Wagner Interior Supply of Wichita, Inc. v. Dynamic Drywall, Inc.

Decision Date24 February 2017
Docket NumberNo. 113,037,113,037
Citation389 P.3d 205,305 Kan. 828
Parties WAGNER INTERIOR SUPPLY OF WICHITA, INC., Appellant, v. DYNAMIC DRYWALL, INC., et al., Defendants, (Puetz Corporation and United Fire & Casualty Company), Appellees.
CourtKansas Supreme Court

Vincent F. O'Flaherty, of Law Offices of Vincent F. O'Flaherty, Attorney, LLC, of Kansas City, Missouri, argued the cause and was on the briefs for appellant.

Ryan M. Peck, of Morris, Laing, Evans, Brock & Kennedy, Chartered, of Wichita, argued the cause, and Nanette Turner Kalcik and Richard A. Kear, of the same firm, were with him on the briefs for appellees.

The opinion of the court was delivered by Stutzman, J.:

Puetz Corporation (Puetz) was the general contractor to build a hotel in Wichita, Kansas. One of its subcontractors, Dynamic Drywall, Inc. (Dynamic), obtained materials for its part of the project from Wagner Interior Supply of Wichita, Inc. (Wagner), but failed to pay for them. Wagner filed a lien statement with the district court in Sedgwick County, claiming a lien against the hotel property. The owner of the hotel, Wichita Hospitality Group, LLC, was in the process of refinancing the project and Wagner's lien stood as a cloud on the title, so Puetz filed a bond with the district court to secure payment of Wagner's claim. With approval of the bond by the district court came the discharge of the lien under the terms of K.S.A. 60–1110.

Puetz contends Wagner's lien was defective because it had not been properly perfected, so the lien could have been challenged and removed, preventing foreclosure, had there been time for litigation. Although it chose to file the bond rather than litigate the lien, Puetz claims the opportunity was not lost, as its argument about the defects in Wagner's lien filing survived the release of the lien and still can be asserted as a defense to Wagner's claim against the bond. Wagner takes the position that any defenses Puetz may have had against the lien filing have no relevance now, since the filing of the approved bond discharged the lien. The district court reviewed summary judgment motions from both Puetz and Wagner and granted judgment to Puetz. On Wagner's appeal, the Court of Appeals reversed the district court. We affirm that decision.

FACTS AND PROCEDURAL BACKGROUND

In September 2012, Wichita Hospitality Group engaged Puetz to act as general contractor for the construction of a new Holiday Inn Express & Suites hotel in Wichita. Puetz subcontracted the drywall work on the project to Dynamic and paid Dynamic for its part of the work. Dynamic ordered materials for the project from Wagner, but it did not pay for those materials that Wagner provided and that were used in the construction. Dynamic later filed a petition for bankruptcy relief.

Near the end of November 2013, Wagner, as an unpaid supplier, filed a lien statement with the clerk of the district court of Sedgwick County, claiming a lien against the hotel property in the amount of its unpaid claim, $108,162.97. At the time Wagner filed its lien statement, Wichita Hospitality Group was refinancing the hotel and Wagner's filing placed a cloud on the title, affecting the refinancing. To clear that problem, Puetz presented a bond to the district court pursuant to K.S.A. 60–1110, titled "Release of Lien Bond" with Puetz as principal and United Fire & Casualty Company (United) as surety, specifically securing the payment of Wagner's claim. Under the provisions of that statute, once the bond was approved by a judge of the district court and filed with the court clerk, Wagner's lien was discharged. The approved bond was filed on January 13, 2014.

In February 2014, Wagner filed suit against Dynamic, Puetz, and United for payment for the materials it had supplied to Dynamic for the hotel. Wagner made a claim against the bond for the money it was owed and sought damages from Dynamic and Puetz for unjust enrichment. Both sides filed motions for summary judgment and, in November 2014, the district court entered an order granting summary judgment to Puetz and United. Wagner's claim against Dynamic was stayed because of Dynamic's bankruptcy.

On Wagner's timely appeal, the Court of Appeals reversed the order of the district court and directed that judgment be granted to Wagner. See Wagner Interior Supply of Wichita, Inc. v. Dynamic Drywall, Inc. , No. 113037, 2015 WL 5750465 (Kan. App. 2015) (unpublished opinion).

ANALYSIS

Standard of review

The case is before us to review the district court's order for summary judgment that was reversed by the Court of Appeals. Our standard of review is de novo.

"On appeal from summary judgment, an appellate court applies the same rules as the district court, and where the appellate court finds reasonable minds could differ as to the conclusions drawn from the evidence, summary judgment must be denied. Miller [v. Westport Ins. Corp. ], 288 Kan. [27] at 32[, 200 P.3d 419 (2009) ]. When material facts are uncontroverted, as they are in this case, an appellate court reviews summary judgment de novo. Troutman v. Curtis , 286 Kan. 452, Syl. ¶ 1, 185 P.3d 930 (2008) ; Klein v. Oppenheimer & Co. , 281 Kan. 330, Syl. ¶ 7, 130 P.3d 569 (2006)." Adams v. Board of Sedgwick County Comm'rs , 289 Kan. 577, 584, 214 P.3d 1173 (2009).

We also are required to interpret and apply K.S.A. 60–1110 to undisputed facts. When engaging in statutory interpretation we exercise unlimited review. Redd v. Kansas Truck Center , 291 Kan. 176, 187, 239 P.3d 66 (2010).

Discussion

A mechanic's lien is purely a statutory creation and, to create an enforceable lien, the requirements of the statute must be followed strictly. Haz–Mat Response, Inc. v. Certified Waste Services Ltd. , 259 Kan. 166, 170, 910 P.2d 839 (1996). K.S.A. 60–1102(a) and 60–1103(a) prescribe the requirements for an unpaid supplier to perfect a lien against the real estate where the materials were used.

The Kansas mechanic's lien law is remedial, providing effective security to anyone furnishing labor, equipment, material, or supplies used or consumed for the improvement of real property under a contract with the owner. The theory behind granting a lien against the property is that the property benefitting from the improvement should be charged with payment for the labor, equipment, material, or supplies used in the improvement. Haz–Mat Response, Inc. , 259 Kan. at 170, 910 P.2d 839.

Since the facts are undisputed, the arguments raised by Puetz and Wagner center on K.S.A. 60–1110, which provides:

"The contractor or owner may execute a bond to the state of Kansas for the use of all persons in whose favor liens might accrue by virtue of this act, conditioned for the payment of all claims which might be the basis of liens in a sum not less than the contract price, or to any person claiming a lien which is disputed by the owner or contractor, conditioned for the payment of such claim in the amount thereof. Any such bond shall have good and sufficient sureties, be approved by a judge of the district court and filed with the clerk of the district court. When bond is approved and filed, no lien for the labor, equipment, material or supplies under contract, or claim described or referred to in the bond shall attach under this act, and if when such bond is filed liens have already been filed, such liens are discharged. Suit may be brought on such bond by any person interested but no such suit shall name as defendant any person who is neither a principal or surety on such bond, nor contractually liable for the payment of the claim."

Puetz maintains that when it filed the approved bond, its defense against the defectively filed lien merely migrated over to become a defense against the claim by Wagner against the bond. As Puetz sees it, any other interpretation would act to cure the errors Wagner made in filing its lien, and K.S.A. 60–1110 was not intended to improve the position of a party who had attempted, but failed, to file an effective lien. Wagner, however, contends the statute specifically discharged the lien when the approved bond was filed, and with the lien went any arguments about its validity. Both Puetz and Wagner insist the statute is absolutely clear in support of their opposite interpretations.

We considered the requirements for claims against a statutory lien bond in Murphree v. Trinity Universal Ins. Co. , 176 Kan. 290, 269 P.2d 1025 (1954). The issue was whether claims could be made against the contractor's statutory bond for materials and labor that were not provided to the contractor or a subcontractor, but were directly requested by and furnished to the owner. We held those who carried out their transactions directly with the owner had no claim against the contractor's bond. 176 Kan. at 294, 269 P.2d 1025. We also discussed the nature of the statutory bond and observed:

"[W]hen the bond is filed a claimant is not required to file a lien statement in order to preserve his rights—he may then look to the bond for recovery—but other than this the bond effects no change in the rights and relations of the parties. A claimant can recover on the bond only if in its absence he could have perfected and enforced a lien." 176 Kan. at 294, 269 P.2d 1025.

We again took up a question on the right to claim against a statutory lien bond in Bob Eldridge Constr. Co., Inc. v. Pioneer Materials, Inc. , 235 Kan. 599, 684 P.2d 355 (1984). The facts in Eldridge bear many similarities to those in the present case and both parties have given it substantial attention.

The Bob Eldridge Construction case

Bob Eldridge Construction Company, Inc. (Eldridge), was a general contractor building two apartment buildings for the elderly in Haysville and Wichita. Eldridge subcontracted its drywall work on the project to R & S Construction Company (R & S). Pioneer Materials, Inc. (Pioneer), supplied all drywall for the two buildings, under an arrangement by which Eldridge and R & S would call to place orders as they were needed. R & S left the...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT