Walsh Constr. Co. v. U.S. Sur. Co.

Decision Date25 September 2018
Docket NumberCivil Action No. 17-2251 (JDB)
Parties WALSH CONSTRUCTION COMPANY II, LLC, Plaintiff, v. UNITED STATES SURETY COMPANY, et al., Defendants.
CourtU.S. District Court — District of Columbia

Joseph Henry Kasimer, Mariam Wagih Tadros, Rees Broome, PC, Tysons Corner, VA, for Plaintiff.

Dylan M. Marck, Pro Hac Vice, Fred A. Mendicino, Pro Hac Vice, James J. Faughnan, Faughnan Mendicino PLLC, Dulles, VA, for Defendants.

MEMORANDUM OPINION

JOHN D. BATES, United States District Judge

Two parties to a construction bond each claim that the other breached the bond first and thus should be liable for costs and damages. Plaintiff Walsh Construction Company II, LLC ("Walsh") is a general contractor that was hired in 2015 to construct a hotel in the District of Columbia. Defendants United States Surety Company and U.S. Specialty Insurance Company (together, "the Surety") jointly issued a performance bond to one of Walsh's subcontractors, Mid-Atlantic Air, Inc. ("MAA"), which guaranteed completion of the subcontract work.

The underlying controversy arose when Walsh declared MAA to be in default on the subcontract. Initially, the Surety financed the performance of MAA's subcontract work, but after investigating Walsh's declaration of default the Surety denied liability and stopped performing under the bond. Walsh then sued the Surety, and the Surety counterclaimed, alleging that Walsh had breached both the bond and the underlying subcontract. See Answer & Countercl. ("Countercl.") [ECF No. 12]. Walsh now moves to dismiss the counterclaim. See Walsh Constr. Co. II, LLC's Mem. in Supp. of Its Mot. to Dismiss Countercl. ("Walsh's Mot.") [ECF No. 14]. For the following reasons, Walsh's motion will be granted in part and denied in part.

BACKGROUND 1

In 2015, a company called Adams Morgan Hotel Owner, LLC (the "Owner") hired Walsh to construct the Adams Morgan Historic Hotel in northwestern Washington, D.C. See Countercl. ¶ 4.2 Shortly thereafter, MAA subcontracted with Walsh to perform heating, ventilation, air conditioning, and plumbing work on the hotel. See Compl. [ECF No. 2] ¶ 7. In addition to that work, the subcontract required MAA to perform "any and all changes [to its] Work" that Walsh might later order, for which MAA would be paid "an amount equal to the direct cost of labor and materials actually and reasonably used ..., plus mark up for overhead and profit." See Ex. 2 to Walsh's Mot. ("Subcontract Agreement") [ECF No. 14-3] ¶¶ 4.1–4.2. As a condition of the subcontract, MAA and the Surety executed a performance bond, which guaranteed MAA's performance of the subcontract and named Walsh as an obligee. Countercl. ¶¶ 6–7. MAA and the Surety also entered into a payment bond, which required the Surety to compensate MAA's subcontractors and suppliers in the event of MAA's default. Id. ¶¶ 6, 93.

MAA performed its obligations under the subcontract until April 6, 2017, when MAA notified Walsh in writing that it would not complete any further change-order or overtime work because of several unpaid change-order invoices totaling more than $2 million. See Ex. B. to Countercl. [ECF No. 12].3 Two weeks later, on April 20, 2017, Walsh declared MAA to be in default of the subcontract and terminated the agreement, alleging that MAA had breached by failing to complete its work on time. See Ex. 4. to Compl. at 2–3.

After declaring MAA to be in default, Walsh issued a demand to the Surety under the performance bond. See id. at 1. The Surety began investigating Walsh's claim of default, and the Surety later exercised its option to extend its deadline to respond to Walsh's claim by financing performance of the subcontract during the extension period. Countercl. ¶ 44. The Surety financed performance from May 5, 2017 through July 28, 2017 ("the financing period") and retained a replacement subcontractor for MAA during that time. Countercl. ¶¶ 45, 54. During this period, the Surety alleges that it spent more than $6.2 million on the project: over $4 million to finance the subcontract work itself, and an additional $2.2 million to compensate MAA's subcontractors and suppliers for work and materials tendered before Walsh's declaration of default. See Countercl. ¶ 93. On July 28, the Surety completed its investigation, denied liability under the bond, and ceased financing the subcontract work. Countercl. ¶ 92; see Ex. O to Countercl.

Following the Surety's denial of liability, Walsh filed a complaint against the Surety seeking damages for its alleged breach of the performance bond. See Compl. ¶¶ 36–44.

The Surety answered Walsh's complaint, see Countercl. at 1–11, and filed a ten-count counterclaim, id. at 11–38. The Surety's counterclaim alleges that if MAA's work was delayed at all, such delays were attributable to design defects and Walsh's poor administration of the project. See Countercl. ¶¶ 28–32; U.S. Surety Co.'s & U.S. Specialty Ins. Co.'s Opp'n to Mot. to Dismiss ("Surety's Opp'n") [ECF No. 16] at 4. The Surety further alleges that Walsh failed to pay MAA on time, so any delays—as well as MAA's ultimate refusal to continue performing change orders and overtime work—were justified. See Countercl. ¶ 35. Additionally, the Surety claims that Walsh intentionally obstructed the Surety's investigation of Walsh's claim by failing timely and accurately to respond to requests for information, see Surety's Opp'n at 6–7 (citing Countercl. ¶¶ 47, 55–61, 77), and by failing timely to provide its estimate of the subcontract balance, see id. at 7–8 (citing Countercl. ¶¶ 85–86, 88–89, 92).

The Surety's counterclaim initially asserted ten counts, although the Surety later withdrew two.4 Counts One and Four allege that the Surety is entitled to recover more than $4 million that the Surety allegedly spent on the project during the financing period pursuant to Paragraph 8 of the performance bond, which requires Walsh to reimburse the Surety for its "losses, expenses[,] and reasonable attorney's fees" in the event of an unjustified declaration of default. Countercl. ¶ 101; see id. ¶¶ 94–102, ¶¶ 115–123. Count One alleges that Walsh's declaration of default was unjustified because Walsh had already materially breached the subcontract by failing to pay MAA, see id. ¶ 97, and Count Four claims that even if MAA had delayed the project, Walsh was estopped from relying on those delays for its declaration of default because it had not objected to them before the preceding week, see id. ¶¶ 119, 121.

Counts Six and Seven also allege that Walsh materially breached the subcontract. The Surety seeks to recover approximately $2.6 million that Walsh allegedly owes MAA under the subcontract, as well as the $2.2 million that the Surety claims it paid to MAA's subcontractors and suppliers following Walsh's declaration of default. See id. ¶¶ 130–39, 140–152. Count Six claims that the Surety is eligible to recover these sums because of an indemnity agreement that assigned to the Surety all of MAA's rights against Walsh under both bonds. See id. ¶¶ 137–39. Count Seven claims that the Surety is entitled to recover under the doctrine of equitable subrogation, see id. ¶¶ 147–152, which allows a party to recover in equity when it has "paid the debt of another," Nat'l Union Fire Ins. Co. of Pittsburgh v. Riggs Nat'l Bank of Wash., D.C., 646 A.2d 966, 968 (D.C. 1994).

Counts Two, Nine, and Ten allege various other breaches of the performance bond. Specifically, Count Two alleges that Walsh failed to cooperate with the Surety's investigation, see id. ¶¶ 103–108; Count Nine alleges that Walsh repudiated the bond by refusing to disclose its estimate of the subcontract balance, see id. ¶¶ 157–162; and Count Ten alleges several breaches of the covenant of good faith and fair dealing, see id. ¶¶ 163–165. Finally, Count Eight alleges that the Surety is entitled to recover the sums it paid during the financing period under the doctrines of promissory estoppel and unjust enrichment. See id. ¶¶ 153–156.

Walsh has moved to dismiss each count of the Surety's counterclaim on grounds that are explained more fully below. Walsh's motion to dismiss is now fully briefed and ripe for decision.

LEGAL STANDARD

To survive a Rule 12(b)(6) motion to dismiss for failure to state a claim, a "complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’ " Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) ). Plausibility means that the claim at issue rises "above the speculative level." Twombly, 550 U.S. at 555, 127 S.Ct. 1955. The Court must "accept all the well-pleaded factual allegations of the complaint as true and draw all reasonable inferences from those allegations in the plaintiff's favor." Banneker Ventures, LLC v. Graham, 798 F.3d 1119, 1129 (D.C. Cir. 2015) (citing Iqbal, 556 U.S. at 678, 129 S.Ct. 1937 ) ). "Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice," and a "claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged." Iqbal, 556 U.S. at 678, 129 S.Ct. 1937 (citing Twombly, 550 U.S. at 555–556, 127 S.Ct. 1955 ).

ANALYSIS
I. Claims Alleging a Breach of Paragraph 8 of the Performance Bond

In Counts One and Four of its counterclaim, the Surety seeks to recover under Paragraph 8 of the performance bond more than $4 million that it spent during the financing period. See Ex. 2 to Compl. ("Bond") [ECF No. 2-2] ¶ 8. That paragraph states: "If it is determined that [Walsh's] declaration of [MAA's] default was not justified under the Subcontract, [Walsh] shall pay Surety an amount equal to Surety's losses, expenses and reasonable attorneys' fees in performing under this Bond." Id. Paragraph 8.1 of the...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT