VanVelsor v. Dzewaltowski, 181-77

Decision Date04 April 1978
Docket NumberNo. 181-77,181-77
Citation136 Vt. 103,385 A.2d 1102
PartiesWesley VanVELSOR v. John J. DZEWALTOWSKI and Arlene Dzewaltowski.
CourtVermont Supreme Court

Divoll & Doores, P.C., Bellows Falls, for plaintiff.

Fink & Birmingham, Ludlow, for defendants.

Before BARNEY, C. J., and DALEY, LARROW, BILLINGS and HILL, JJ.

BILLINGS, Justice.

In March, 1973, plaintiff, a builder, contracted with defendants to construct an exterior shell of a house on defendants' property for a contract price of $20,900.00. During the course of construction, plaintiff at the request of the defendants performed certain additional labor and provided certain additional materials for an added cost of $1,482.43 to defendants. In October, defendants became dissatisfied with the plaintiff's work and ordered him to cease operations. The work was substantially completed at that time. As shown by the detailed final invoice submitted to defendants, defendants had paid plaintiff $15,400.00 of the contract price, and plaintiff estimated that his cost to complete the contract would be $1,303.80.

The plaintiff sued defendants for the balance due under the contract less plaintiff's cost for time and material necessary to complete the contract. The defendants filed a counterclaim that, in essence, alleged plaintiff's prior breaches forced defendants to terminate the contract; they sought damages for their cost in curing alleged defects in the work and in completing the contract.

The trial court gave plaintiff judgment for $5,678.63, the amount due under the contract less the credit of $1,303.80. The trial court also gave judgment to the defendants on their counterclaim in the amount of $3,869.92, which is a sum paid by defendants to a contractor and supplier for labor and material necessary to complete the contract. Only plaintiff has appealed.

Plaintiff has raised numerous claims of error on appeal. In view of our disposition of this matter, we need only be concerned with three of them. First, plaintiff alleges that the trial court failed to find essential facts necessary to support its judgment on defendants' counterclaim. Secondly, plaintiff charges that the trial court erred when it denied interest to the plaintiff on his judgment. Lastly, plaintiff claims that the trial court erred by deducting from plaintiff's judgment his cost to complete the contract, while giving defendants judgment for their cost to complete the contract, thereby granting defendants a double recovery on their claim.

In an action for breach of a construction contract, the measure of damages depends upon which party breached the contract. Where the owner breaches the contract by demanding that the work shall stop, the contractor is entitled to recover the contract price less his cost to perform the remainder of the contract. 5 A. Corbin, Contracts § 1094 (1964); see Gibson v. Wheldon, 82 Vt. 175, 180, 72 A. 909, 911-12 (1909). On the other hand, if the contractor breaches the contract by defective construction, whether the breach is partial or total, or by refusal or failure to complete the work, "the (owner) can get a judgment for damages measured by the reasonable cost of reconstruction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste." 5 A. Corbin, supra, § 1089, at 485. In particular, if the contractor has rendered substantial performance of the contract, failing only in some minor particulars, the owner may set off against the contract price a fair allowance to make good the defects. Vermont Structural Steel Corp. v. Brickman, 126 Vt. 520, 523, 236 A.2d 658, 660 (1967).

The measure of damages applicable to the instant situation depends upon whether defendants were justified in terminating the contract. Inexplicably, ...

To continue reading

Request your trial
26 cases
  • Rutz v. Essex Junction Prudential Committee
    • United States
    • Vermont Supreme Court
    • January 27, 1983
  • Post & Beam Equities Grp., LLC v. Sunne Vill. Dev. Prop. Owners Ass'n
    • United States
    • Vermont Supreme Court
    • May 15, 2015
    ...the contract price, [the contractor's] cost of completion and other costs avoided.” (citations omitted)); VanVelsor v. Dzewaltowski,136 Vt. 103, 105, 385 A.2d 1102, 1104 (1978)(“Where the owner breaches the contract ..., the contractor is entitled to recover the contract price less [the] co......
  • Fletcher Hill, Inc. v. Crosbie
    • United States
    • Vermont Supreme Court
    • January 14, 2005
    ...make that payment. ¶ 25. The trial court instructed the jury on the law, drawing heavily on our decision in VanVelsor v. Dzewaltowski, 136 Vt. 103, 105-06, 385 A.2d 1102, 1104 (1978). Dzewaltowski provides one possible outcome of a builder/owner contract dispute: "[I]f the contractor has re......
  • Winey v. William E. Dailey, Inc.
    • United States
    • Vermont Supreme Court
    • November 5, 1993
    ...in breach of contract actions. See Eccomunity, Inc. v. Lussier, 147 Vt. 276, 279, 514 A.2d 711, 714 (1986); VanVelsor v. Dzewaltowski, 136 Vt. 103, 106, 385 A.2d 1102, 1104 (1978). However, our more recent decisions have announced a general rule, applicable in either tort or contract action......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT