Weathered v. Garrett
Decision Date | 23 February 1891 |
Docket Number | 131 |
Citation | 140 Pa. 224,21 A. 319 |
Parties | C. B. WETHERED ET AL. v. W. E. GARRETT, JR., ET AL |
Court | Pennsylvania Supreme Court |
Argued February 4, 1891
APPEAL BY WYNN & HENWOOD FROM THE COURT OF COMMON PLEAS OF MONTGOMERY COUNTY.
No. 131 July Term 1890, Sup. Ct.; court below, No. 30 October Term 1889, C.P.
On June 24, 1889, Charles B. Wethered and Edmund C. Wethered, trading as Thomas W. Wethered's Sons, successors to Thomas W Wethered, brought scire facias sur mechanics' lien against William E. Garrett, Jr., owner or reputed owner, and Thomas Wynn and Alfred Henwood, trading as Wynn & Henwood contractors.
The lien in question was filed on April 22, 1889, for the sum of $1,221.73, against "All those four certain buildings known as the palm-house, two greenhouses, and pit, and lot or piece of ground and curtilage appurtenant thereto, being the ground covered by such buildings and so much other ground immediately adjacent thereto and belonging in like manner to the owner of said buildings and ground as may be necessary for the ordinary and useful purposes of said buildings situate in Lower Merion township, Montgomery county Pennsylvania, and being part of that larger tract or piece of ground described according to plan of Daniel Kinzie, surveyor, made first of December, 1885; [giving a description by metes and bounds] containing forty-four acres, sixty-four perches."
The bill of particulars appended to the lien showed the claim to be for the furnishing of various boilers, pipes, pipe fittings, and castings, etc., between October 1 and November 13, 1888.
Judgment was entered against William E. Garrett, Jr., owner, for want of an affidavit of defence. Wynn & Henwood, contractors, filed an affidavit of defence and obtained a rule to strike off the lien. After argument, the court discharged the rule except as to certain items for freight, railroad fare, etc., which were ordered to be stricken out without prejudice to the remainder of the lien, and amended the judgment against the owner, upon a rule to open the same, by excluding therefrom the amounts of the same items. [*] The defendants Wynn & Henwood then filed the following pleas: "Nil debet; nunquam indebitatus; that the plaintiffs are not, nor are any of them, citizens of Pennsylvania; that the materials charged for in the lien were not furnished on the credit of the buildings or any of them; that the buildings are not sufficiently described in the lien filed."
At the trial on March 17, 1890, the following facts were shown:
In the year 1888, William E. Garrett, Jr., gave out contracts for the erection of a group of conservatories upon the tract of land described in the lien, then owned by him. The plans prepared by his architect provided for the erection of a building divided by a partition into two greenhouses, and for another structure called the palm-house, upon a separate foundation and with a separate roof, but joined to the greenhouses and having communicating doors by which to pass from one to the other. The plans provided also for a system of heating apparatus, by which all the greenhouses could be heated from a common source, but so arranged that either of them could be heated separately. The heat was to be supplied from a "pit" or boiler room, adjoining one of the greenhouses, and placed in the cellar of a building occupied as a dwelling by the gardener. There was some difference in the opinions of the witnesses, given upon the trial, as to whether these various structures ought to be regarded as together constituting one building, or whether one or more of them should be regarded as separate buildings, distinct from the others. The architect who prepared the plans testified that, speaking as an architect he would call them one house, but that for purposes of horticulture they were separate buildings. Witnesses for the plaintiffs testified that the buildings as they were erected could readily be identified by the description given in the mechanics' lien.
The contract for putting in the heating apparatus was given to Wynn & Henwood, who ordered from the plaintiff firm, in New York, the supplies required for that purpose. They were shipped by the plaintiffs in September, 1888, except certain valves, etc., for controlling the heat in the pipes leading from the greenhouses into the palm-house, which were furnished about November 5, 1888. While the work was in progress, a set of ventilating apparatus was directed to be put in also. This was ordered from the plaintiffs by Wynn & Henwood, some time after placing the order for the heating apparatus. The ventilating apparatus was furnished and put in early in 1889. The various articles furnished by the plaintiffs were furnished expressly for the conservatory buildings in course of erection for Garrett.
After the completion of their contract with Garrett, the firm of Wynn & Henwood became insolvent and made an assignment for the benefit of creditors.
At the close of the testimony, the court, WEAND, J., charged the jury in part as follows:
It is also said that they were not furnished in time; that is, within six months of filing the lien. . . . .
No inference, of course, should be drawn against the defendants, on the other hand, simply because they are insolvent or have made an assignment. Neither of these facts has anything to do with this case.
The defendants have asked me to charge you on several points of law:
1. Plaintiffs, not being citizens of Pennsylvania, are not entitled to the benefit and cannot take advantage of our mechanics' lien laws, and the verdict must be for the defendants.
Answer: This is refused. This is not the law.
2. There can be no lien filed for the articles charged for in this case, and the verdict should be for the defendants.
Answer: This is refused.
3. If the jury believe that the only work with which the defendants, Wynn & Henwood, were concerned, was the heating of the building, then the verdict should be for the defendants.
Answer: This is refused.
6. If the jury believe that the structure against which the lien is filed constitutes but a single whole and complete building, then the verdict should be for the defendants.
Answer: This is refused.
7. If the jury believe that the articles charged for were furnished not under a single contract for the entire lot of articles charged for, then the verdict should be for the defendants.
Answer: This is refused.
The jury returned a verdict for the plaintiffs for $1,294.66. A rule for a new trial having been discharged and judgment entered, defendants Wynn & Henwood took this appeal, assigning for error:
1-4. The parts of the charge embraced in [] to
5-7. The refusal of defendant's points. to
10, 11. The refusal of defendant's points.
Judgment affirmed.
Mr. Webster A. Melcher (with him Mr. Alexander Simpson, Jr.), for the appellants:
1. There is a legal standard for the identification required in the description which a mechanics' lien must set forth and the description in the present case was insufficient: Wray v. Haines, 4 W.N. 358; Barclay's App., 13 Pa. 495; ...
To continue reading
Request your trial- In re Estate of Jacobs
-
Young v. Porter-Leach Hardware Co., Inc.
...in no position to complain of the judgment wherein the Company was adjudged a lien on Wallace's home, 40 C.J. 395, § 541; Wethered v. Garrett, 140 Pa. 224, 21 A. 319; Clark v. Brown, 22 Mo. The judgment is affirmed. ...
-
Young v. Porter-Leach Hardware Co., Inc.
...position to complain of the judgment wherein the Company was adjudged a lien on Wallace's home, 40 C.J. 395, Section 541; Wethered v. Garrett, 140 Pa. 224, 21 A. 319; Clark v. Brown, 22 Mo. The judgment is affirmed. ...