Waste Management of Illinois, Inc. v. Illinois Pollution Control Bd.

Decision Date21 November 1991
Docket Number71003,Docket Nos. 71001
Parties, 165 Ill.Dec. 875 WASTE MANAGEMENT OF ILLINOIS, INC., Appellee, v. The ILLINOIS POLLUTION CONTROL BOARD et al., Appellants.
CourtIllinois Supreme Court

Larry M. Clark, Mundelein, for appellant Village of bensenville.

Neil F. Hartigan and Roland W. Burris, Attys. Gen., Springfield (Robert Ruiz and Rosalyn Kaplan, Sols. Gen., and Michelle D. Jordan, Matthew J. Dunn, Joseph J. Annunzio, William E. Seith and Kelly A. O'Connor, Asst. Attys. Gen., Chicago, of counsel), for appellant Ill. Pollution Control Bd.

Pedersen & Houpt, Chicago (Donald J. Moran and Marilee Roberg, of counsel), for appellee.

Justice CLARK delivered the opinion of the court:

On July 22, 1988, Waste Management of Illinois, Inc., submitted to the Village of Bensenville (Village) an application for local siting approval for a waste transfer station. The Village denied approval on February 2, 1989, on the grounds that Waste Management had not met its burden of proof under the "need" and "traffic" criteria of the local siting provisions of the Illinois Environmental Protection Act (Act) (Ill.Rev.Stat.1989, ch. 111 1/2, pars. 1039.2(a)(i), (a)(vi)).

On February 8, 1989, Waste Management brought an appeal before the Pollution Control Board (Board). Section 40.1(a) of the Act provides that an applicant may appeal the denial of an application of local site approval to the Board. (Ill.Rev. Stat.1989, ch. 111 1/2, par. 1040.1(a).) If the Board does not take "final action" on the appeal "within 120 days," the petitioner may deem the site location approved. (Ill.Rev.Stat.1989, ch. 111 1/2, par. 1040.1(a).) In an order dated July 13, 1989, the Board affirmed the Village's decision. The Board issued its opinion setting forth its findings on August 10, 1989. July 13, 1989, was the 120-day deadline for "final action" under section 40.1 of the Act (Ill.Rev.Stat.1989, ch. 111 1/2, par. 1040.1(a)).

On August 25, 1989, pursuant to section 101.246 of the Administrative Code (35 Ill.Adm.Code § 101.246 (1989)), Waste Management filed with the Board a motion for reconsideration, claiming, inter alia, that the Board had not taken "final action" (Ill.Rev.Stat.1989, ch.111 1/2, par. 1040.1(a)) within the statutory time period because the opinion was issued after the July 13, 1989, deadline. In an order dated September 13, 1989, the Board denied Waste Management's motion.

On September 20, 1989, Waste Management filed an appeal with the appellate court, again arguing that the Board had not taken "final action" within the statutory time period. The appellate court, with one justice dissenting, reversed the Board's decision. (201 Ill.App.3d 614, 146 Ill.Dec. 961, 558 N.E.2d 1295.) The appellate court held that the August 10, 1989, opinion constituted the final determination by the Board; therefore, Waste Management's application for site location of the waste transfer station must be deemed approved. (201 Ill.App.3d at 621, 146 Ill.Dec. 961, 558 N.E.2d 1295.) We granted the Board's petition for leave to appeal.

We begin by noting that this appeal involves the interpretation of a statutory provision, section 40.1 of the Act. When interpreting a disputed provision, this court must ascertain and give effect to the true intent and meaning of the legislature, considering first the statutory language. (In re Marriage of Logston (1984), 103 Ill.2d 266, 277, 82 Ill.Dec. 633, 469 N.E.2d 167.) Those terms which are unambiguous, when not specifically defined, must be given their plain and ordinary meaning. (See, e.g., People v. Moore (1978), 69 Ill.2d 520, 523, 14 Ill.Dec. 470, 372 N.E.2d 666.) Moreover, this court shall not insert words into legislative enactments when the statute otherwise presents a cogent and justifiable legislative scheme. (See Hagen v. City of Rock Island (1959), 18 Ill.2d 174, 179, 163 N.E.2d 495.) Mindful of this standard, we shall examine the provision.

Section 40.1 of the Act contains the procedure for appeal to the Board from denial of an application of local site approval. The section provides in part:

"If the county board or the governing body of the municipality * * * refuses to grant approval * * *, the applicant may, within 35 days, petition for a hearing before the Board to contest the decision of the county board or the governing body of the municipality. * * * In making its orders and determinations under this Section, the Board shall include in its consideration the written decision and reasons for the decision of the county board or the governing body of the municipality, the transcribed record of the hearing * * *, and the fundamental fairness of the procedures used by the county board of the municipality in reaching its decision. * * * If there is no final action by the Board within 120 days, petitioner may deem the site location approved; * * *." Ill.Rev.Stat.1989, ch. 111 1/2, par. 1040.1(a).

A plain reading of the disputed provision reveals that nowhere in the text does the word "opinion" appear. Reference is made to a "written decision" but it is to the written decision of the county board or the governing municipal body from which the petitioner is appealing that is meant. The appellate court concluded that a separate written opinion was required for "final action" based entirely on its conclusion that section 40.1 and section 33(a) of the Act, which provides, inter alia, that "[i]n all such matters the Board shall file and publish a written opinion stating the facts and reasons leading to its decision" (Ill.Rev.Stat.1989, ch. 111 1/2, par. 1033(a)), must be considered together. 201 Ill.App.3d at 619, 146 Ill.Dec. 961, 558 N.E.2d 1295.

In support of its conclusion, the appellate court cited generally Clean Air Coordinating Committee v. Environmental Protection Agency (1976), 42 Ill.App.3d 124, 127, 355 N.E.2d 573, and Waste Management of Illinois, Inc. v. Pollution Control Board (1988), 175 Ill.App.3d 1023, 1035, 125 ill.dec. 524, 530 N.E.2d 682. We do not believe these cases support the proposition for which the court cited them. In Clean Air, the statutory phrases the court "considered together" were two sentences occurring in the same paragraph of a single statutory provision. The merger the court below forced is between two requirements occurring in two entirely separate provisions, unlike the situation in Clean Air, and we do not believe the conclusion or analysis in Clean Air in any way support the proposition for which the majority below relies on it.

Likewise, we believe the court's reliance on Waste Management of Illinois, Inc. v. Pollution Control Board is misplaced. In Waste Management, the court reconciled two provisions appearing in separate sections of the Act, sections 39.2(g) and 40.1(a). Section 39.2(g) contains the siting procedures for a new regional pollution control facility and provides that the procedures contained therein "shall be the exclusive siting procedures," while section 40.1(a) indicates that the siting procedures shall be conducted pursuant to section 39 as well as those procedures employed by the county board or the governing body of the municipality. (Ill.Rev.Stat.1989, ch. 111 1/2, par. 1040.1(a).) The apparent conflict in the two provisions was resolved by reading the two provisions together so that the one provision was read to explain or define the other and thereby avoid any inconsistency.

The case before us presents no such inconsistency. One section, section 40.1, requires final action within 120 days. The other section, section 33(a), requires written findings. No conflict exists. As the dissent below aptly noted, "[n]othing ties the one provision to the other" outside of the majority's forced merger of the two provisions. (201 Ill.App.3d at 628, 146 Ill.Dec. 961, 558 N.E.2d 1295 (McNamara, J., dissenting).) In fact, section 33(a) is found under a separate title than that under which section 40.1 appears. Section 33(a) is found under title VIII, "Enforcement," while section 40.1 occurs under title X, "Permits." The requirement that the Board file and publish a written opinion "[i]n all such matters" refers to enforcement appeals. The instant matter involves an applicant's request to a municipality for local siting approval to construct and operate a solid waste transfer station.

The only reference to section 33(a) found in title X appears in section 40.1, which provides, inter alia, that "[a]t such hearing [the appeal before the Board] the rules prescribed in Sections 32 and 33(a) of this Act shall apply." (Ill.Rev.Stat.1989, ch. 111 1/2, par. 1040.1.) By its own terms, section 40.1 explicitly states that the rules in section 33(a) shall apply at the hearings, not to any action taken subsequent thereto.

In addition to referring to intrinsic evidence as an aid in interpreting a statute, it is appropriate to consider extrinsic evidence as well. Legislative debates on the disputed provision or amendments thereto frequently shed light on the provision, but the floor debates in this matter offer no additional insight into the phrase beyond that inferred from its plain and ordinary meaning. (See 83d Ill.Gen.Assem., House Proceedings, November 27, 1984, at 37-38, 42-43; 83d Ill.Gen.Assem., Senate Proceedings, May 23, 1984, at 175; 83d Ill.Gen.Assem., Senate Proceedings, May 9, 1984, at 171.) Reference to...

To continue reading

Request your trial
20 cases
  • Hernandez v. Lifeline Ambulance, LLC
    • United States
    • Illinois Supreme Court
    • June 18, 2020
    ...the statute otherwise presents a cogent and justifiable legislative scheme. Waste Management of Illinois, Inc. v. Illinois Pollution Control Board , 145 Ill. 2d 345, 348, 165 Ill.Dec. 875, 585 N.E.2d 606 (1991). Thus, where the legislature has not chosen to impose the condition or limitatio......
  • County of Du Page v. Illinois Labor rel.
    • United States
    • Illinois Supreme Court
    • December 18, 2008
    ... ... 121, 817 N.E.2d 479; Alternate Fuels, Inc. v. Director of the Illinois Environmental Protection ... , as we all know, during which time the employer has control of the employers [ sic ] and can interfere with the ... See Waste Management of Illinois, Inc. v. Illinois Pollution Control ... ...
  • People ex rel. Hansen v. Phelan, s. 1-92-2915
    • United States
    • United States Appellate Court of Illinois
    • March 16, 1993
    ...presents a cogent and justifiable legislative scheme." (Waste Management of Illinois, Inc. v. Illinois Pollution Control Board (1991), 145 Ill.2d 345, 348, 165 Ill.Dec. 875, 876, 585 N.E.2d 606, 607.) The language of the Ordinance, which delegates to the President the power to "direct and c......
  • Lake Envtl., Inc. v. Arnold
    • United States
    • Illinois Supreme Court
    • September 24, 2015
    ...words into its rules when the rule is otherwise “cogent and justifiable.” Waste Management of Illinois, Inc. v. Illinois Pollution Control Board, 145 Ill.2d 345, 348, 165 Ill.Dec. 875, 585 N.E.2d 606 (1991) ; see People v. Roberts, 214 Ill.2d 106, 116, 291 Ill.Dec. 674, 824 N.E.2d 250 (2005......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT