Ward v. Atlantic Coast Line Co, 485

Decision Date18 April 1960
Docket NumberNo. 485,485
Citation362 U.S. 396,80 S.Ct. 789,4 L.Ed.2d 820
PartiesRaymond P. WARD, Petitioner, v. ATLANTIC COAST LINE R. CO
CourtU.S. Supreme Court

Mr. Neal P. Rutledge, Miami, Fla., for petitioner.

Mr. Sam T. Dell, Jr., Gainesville, Fla., for respondent.

PER CURIAM.

In this action under the Federal Employers' Liability Act, 35 Stat. 65, as amended, 45 U.S.C. §§ 51—60, 45 U.S.C.A. §§ 51—60, the Court of Appeals for the Fifth Circuit, by a divided court, affirmed a judgment in favor of the respondent railroad entered on a jury verdict in the District Court for the Northern District of Florida. 265 F.2d 75. We granted certiorari, 361 U.S. 861, 80 S.Ct. 126, 4 L.Ed.2d 101, to consider the issues presented in the light of our decisions in Sinkler v. Missouri Pacific R. Co., 356 U.S. 326, 78 S.Ct. 758, 2 L.Ed.2d 799, and Baker v. Texas & Pacific R. Co., 359 U.S. 227, 79 S.Ct. 664, 3 L.Ed.2d 756. The latter is an intervening decision.

The railroad employed the petitioner as a laborer in a section gang with a regular work-week from Monday through Friday. The petitioner was injured on a Saturday, ordinarily the gang's day off, when the gang, super- vised by their foreman, using the work tools supplied by the railroad, adn following standard railroad methods for doing the work, were replacing ties under a siding track which ran off the railroad's main line tracks to the plant of the M. & M. Turpentine Company. That company had an agreement with the railroad calling for the railroad to make periodic inspections of the track and for the repairs disclosed to be necessary by such inspections to be made by and at the expense of the Turpentine Company 'to the satisfaction of the (railroad's) Chief Engineer.' When an inspection revealed the need for the work in question, the Turpentine Company engaged the petitioner's foreman to recruit his crew to do the work on their day off under his direction. The foreman offered the crew railroad overtime rates of pay for doing the work, but there is a sharp conflict in the evidence whether he told the crew that they would not be working for the railroad but for someone else. The foreman paid the wages with funds supplied to him by the Turpentine Company.

The petitioner contends that the proofs require a holding as a matter of law that the Turpentine Company, in the maintenance of the siding, was the 'agent' of the respondent railroad within the meaning of § 1 of the Federal Employers' Liability Act, 45 U.S.C. § 51, 45 U.S.C.A. § 51, as we construed that term in Sinkler v. Missouri Pacific R. Co., supra. We find no merit in this contention. Indeed, we do not think that the proofs presented a jury question whether the Turpentine Company was the railroad's 'agent' within the meaning of the Act. This was not a situation, as in Sinkler, in which the railroad engaged an independent contractor to perform operational activities required to carry out the franchise. This was a siding privately owned by the Turpentine Company and established to service it alone. In maintaining it, we do not see how it can be said under the proofs that the Turpen- tine Company was 'engaged in furthering the operational activities of respondent.' Sinkler v. Missouri Pacific R. Co., supra, 356 U.S. at page 331, 78 S.Ct. at page 763. Even the use of the siding by local farmers in harvest time to load respondent's cars with watermelons, a fact heavily relied upon by the petitioner, was, according to uncontradicted testimony, not at the instance of the railroad but because the President of the Turpentine Company 'leased this track—I guess that is what you would call it—anyhow, he let those farmers load watermelons out there on that track and he always repaired it every year before watermelon time.'

However, we agree with the petitioner's alternative contention that the trial judge erred in refusing to instruct the jury as requested by the petitioner, 1 and in giving the instructions he did,2 as to the factors to be considered by the jury in determining whether the petitioner was an 'employee' of the railroad during the performance of the work within the meaning of the Act. The instructions given in effect limited inquiry to the question whether the petitioner was aware that the railroad considered him not to be working for it but for some third party. But neither the railroad's communication of its concept of petitioner's status to petitioner, nor his acquiescence therein, if shown, is determinative of the issue. Cf. Cimorelli v. New York Central R. Co., 6 Cir., 148 F.2d 575, 578. The parties' characterization is but one factor to be considered among others, see Restatement, Agency 2d, § 220(2)(i), and the issue is one for determination by the jury on the basis of all the relevant factors. Baker v. Texas & Pacific R. Co., supra.

Reversed.

Mr. Justice FRANKFURTER would dismiss this writ of certiorari as improvidently granted. As the Court's opinion demonstrates, the case solely presents the appropriateness of instructions given by a trial court and the refusal of requested instructions in the light of the unique circumstances of a particular situation. As such it falls outside the considerations which, according to Rule 19 of this Court, 28 U.S.C.A., govern the granting of a petition for certiorari. See Ferguson...

To continue reading

Request your trial
153 cases
  • Community For Creative v. Reid
    • United States
    • U.S. Supreme Court
    • June 5, 1989
    ...S.Ct., at 475-476, and n. 5; id., at 332, 95 S.Ct., at 480 (Stewart, J., concurring in judgment); Ward v. Atlantic Coast Line R. Co., 362 U.S. 396, 400, 80 S.Ct. 789, 792, 4 L.Ed.2d 820 (1960); Baker, supra, 359 U.S., at 228, 79 S.Ct., at 665. This practice reflects the fact that "federal s......
  • Houston v. Lack
    • United States
    • U.S. Supreme Court
    • June 24, 1988
    ...609 F.2d 815, 816 (CA5 1980); Ward v. Atlantic Coast Line R. Co., 265 F.2d 75, 80 (CA5 1959), rev'd on other grounds, 362 U.S. 396, 80 S.Ct. 789, 4 L.Ed.2d 820 (1960); Allen v. Schnuckle, 253 F.2d 195, 197 (CA9 1958). It seems to me that to leave them undisturbed only "to the extent [they] ......
  • 42 498 Kelley v. Southern Pacific Company 8212 1270
    • United States
    • U.S. Supreme Court
    • December 23, 1974
    ...factors under law. See Restatement, Agency 2d, § 220, comment c; § 227, comment a.' Id., at 228. Ward v. Atlantic Coast Line R. Co., 362 U.S. 396, 80 S.Ct. 789, 4 L.Ed.2d 820 (1960), involved similar considerations to those in Baker. The petitioner was employed as a laborer by the railroad,......
  • Vanskike v. ACF Industries, Inc.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • November 9, 1981
    ...Hortman v. Henderson, 434 F.2d 77, 79 (7th Cir. 1970), or singles out the testimony of In Ward v. Atlantic Coast Line R.R., 362 U.S. 396, 80 S.Ct. 789, 4 L.Ed.2d 820 (1960) (per curiam), the Supreme Court reversed because the trial court's instruction on FELA employment had incorrectly limi......