Valley Engineers Inc. v. Electric Engineering Co.

Decision Date26 October 1998
Docket NumberNo. 97-16383,97-16383
Citation158 F.3d 1051
Parties, 98 Cal. Daily Op. Serv. 7983, 98 Daily Journal D.A.R. 11,091 VALLEY ENGINEERS INC.; Nugget Hydroelectric, L.P., Plaintiffs, v. ELECTRIC ENGINEERING COMPANY, Defendant-Counter-Claimant-Cross-Claimant-Appellant, Credit Suisse, a Swiss Corporation, Counter-Defendant-Counter-Claimant-Appellee, Bruce Brown; Calpine Corporation; William B. Betchart, Counter-Defendants-Appellees, and AMERICAN HOME INSURANCE COMPANY, Counter-Defendant, v. ENERVEST CORPORATION, a Colorado Corporation; Enervest Management Corporation, a Colorado Corporation, Third-Party-Defendants-Appellees.
CourtU.S. Court of Appeals — Ninth Circuit

Diane Wallis Huijgen, Huijgen & Associates, Union City, CA, for appellant Electric Engineering Company.

Mark Pomeranz, Pomeranz & Landsman, North Miami, FL, for appellant Electric Engineering Company.

Kenneth M. Fitzgerald, Latham & Watkins, San Diego, CA, for appellees Credit Suisse and Bruce Brown.

Chris Gibson, Boutin, Dentino, Gibson & Di Giusto, Sacramento, CA, for appellees Calpine and Will B. Betchart.

Steven N. Yermish, Paoli, PA, for appellees Enervest Corporation & Enervest Management Corporation.

Appeal from the United States District Court for the Eastern District of California; Edward J. Garcia, District Judge Presiding. D.C. No. CV-91-00008-EJG.

Before: WALLACE, T.G. NELSON, and KLEINFELD, Circuit Judges.

KLEINFELD, Circuit Judge:

This case concerns sanctions for discovery violations.

Jurisdiction and Standards of Review.

We have jurisdiction over this timely filed appeal pursuant to 28 U.S.C. § 1291. A dismissal under Fed.R.Civ.P. 37 is reviewed for abuse of discretion. Anheuser-Busch, Inc. v. Natural Beverage Distributors, 69 F.3d 337, 348 (9th Cir.1995). The district court's factual findings are reviewed for clear error. Id.

Facts.

Nugget Hydroelectric hired Electric Engineering to build four small hydroelectric projects for $11 million. Because construction was going badly, the scope of the contract was reduced from four projects to one. The contract price on the remaining project, Deadwood Creek, was raised from $2 million to $2.5 million. The contract was a turn-key deal, requiring that Electric Engineering get all required permits and easements, and take full responsibility for design, not relying on Nugget Hydroelectric. Electric Engineering did not build the project as promised, and was fired when it missed its deadlines. Electric Engineering's president knew when Electric Engineering agreed to the revised Deadwood Creek contract that Electric Engineering was not going to perform as promised.

Just before the revised agreement was signed, Electric Engineering's project manager for the Deadwood Creek project, John Carroll, wrote to the company president, cross-copying the company's lawyers, the memorandum critical to this case. The importance of the memorandum is apparent from its face:

I have agonized over the available evidence for the entire weekend and have made several false starts of this letter.

...

Deadwood appears to be priced with the same unit prices [as Big Mosquito, one of the three deleted projects]. I do not know the justification for using the same unit prices for Deadwood as Big Mosquito. It is impossible to build the job for the bid prices. The installation of the penstock could cost two or three times the bid amount ...

The two inlets for Deadwood are located in incredibly difficult terrain, several thousand feet from the nearest dirt road access.

...

Nine thousand feet of Deadwood penstock must be delivered several thousand feet down a 1:1 slope and then delivered horizontally to its installation point.

...

I am scared to death of the cost of constructing Deadwood. We have little time to experiment to find the best methods. We have limited resources with which to do the job.

...

While this is going on, Bill McCarty can be cooperating to resolve all of the pay request matters to bring us up to date with our billing. The bank should be so happy to see this happening, we should have another pay day before the plug is pulled on Deadwood.

(emphasis added).

Ultimately Electric Engineering failed to complete the project and was fired, Nugget Hydroelectric went bankrupt, and a subcontractor completed the project. Multiple lawsuits were filed in every direction. Electric Engineering sued other entities and people involved on the theory that their interference and failures to disclose had caused the overruns.

The claims against American Home, Electric Engineering's surety, went to trial, but were settled mid-trial. The claims by and against Electric Engineering never got to trial. After endless discovery disputes, the judge eventually dismissed Electric Engineering's claims as a discovery sanction. Electric Engineering had committed many discovery violations. The most critical had to do with hiding the memorandum quoted at length above. Electric Engineering appeals from dismissal of its claims against the construction lender (Credit Suisse), its project monitor (Calpine), the owner (Enervest, which owned Nugget), and various individual defendants.

Analysis.

The main issues on appeal boil down to these three: (1) did Electric Engineering waive its right to appeal the issues it does; (2) did the district court err in finding that Electric Engineering deliberately hid the memorandum; and (3) was hiding the memorandum a sufficient basis for so harsh a discovery sanction as dismissal?

A. Waiver.

Electric Engineering appealed the discovery sanction before judgment was entered as to all claims and all parties. We dismissed the appeal for lack of jurisdiction, because it was interlocutory. Valley Engineers v. American Home Assurance Co., 111 F.3d 139 (table), 1997 WL 191468, at 2 (9th Cir., April 17, 1997). Credit Suisse argues that because Electric Engineering did not appeal the dismissal as to Credit Suisse in that earlier appeal, only as to other defendants, it waived its right subsequently to appeal the sanctions order as to Credit Suisse. But none of its citations are on point, because in those cases, the appellate court had jurisdiction over the first appeal.

The point of the cases Credit Suisse relies on is that if a party has a chance to appeal a mistake to a court that can correct the error, and does not, then it should not be able to appeal the error when a subsequent occasion for appeal arises. Alioto v. Cowles Communications, Inc., 623 F.2d 616, 618 (9th Cir.1980) ("a new contention that could have been but was not raised"). The reason for this rule does not apply where the claimed error could not have been corrected because the appellate court lacked jurisdiction. An appeal that is dismissed because the appellate court lacks jurisdiction does not bar or waive a subsequent appeal when jurisdiction exists.

B. Willfulness.

For more than three years, Credit Suisse, taking the lead for defendants in discovery had unfulfilled requests for production outstanding that covered the Carroll memorandum. For more than two years, Electric Engineering's lawyers violated court orders by failing to produce it. Several trial date settings had to be vacated because the discovery was incomplete. Warnings were given and monetary sanctions were imposed as Electric Engineering violated one court order after another. Even after, as a sanction, Electric Engineering had lost its attorney-client privilege regarding discovery requests, it continued to assert the nonexistent privilege regarding the Carroll memorandum. Finally, on the eve of a sanctions hearing, new lawyers for Electric Engineering produced the memorandum. Credit Suisse moved for case-dispositive sanctions, and got them.

The magistrate judge held two days of hearings, with testimony in person and by videotape, in order to resolve the sanctions motion. He found, after meticulous analysis of all the evidence, that Electric Engineering's "disobedience of the court's order was willful," and "the Carroll memorandum was intentionally withheld from disclosure in willful violation of the court's order." The district judge independently conducted a careful review of the magistrate judge's findings and recommendations in light of the objections submitted. The district judge reached the same conclusion, for the reasons mentioned by the magistrate judge and for some additional ones noted by the district judge.

Electric Engineering argues that this finding of fact was clearly erroneous. Its argument is that the Carroll memorandum had been produced to another party, Calpine, showing absence of willfulness, and that the memorandum was not so important that willfulness could be inferred from the fact of its nonproduction. Electric Engineering also argues that the nonproduction should be blamed on American Home, its performance bonding company that was managing the litigation during part of the litigation, not on Electric Engineering.

We have carefully reviewed the record and find ample support in it for the conclusions reached by the magistrate judge and district judge. The Carroll memorandum was what any experienced lawyer would call a "smoking gun." It showed that the man who knew the most about the construction project, the project manager, knew it could not be done as promised, had told the president of the company, and consciously viewed the company's conduct as a way to "have another pay day before the plug is pulled." The memorandum established that overwhelming obstacles to successful completion were known to Electric Engineering and were not the result of interference by the other participants in the project. It was a fair inference that Carroll would not have "agonized over the available evidence for the entire weekend and have made several false starts of this letter" if the substance of the letter was not viewed by him as especially agonizing and important. Willfulness was a fair...

To continue reading

Request your trial
494 cases
  • Green v. Lisa Frank, Inc.
    • United States
    • Arizona Court of Appeals
    • January 20, 2009
    ...addressed discovery violations, where the rule described in Hammond readily can be applied. See, e.g., Valley Eng'rs Inc. v. Elec. Eng'g Co., 158 F.3d 1051, 1053, 1056 (9th Cir.1998); Halaco, 843 F.2d at 378, 379-80; Fjelstad, 762 F.2d at 1336, 1338; Prof'l Seminar Consultants, Inc. v. Sino......
  • Coulter v. Kelley
    • United States
    • U.S. District Court — Western District of Arkansas
    • March 31, 2015
    ...(8th Cir. 1991). This exclusion did not apply, however, to time periods over eleven (11) days. See Valley Engineers Inc. v. Electric Engineering Co., 158 F.3d 1051, 1058-9 (9th Cir. 1998) (holding, pursuant to Rule 6, intermediate weekend days were not excluded from periods over 10 days). B......
  • Bernstein v. Bankert
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • July 31, 2013
    ...reasonable justification under the circumstances.” Harman v. Apfel, 211 F.3d 1172, 1175 (9th Cir.2000) (citing Valley Eng'rs v. Elec. Eng'g Co., 158 F.3d 1051, 1057 (9th Cir.1998), cert. denied, 526 U.S. 1064, 119 S.Ct. 1455, 143 L.Ed.2d 542 (1999)). This is not such a case. In its decision......
  • USA v. Pineda-doval
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • August 10, 2010
    ...justification under the circumstances.” Harman v. Apfel, 211 F.3d 1172, 1175 (9th Cir.2000) (citing Valley Eng'rs Inc. v. Elec. Eng'g Co., 158 F.3d 1051, 1057 (9th Cir.1998)). The photos of Reyes-Bonilla and Rivas-Vasquez, both passengers in the Suburban, were covered by the letter of the G......
  • Request a trial to view additional results
3 books & journal articles
  • Discovery
    • United States
    • James Publishing Practical Law Books Preparing for Trial in Federal Court
    • May 4, 2010
    ...disposition of cases on their merits; and (5) the availability of less drastic sanctions. Valley Eng’rs, Inc. v. Electric Eng’g Co. , 158 F.3d 1051 (9th Cir. 1998). • Sanctions may include the denial of the use of late produced documents and/or the striking of witnesses and/or the denial of......
  • Table of Cases
    • United States
    • James Publishing Practical Law Books Preparing for Trial in Federal Court
    • May 4, 2010
    ...Jackson, Mississippi , 227 F.R.D. 464 (S.D. Miss. 2005), Form 7-25 C- 837 Table of Cases -V- Valley Eng’rs, Inc. v. Electric Eng’g Co. , 158 F.3d 1051 (9th Cir. 1998), §4:138 Van Dusen v. Barrack , 376 U.S. 612 (1964), §7:55 Van Gerwen v. Guarantee Mut. Life Co. , 214 F.3d 1041, 1045 (9th C......
  • Deposing & examining the rule 30(b)(6) witness
    • United States
    • James Publishing Practical Law Books Deposing & Examining Employment Witnesses
    • March 31, 2022
    ...if it merely applies law to lies. True facts must be the foundation for any just result.” Valley Engineers Inc. v. Elec. Eng’g Co., 158 F.3d 1051, 1058 (9th Cir. 1998). I. BACKGROUND Plaintiff Jane Smith (“Smith”) has alleged in her Second Amended Complaint (hereinafter “SAC”) that Defendan......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT