Vincenzi v. Cerro

Decision Date06 April 1982
Citation442 A.2d 1352,186 Conn. 612
CourtConnecticut Supreme Court
PartiesWilliam VINCENZI et al. v. Giovanni CERRO et al.

Joseph M. Brophy, Westport, for appellants-cross appellees (defendants).

Robert R. Sheldon, with whom, on the brief, were T. Paul Tremont and Thomas M. Yuditski, Bridgeport, for appellees-cross appellants (plaintiffs).

Before SPEZIALE, C. J., and PETERS, HEALEY, PARSKEY and SHEA, JJ.

SHEA, Associate Justice.

In this suit on a building contract the trial court found that a balance of $20,015.40 plus interest was owed by the defendant owners for their home which the plaintiffs had constructed. From the judgment rendered the defendants have appealed claiming error in the conclusion of the trial court that the plaintiffs were entitled to recover on the basis of the contract price by virtue of their substantial performance of the work; in allowing the plaintiffs to be compensated for certain extra work not included in the original contract; in disallowing wholly or partially the setoffs claimed by the defendants for delay, correction of defective work, and finishing some items of the contract which the plaintiffs failed to complete; and in awarding the amount of interest included in the judgment. The plaintiffs have cross appealed claiming only that the calculation of interest was erroneous and prejudicial to them.

During oral argument the plaintiffs confessed error in the award of $100 as an extra charge for insulating the basement of the house as required by the building code and also conceded that the trial court should not have used eight percent as the legal rate for the calculation of interest for the portion of the period involved prior to October 1, 1979, when General Statutes § 37-1(a) was amended to change the legal rate from six to eight percent per year. Public Acts 1979, No. 79-364, § 1. The defendants also confessed error with respect to the interest award by virtue of the allowance of interest only to the date of trial rather than to the date of judgment. The parties agreed that they would be able to recalculate the amount of the damages with these revisions.

In a memorandum of decision the trial court set forth the facts in commendable detail. On October 5, 1976, the parties signed a written contract for the plaintiffs to construct a three-family house on land owned by the defendants in Bridgeport. The contract price was $91,000, to be paid in five installments as various stages of the work were finished. The house was to be completed within 150 days from the date of the execution of the contract, which would make the projected completion date March 4, 1977. Except for $2000 withheld for incomplete items, the first four scheduled payments were made. The payments made totaled $67,100, leaving a balance of $23,900 on the contract price. In August, 1977, the plaintiffs demanded this balance, but the defendants refused on the ground that the house was not complete and that some work was defective. The court found that the work was not finished at that time because the heating system was not approved until October, 1977, and a certificate of occupancy was not issued until November 9, 1977. This date, when the certificate of occupancy was obtained, was deemed by the trial court to be the date when the contract had been substantially performed by the plaintiffs.

The judgment awarded the plaintiffs the balance of the contract price, $23,900, plus certain extras totalling $1118.30, but deducted therefrom $5002.90 for defective or incomplete work and for the loss of rent suffered by the defendants for the period of unjustifiable delay.

The principal claim of the defendants is that the doctrine of substantial performance was inapplicable in this case because the plaintiffs were guilty of a wilful or intentional breach of contract by failing to complete all of the work required. "There is no reason why one who has substantially performed such a contract, but unintentionally failed of strict performance in the matter of minor details, should have imposed upon him as a condition of recovery for that of which the other party has received the benefit, the burden of showing by direct evidence its reasonable value, or why he should be deprived of all benefit of the contract which he has substantially performed." Daly & Sons v. New Haven Hotel Co., 91 Conn. 280, 287-88, 99 A. 853 (1917). The defendants rely on this articulation of the doctrine of substantial performance, which is also quoted in the memorandum of decision, as indicating that a builder who has failed to complete his contract fully may not invoke its benefit unless he was prevented from doing so by some circumstance beyond his control, such as interference by the owner. We have in several cases approved the common statement that a contractor who is guilty of a "wilful" breach cannot maintain an action upon the contract. Morici v. Jarvie, 137 Conn. 97, 100, 75 A.2d 47 (1950); Kelley v. Hance, 108 Conn. 186, 189, 142 A. 683 (1928); Tice v. Moore, 82 Conn. 244, 249, 73 A. 133 (1909); see 3A Corbin, Contracts § 707. The contemporary view, however, is that even a conscious and intentional departure from the contract specifications will not...

To continue reading

Request your trial
21 cases
  • Foley v. Huntington Co.
    • United States
    • Connecticut Court of Appeals
    • 27 d2 Agosto d2 1996
    ...so as to invoke the other's obligation to pay a liquidated sum or to provide services under the contract. See Vincenzi v. Cerro, 186 Conn. 612, 442 A.2d 1352 (1982); Cecio Bros., Inc. v. Feldmann, supra, 161 Conn. at 265, 287 A.2d 374. On the basis of our review of the applicable cases, we ......
  • Aetna Cas. and Sur. Co. v. Murphy
    • United States
    • Connecticut Supreme Court
    • 1 d2 Março d2 1988
    ...an action against the owner on the contract. Grenier v. Compratt Construction Co., supra, 148-49, 454 A.2d 1289; Vincenzi v. Cerro, 186 Conn. 612, 615, 442 A.2d 1352 (1982). In contracts for the sale of real property, the fact that a contract states a date for performance does not necessari......
  • State v. Periere
    • United States
    • Connecticut Supreme Court
    • 6 d2 Abril d2 1982
  • DuBaldo Elec., LLC v. Montagno Const., Inc.
    • United States
    • Connecticut Court of Appeals
    • 23 d2 Fevereiro d2 2010
    ...termination from the job, that incidental action does not negate a finding of substantial performance." Relying on Vincenzi v. Cerro, 186 Conn. 612, 442 A.2d 1352 (1982), the defendants assert that the doctrine of substantial performance is inapplicable because DuBaldo intentionally breache......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT