US FOR USE AND BENEFIT OF, ETC. v. BUTT & HEAD

Decision Date26 March 1982
Docket NumberNo. C-3-80-453.,C-3-80-453.
Citation535 F. Supp. 1155
PartiesUNITED STATES of America For Use and Benefit of NABERHAUS-BURKE, INC., Plaintiff, v. BUTT & HEAD, INC., et al., Defendants.
CourtU.S. District Court — Southern District of Ohio

Don R. Gardner, Cincinnati, Ohio, for plaintiff.

Robert Bruce Shearer, Dayton, Ohio, for defendants.

DECISION AND ENTRY ADOPTING REPORT AND RECOMMENDATION OF MAGISTRATE IN ITS ENTIRETY; DEFENDANTS' OBJECTIONS TO REPORT AND RECOMMENDATION OF MAGISTRATE OVERRULED; DEFENDANTS' MOTION FOR SUMMARY JUDGMENT OVERRULED; ORDER OF REFERENCE TO MAGISTRATE ORDERED AMENDED

RICE, District Judge.

This case, filed in this Court pursuant to the Miller Act, 40 U.S.C. §§ 270a-270d, involves an effort by the Plaintiff to recover monies from a surety. Defendants filed a motion for summary judgment (Doc. # 10), and in a Report and Recommended Decision (Doc. # 18), the United States Magistrate recommended that said motion be overruled. The matter is before this Court upon Defendants' motion to review said Report (Doc. # 19), made pursuant to 28 U.S.C. § 636(b)(1)(C). For the reasons set forth below, the Defendants' objections to said Report are overruled. Accordingly, Defendants' motion for summary judgment is overruled.

I. FACTUAL BACKGROUND

The Magistrate's Report ably summarized the disputed and undisputed facts in this case, and said facts need not be recited at great length herein. This action, as previously mentioned, is based on the Miller Act. Under said Act, a contractor constructing a building for the United States must furnish a performance bond and a payment bond with a satisfactory surety. 40 U.S.C. § 270a(a). The Act further provides that every "person who has furnished labor or material in the prosecution of work provided for" in a contract, may sue on the payment bond for unpaid amounts, provided said person has a direct contractual relationship with a subcontractor or the prime contractor. 40 U.S.C. § 270b(a). To bring an action in court, said person must give written notice to the contractor "within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made," id., and file suit within "one year after the day on which the last of the labor was performed." 40 U.S.C. § 270b(b).

The Magistrate's Report summarized the undisputed facts in this action, filed by the Plaintiff NA Engineering Company (hereinafter NA), a division of Naberhaus-Burke, Inc.:

The following facts are set forth in the pleadings and are undisputed: The United States of America entered into a written contract with Defendant Butt & Head, Inc. (hereinafter Butt & Head), the prime contractor, to furnish all labor and materials to perform all work required for Wright Patterson Air Force Base, Dayton, Ohio. Butt & Head, in turn, subcontracted with J&D Erection, Inc. (hereinafter J&D) to perform certain obligations of the prime contractor. J&D then subcontracted with Plaintiff NA to furnish calculations and certain specified shop drawings for the project. In order to protect the subcontractor's labor and materials invested, Butt & Head furnished a payment bond, pursuant to 40 U.S.C. § 270a, naming Defendant Federal Insurance Company as surety (hereinafter Federal). Upon completion of Plaintiff's contractual duties, Plaintiff demanded payment from J&D for the outstanding balance of $22,140.00 due on the contract. Such payment was not made. Plaintiff then demanded payment from Federal.

Report at 1.

The complaint further alleges that the last date on which Plaintiff furnished services under the sub-contract was May 27, 1980 (Complaint, ¶ 9). Written notices to the contractor are alleged to have been served on March 28, 1980, April 7, 1980, and June 11, 1980 (Complaint, ¶ 10). The complaint was filed on October 22, 1980. On December 18, 1980, this Court referred the case to the United States Magistrate (Doc. # 6), pursuant to 28 U.S.C. § 636(b)(1)(B) & (C) and Fed.R.Civ.P. 53(c). Defendants thereupon moved for summary judgment (Doc. # 10).1 This motion was overruled.

II. REVIEW OF THE MAGISTRATE'S REPORT; REPORT ADOPTED IN ITS ENTIRETY

The Magistrate made his recommendation, with respect to the summary judgment motion, pursuant to 28 U.S.C. § 636(b)(1)(B). Upon review, this Court must make a de novo determination of those portions of the report to which objection is made. The Court may accept, reject, or modify, in whole or in part, the recommendation made by the Magistrate. 28 U.S.C. § 636(b)(1)(C); Pope v. Harris, 508 F.Supp. 773, 775 (S.D.Ohio 1981). This Court will consider Defendants' objections to the Magistrate's Report under this standard.

Consideration of said objections will require this Court to briefly review the relevant case law under the Miller Act. Defendants moved for summary judgment on two principal grounds, to wit:

(1) Plaintiff was not a "person" furnishing "labor" who could bring suit under § 270b; and
(2) even if Plaintiff was a statutorily defined "person," it did not give the required notice to the contractor within 90 days, § 270b(a), and did not file suit within the one-year limit, § 270b(b).

A review of the Miller Act provisions, and relevant case law, will aid in delineating Defendants' grounds in support of their summary judgment motion.

The Magistrate capably and correctly summarized the relevant case law. Report at 2-3. The Miller Act is designed to provide an analogue to mechanic's liens utilized with private construction projects. Although intended to be remedial in nature and liberally construed, the Act is not to be applied so as to impose wholesale liability on payment bonds. Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 893, 88 L.Ed. 1163 (1944); J. W. Bateson Co., Inc. v. United States ex rel. Board of Trustees, 434 U.S. 586, 594, 98 S.Ct. 873, 877, 55 L.Ed.2d 50 (1978).

While case law interpreting the word "labor" in § 270b(a) is relatively sparse, the word has been construed to include physical toil, but not work by a professional, such as an architect or engineer. However, the term does include an architect or another professional who actually superintends the work as it is done on the job site. American Surety Co. v. United States ex rel. Barrow-Agee Labs., 76 F.2d 67, 68 (5th Cir. 1935); J. J. Henry Co. v. United States, 411 F.2d 1246, 1252-53 n.7, 188 Ct.Cl. 39, 45-46 n.7 (1969); National Bank of Newark v. Terminal Const. Corp., 217 F.Supp. 341, 360 (D.N.J.1963), aff'd. per curiam, 328 F.2d 315 (3rd Cir. 1964). In addition, the term has been construed to include a consulting engineer responsible for inspecting a job while in progress. United States ex rel. Charles H. Thayer v. Metro Const. Co., 330 F.Supp. 386, 387-88 (E.D.Va. 1971). Based on this review of the case law,2 the Magistrate concluded that:

Plaintiff must have provided services in the nature of supervision or inspection to satisfy the "labor in prosecution of the work" provision of the Miller Act, 40 U.S.C. § 270b.

Report at 2. This Court agrees with the Magistrate's conclusion.

Defendants argue that Plaintiff, an engineering firm, did no supervising or inspecting at the job site, and thus did not furnish "labor" so as to come within the ambit of the Miller Act. In any event, Defendants contend that Plaintiff last billed work on the contract on June 19, 1979, and that, as a result, the notices and complaint were filed long after the 90-day and one-year statutory minimums, respectively.

In support of these contentions, Defendants submitted a number of documents concerning Plaintiff's performance under the contract. The contract itself (Doc. # 10, Exh. 1) between Plaintiff and J&D does not make any specific reference to Plaintiff providing on-site services. An affidavit sworn to by Garth Williams (Doc. # 10, Exh. 10), an employee of Butt & Head, stated that one of Plaintiff's engineers, E. Paul Naberhaus, only briefly visited the job site on two occasions. Another document (Doc. # 10, Exh. 12), an invoice, indicates that Plaintiff completed billing on the aforementioned contract on June 19, 1979. Finally, Defendants submitted several letters exchanged between Plaintiff and J&D which indicate, Defendants argue, that any work Plaintiff did perform after June 19, 1979, was simply not supervisory in nature. (Doc. # 10, Exhs. 4-9).

In its memorandum contra (Doc. # 14), Plaintiff also submitted a large number of documents which allegedly indicated that, through May of 1980, Plaintiff performed work under the contract, including supervision and consultation. Probably the most important of these documents is an affidavit sworn to by Mr. Naberhaus (Doc. # 13), which states, inter alia, that Plaintiff performed "job-site consultation and job-site review" (Doc. # 13, (2)(d)) under the contract. Plaintiff also points out that the contract at issue provided that the final installment would be payable upon "release and payment by the general contractor." (Doc. # 10, Exh. 1, § 2). This provision, it is said, also indicates that possibility of job site services by the engineer was contemplated.

As the Magistrate correctly recognized, Report at 3, Defendants' summary judgment motion, made pursuant to Fed.R. Civ.P. 56, can only be sustained when the movant demonstrates conclusively that there exists no genuine issue of material fact, all evidence and inferences drawn therefrom having been construed in the light most favorable to the opposing party. Heheman v. E. W. Scripps Co., 661 F.2d 1115, 1127 (6th Cir. 1981). Applying this standard, the Magistrate held as follows:

Plaintiff has raised an issue of material fact as to the actual date of completion of the contract. This completion date controls the limitations period of the Miller Act, 40 U.S.C. § 270b(a), (b). Plaintiff also raises an issue of material fact as to whether the work it performed from the outset of
...

To continue reading

Request your trial
10 cases
  • United States v. Leebcor Servs.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • August 18, 2022
    ...Inc. v. Gulf Ins. Co., 313 F. Supp. 2d 593, 597 (E.D. Va. 2004) (Smith, J.) (quoting United States ex rel. Naberhaus-Burke, Inc. v. Butt & Head, Inc., 535 F. Supp. 1155, 1158 (S.D. Ohio 1982)). But "skilled professional work which involves actual superintending, supervision, or inspection a......
  • Gandee v. Glaser
    • United States
    • U.S. District Court — Southern District of Ohio
    • February 24, 1992
    ...Co., 93 F.R.D. 547, 551 (S.D.Ohio 1982), aff'd without op., 785 F.2d 308 (6th Cir.1986); United States for Use and Benefit of Naberhaus-Burke v. Butt & Head, Inc., 535 F.Supp. 1155 (S.D.Ohio 1982). The Magistrate Judge in this case excluded the Association's exhibits attached to its amicus ......
  • United States v. Baylin, Cr. A. No. 81-22.
    • United States
    • U.S. District Court — District of Delaware
    • March 26, 1982
  • U.S. for Use and Benefit of Olson v. W.H. Cates Const. Co., Inc.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • August 17, 1992
    ...of the remedy afforded by the Miller Act. 3 See F.D. Rich Co., Inc., 417 U.S. at 126-27, 94 S.Ct. at 2163-64; U.S. v. Butt & Head, Inc., 535 F.Supp. 1155, 1158 n. 2 (S.D.Ohio 1982). Cf. United States v. U.S. Fidelity and Guaranty Co., 656 F.2d 993, 996 (5th Cir.1981). But see U.S. v. Kiewit......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT