Walker v. Tenneco Oil Co., 79-2189

Decision Date25 April 1980
Docket NumberNo. 79-2189,79-2189
PartiesHoward L. WALKER, Plaintiff-Appellant, v. TENNECO OIL COMPANY, Defendant-Appellee. Summary Calendar. *
CourtU.S. Court of Appeals — Fifth Circuit

George A. Flournoy, Leonard Fuhrer, Alexandria, La., for plaintiff-appellant.

Edward J. Koehl, Jr., New Orleans, La., for defendant-appellee.

Appeal from the United States District Court for the Eastern District of Louisiana.

Before GEE, HENDERSON and HATCHETT, Circuit Judges.

PER CURIAM:

Howard Walker was injured on February 7, 1977, in an accident on a fixed offshore oil drilling platform located on the Outer Continental Shelf in the Gulf of Mexico, off the coast of Louisiana. Separate actions were instituted against appellee Tenneco Oil Company, the owner of the fixed platform, by appellant and Ray Mallory, 1 both of whom were employees of Hydraulic Workover, Inc. (HWI), an independent contractor that had contracted with Tenneco to perform workover operations on the platform. Tenneco filed third-party complaints in each action against HWI, seeking contractual indemnity. The actions were consolidated for trial. The third-party claims were severed from the main demands, which were tried before a jury.

Because of flowage problems with one of its wells, Tenneco found it necessary to obtain from HWI a "snubbing unit" and a four-man, specialized crew proficient in the operation of the unit and the type of work involved. The snubbing unit, a hydraulic jacking mechanism designed to allow lengths of pipe to be forced into and pulled out of a pressurized well, is portable and was secured to this well by eight bolts. The entire unit could be assembled or disassembled in approximately two hours. The snubbing unit had been used by HWI to service the wells at another platform earlier in the week and had been on the platform in question for only two or three days before the accident.

HWI's four-man crew consisted of an operator (Bill Walker, appellant's brother) and three helpers, including appellant. On the morning of the accident, a Tenneco supervisor on another platform eighty miles to the west phoned Bill Walker to discuss a problem in connecting an HWI blowout preventer stack. Bill Walker was requested by Tenneco to go to the distant platform to oversee that operation. He did so, even though none of his helpers had ever worked on a crew with fewer than four members or where there was no operator. Appellant had never worked with any of the other crew members nor had he ever worked in the basket where the controls were located. In fact, he was the least experienced member of the crew.

At the time of the accident, appellant and Mallory were attempting to remove the traveling slips (two large, vice-like pieces of metal which clamp onto the pipe as it is pulled out of the well by the snubbing unit) from the jack assembly. The traveling slips rested on four bolts. Counterbalance cables, which extended through a pulley at the top of the gin pole, were tied to both sides of the slips. The control knobs on the cables were activated and set by either appellant or Mallory. There is no dispute that the controls were excessively set. The slips became cocked or jammed and appellant was shaking the cables in an attempt to loosen the slips and to get an even, balanced pull on them when they suddenly came free, flinging appellant through the air with a slingshot effect; he fell to the platform and suffered injuries to his feet and ankles. No other part of the unit fell or collapsed. At the time of the accident the counterbalance controls were in good working order and not defective.

No Tenneco employees were near the snubbing unit at the time of the accident. Appellant had never operated the snubbing unit and had limited experience with the counterbalance controls. Prior to the accident, Mallory had never removed the slips outside an operator's presence.

At the close of appellant's evidence, Tenneco moved for a directed verdict on the strict liability and negligence claims. The court granted the motion on the strict liability claim but submitted the negligence issue to the jury. The jury returned a verdict of no negligence on the part of Tenneco and the court entered a judgment dismissing appellant's action.

Strict Liability

Walker contends that the district court erred in directing a verdict on the strict liability claim by misconstruing the Louisiana Supreme Court's decision in Olsen v. Shell Oil Co., 365 So.2d 1285 (La.1978). A directed verdict is proper only when, considering all the evidence and inferences therefrom in the light most favorable to the opposing party, the district court determines that a reasonable minded jury could not reach a contrary verdict. Boeing Co. v. Shipman, 411 F.2d 365, 374-75 (5th Cir. 1969) (en banc). See also MacKenzie v. Chrysler Corp., 607 F.2d 1162, 1165 n. 4 (5th Cir. 1979).

Louisiana law governs this tort action brought under the Outer Continental Shelf Lands Act (OCSLA), 43 U.S.C. § 1333(a)(2). Mott v. Odeco, 577 F.2d 273, 275 n. 2 (5th Cir. 1978); Olsen at 1288 n. 2. Appellant seeks to impose strict liability upon Tenneco pursuant to La.Civ.Code art. 2322:

The owner of a building is answerable for the damage occasioned by its ruin, when this is caused by neglect to repair it, or when it is the result of a vice in its original construction.

In Olsen, the Louisiana Supreme Court interpreted article 2322 to impose a non-delegable duty on an owner to keep his or her building and its appurtenances in repair in order to avoid injury to others, with the failure to comply resulting in the imposition of strict liability. See 365 So.2d at 1288-89, 1291; Champagne v. Chevron U.S.A., Inc., 605 F.2d 934, 936 (5th Cir. 1979). To impose liability under article 2322, the following requirements must be met:

(1) There must be a building; (2) the defendant must be its owner; and (3) there must be a "ruin" caused by a vice in construction or a neglect to repair, which occasions the damage sought to be recovered.

Olsen at 1289. There is no doubt that Tenneco's fixed drilling platform constitutes a "building" under the article. Mott at 275 n. 3; Olsen at 1290. Two questions remain: First, was the snubbing unit a necessary "appurtenant" structure to the "building" made "immovable" by attachment? See Olsen at 1291. Second, was the unit defectively manufactured or rendered unsafe by any act or omission by Tenneco? See id. at 1289.

Prior cases impose liability under article 2322 on the owner of a "building" for such "appurtenances" as a defective fire hose, water heater, elevator, window fan, or electrical wiring contained within the "building." See Champagne at 936; Olsen at 1291 n. 12. Most of these items share a common characteristic not found in the snubbing unit: they were, with some degree of permanence, an integral part of the building. However, a window fan is probably no more permanent than is this unit. Furthermore, most equipment on drilling platforms can be moved from one platform to another as the need for it arises. We thus hesitate to say with certainty that the snubbing unit is not an "appurtenant" structure under Louisiana law, since such a holding might have widespread ramifications on the Outer Continental Shelf.

Nevertheless, a directed verdict was proper under Boeing Co. v. Shipman, supra, because there was no evidence of a defect in the unit nor any proof of any negligent handling of the unit by Tenneco. On the contrary, undisputed evidence showed that either plaintiff or Mallory had set the counterbalance controls too high, causing the accident. Improper handling by either of them would absolve Tenneco of strict liability under art. 2322 and the Olsen doctrine. See Champagne at 936; Olsen at 1289, 1293-94 & n. 15.

Jury Charge

Walker also asserts...

To continue reading

Request your trial
12 cases
  • Tidelands Royalty B Corp. v. Gulf Oil Corp., CA 3-79-0244-R.
    • United States
    • U.S. District Court — Northern District of Texas
    • June 18, 1985
    ...lie within any boundary lines projected outward from Louisiana, as contemplated by § 1333(a)(2)(A). 11 See, e.g., Walker v. Tenneco Oil Co., 615 F.2d 1121 (5th Cir.1980); Mott v. ODECO, 577 F.2d 273 (5th Cir.1978), cert. denied, 440 U.S. 912, 99 S.Ct. 1226, 59 L.Ed.2d 461; Moczygemba v. Dan......
  • Buxton v. Amoco Oil Co.
    • United States
    • U.S. District Court — Western District of Louisiana
    • November 20, 1987
    ...which recovery is sought. Steele v. Helmerich & Payne Internat'l Drilling Co., 738 F.2d 703, 704 (5th Cir.1984); Walker v. Tenneco Oil Co., 615 F.2d 1121, 1123-24 (5th Cir.1980); Olsen v. Shell Oil Co., 365 So.2d 1285, 1289 (La.1979). An offshore fixed platform constitutes a "building" with......
  • Coulter v. Texaco, Inc.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • July 29, 1997
    ...v. Shell Oil Co., 365 So.2d 1285, 1289 (La.1978).14 Id. at 1289-90.15 See Entrevia, 427 So.2d at 1148.16 See Walker v. Tenneco Oil Co., 615 F.2d 1121, 1124 (5th Cir.1980) (pretermitting a definitive holding on this same "appurtenance" issue because of its "widespread ramifications").17 365 ......
  • National Service Industries, Inc. v. Hartford Acc. & Indem. Co.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • November 16, 1981
    ...the light most favorable to the party opposing the motion, a reasonable jury could not reach a contrary verdict. Walker v. Tenneco Oil Co., 615 F.2d 1121, 1123 (5th Cir. 1980); Boeing Co. v. Shipman, 411 F.2d 365, 374-75 (5th Cir. 1969) (en banc). We conclude that the district court should ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT