use of Turner, 159 F.2d 182 (CA9 1946); cf. United States for Use of Bryant v. Lembke Construction Co., 370 F.2d 293 (CA10 1966). 8 Travelers Indemnity Co. v. United States for Use and Benefit of Western Steel Co., 362 F.2d 896, 898 ......
  • Vulcraft, a Div. of Nucor Corp. v. Midtown Business Park, Ltd.
    • United States
    • New Mexico Supreme Court
    • October 25, 1990
    ...of whether United Steel was a subcontractor, or whether appellants can maintain a lien. See United States ex rel. Bryant v. Lembke Constr., Co., 370 F.2d 293 (10th Cir.1966); Jesse F. Heard & Sons v. Southwest Steel Prods., 124 So.2d 211, 213 (La.App.1960) ("whether or not one is a subcontr......
  • Atlantic Sea-Con, Ltd. v. Robert Dann Co.
    • United States
    • Maryland Court of Appeals
    • September 1, 1989
    ...382 F.2d 615 (5th Cir.1967) (supplier of materialman had no standing to sue on Miller Act payment bond); United States v. Lembke Construction Company, 370 F.2d 293 (10th Cir.1966) (supplier of materialman could not recover under prime contractor's bond); Eastern Indus. Marketing v. Desco El......
  • Request a trial to view additional results
2 books & journal articles
  • Chapter 11 - § 11.12 • PAYMENT AND NON-PAYMENT OF SUBCONTRACTORS AND MATERIALMEN
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 11 Subcontractors and Materialmen
    • Invalid date
    ...Co., 580 P.2d 1278, 1280 (Colo. App. 1978).[181] 40 U.S.C. §§ 3131 through 3134.[182] United States ex rel. Bryant v. Lembke Constr. Co., 370 F.2d 293, 296-97 (10th Cir. 1966).[183] Kennedy Elec. Co. v. U.S. Postal Serv., 508 F.2d 954, 960 (10th Cir. 1974).[184] C.R.S. § 38-22-127(1).[185] ......
  • Chapter 11 - § 11.1 • DEFINITIONS AND DISTINCTIONS
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 11 Subcontractors and Materialmen
    • Invalid date
    ...Lath v. Acoustical & Constr. Supply, Inc., 851 P.2d 875, 878-80 (Colo. 1993) (CPWA); United States ex rel. Bryant v. Lembke Constr. Co., 370 F.2d 293 (10th Cir. 1966).[9] See C.R.S. § 38-22-101(1).[10] See Kobayashi, 472 P.2d at 727-28; Ragsdale Bros. Roofing v. United Bank of Denver, 744 P......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT