Van Den Hoek v. Bradwisch

Decision Date29 December 1978
Docket NumberNo. 12287,12287
Citation273 N.W.2d 152
PartiesLaverne VAN DEN HOEK, Plaintiff and Respondent, v. Robert BRADWISCH, Defendant and Appellant.
CourtSouth Dakota Supreme Court

Douglas Luebke, of Horstman, Braley & Luebke, Corsica, for plaintiff and respondent.

Charles Rick Johnson, of Johnson, Johnson & Eklund, Gregory, for defendant and appellant.

PORTER, Justice.

CASE SUMMARY

Plaintiff-respondent Van Den Hoek (contractor) brought this action against defendant-appellant Bradwisch (owner), seeking to recover the balance due on a contract to construct a house. The trial court entered a judgment in favor of the contractor for $5,650.00 based on a jury verdict in that amount. We hold that the trial court's instructions allowed the jury to give the contractor damages based on the contract price, whether the contractor substantially performed the contract or not. Thus the jury was not required to determine the question of substantial performance. Since this critical factual question remains undetermined, we reverse the judgment and remand for a new trial.

FACTS

The owner and the contractor entered into a contract whereby the contractor agreed to construct a house in Stickney. The contractor prepared a written agreement in April, 1973, and the parties met in May of the same year to agree on details. The owner expressed a desire to have the house completed by August 1, 1973, and the contractor said he would make an effort to complete the house as soon as possible. There was, however, no completion date in the written contract.

The contractor began construction of the house in May, 1973. During construction, the parties discussed various additions, and although the evidence conflicted, the contractor testified that the owner requested additions with a value of over $2,000.00. The parties apparently did not agree on a price for these additions to the contract.

The house was enclosed by July, 1973, and inside work continued. In July or August, the owner became dissatisfied with the pace of the work. He testified that the contractor left sometime in July or August and did not get back to the project until September 26, 1973. The owner moved into the house on October 1, 1973, even though the furnace was not hooked up and the plumbing was only partially completed.

The testimony of the parties conflicts as to occurrences after October 1, 1973. The contractor testified that he tried to come back to complete inside work on November 20, 1973, and was refused admission to the house. The owner testified that he became aware of certain construction and plumbing defects in November or December, 1973, and called a state plumbing inspector. The inspector's report is a part of the record and lists numerous violations of state plumbing regulations. The owner testified further that he never refused admission to the contractor in 1973, and that the contractor did some plumbing on December 8, 1973. The contractor said he had no recollection of being at the owner's house on December 8, 1973.

Although the parties did talk with one another during the next few months, the contractor did not attempt to complete any further work until March, 1974. By this time, mechanics liens had been filed against the property by suppliers of materials whom the contractor had not paid. The owner testified that he told the contractor to have the liens discharged before he did any further work on the house. The contractor testified that the owner refused to let him work on the house after March, 1974. He also claimed that the owner converted tools and materials left at the site.

The owner claims that the construction was defective in a number of particulars. The greatest fault is said to be in the plumbing. The plumbing defects are set forth in the state plumbing inspector's report. The owner hired a plumber to correct some of these defects, but most of them remained uncorrected to the date of trial, even though the owner and his family were living in the house. The owner also claims that the electrical wiring was incomplete and that he spent nearly $400.00 to complete it. Numerous other defects and unfinished work are also claimed.

The contractor claims that the work was substantially completed, and that the owner prevented him from completing the rest and from correcting defects in original construction.

The jury returned a verdict of $5,650.00 in favor of the contractor. The trial court entered judgment in this amount. The owner appeals.

ISSUE

The issue dispositive of this appeal is: Do the instructions adequately set out the rule of substantial performance of construction contracts as it relates to the measures of damages applicable under that rule? We conclude that the instructions misdirected the jury.

DECISION

We have long recognized the rule of substantial performance of building contracts. We first stated the rule in Aldrich v. Wilmarth, 3 S.D. 523, 54 N.W. 811 (1893): "But where the builders have in good faith Intended to and Have substantially complied with their contract, although there may be Slight defects caused by inadvertence or unintentional omissions, they may recover the contract price, less the damages sustained on account of such defects." (Emphasis supplied). The other cases recognizing this doctrine are collected in Dixon v. Nelson, 79 S.D. 44, 48, 107 N.W.2d 505, 507 (1961).

As we said in Dixon supra, no absolute criteria prevail whereby the courts determine whether performance is sufficient to invoke this doctrine. In Hulst v. Benevolent Hall Ass'n, 9 S.D. 144, 68 N.W. 200 (1896), we held that defects not easily remedied, and not caused by inadvertence, were sufficient to...

To continue reading

Request your trial
7 cases
  • Barton Masonry, Inc. v. Varilek
    • United States
    • South Dakota Supreme Court
    • 19 d2 Novembro d2 1985
    ...who sues to recover on a construction contract has the burden of proving substantial performance of that contract. See Van Den Hoek v. Bradwisch, 273 N.W.2d 152 (S.D.1978). See also, Regan v. Moyle Petroleum Co., 344 N.W.2d 695 (S.D.1984), for the proposition that the party who asserts the ......
  • Ahlers Bldg. Supply, Inc. v. Larsen, 18686
    • United States
    • South Dakota Supreme Court
    • 15 d3 Fevereiro d3 1995
    ...Cedric Sanders Company, 80 S.D. 426, 125 N.W.2d 496 (1963); Woodford v. Kelley, 18 S.D. 615, 101 N.W. 1069 (1904). Van Den Hoek v. Bradwisch, 273 N.W.2d 152, 154 (S.D.1978). The trial court never specified whether it used the "substantial performance" test or some other precept to assess Ah......
  • Rosebud Sioux Tribe v. A & P Steel, Inc.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • 10 d3 Maio d3 1989
    ...South Dakota, the question of substantial performance of construction contracts is considered essentially factual. Van Den Hoek v. Bradwisch, 273 N.W.2d 152, 154 (S.D.1978). If doubt exists, then the question of substantial performance is for the trier of fact; if the inferences are certain......
  • Reif v. Smith, 13345
    • United States
    • South Dakota Supreme Court
    • 26 d3 Maio d3 1982
    ...of making the structure conform to the contract. Northern Farm Supply, Inc. v. Sprecher, 307 N.W.2d 870 (S.D.1981); Van Den Hoek v. Bradwisch, 273 N.W.2d 152, 154 (S.D.1978); Dittmer v. Nokleberg, 219 N.W.2d 201, 209 (N.D.1974). Here, we are concerned with the amount Smiths received as an o......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT