Weitzul Const., Inc. v. Outdoor Environs

CourtTexas Court of Appeals
Writing for the CourtBAKER
CitationWeitzul Const., Inc. v. Outdoor Environs, 849 S.W.2d 359 (Tex. App. 1993)
Decision Date26 January 1993
Docket NumberNo. 05-91-01590-CV,05-91-01590-CV
Petition Historywrit denied
PartiesWEITZUL CONSTRUCTION, INC., Appellant, v. OUTDOOR ENVIRONS, Appellee.

Jeffrey L. Clark, Kelsoe, Anderson & Khourty, P.C., Dallas, for appellant.

Martin D. Steele, Grand Prairie, Michael R. Roach, Lewisville, for appellee.

Before BAKER, BARBER, 1 and MORRIS, 2 JJ.

OPINION

BAKER, Justice.

Based on the jury's verdict, the trial court entered a judgment for Outdoor Environs. In five points of error, Weitzul contends the trial court erred in entering judgment because Outdoor did not produce any evidence of the cost of remedying defects. Weitzul also claims the trial court erred by not submitting Weitzul's requested affirmative defense issue and by awarding Outdoor its attorney's fees. We affirm the trial court's judgment.

THE SPRINKLER SYSTEM AND LANDSCAPE CONTRACTS

Weitzul Construction was the general contractor for the City of Farmers Branch on a pump station project. Weitzul hired Outdoor as a subcontractor to install the sprinkler system and do the landscape work for the project. The sprinkler contract was for $11,000, and the landscape contract was for $22,000. Outdoor went onto the site to do the work. Outdoor claimed it fully performed both the sprinkler and landscape contracts. Outdoor claimed it should receive full payment on both contracts. Weitzul contended that Outdoor did not fully perform either agreement. Weitzul claimed it took over both contracts as provided in the agreements and spent money to complete and remedy Outdoor's defective work. Weitzul claimed the right to backcharge Outdoor for its completion expenses.

PROCEDURAL HISTORY

Outdoor sued Weitzul for the balances due on the sprinkler and landscape agreements. Outdoor claimed it was due $1072.50 on the sprinkler contract and $11,258.83 on the landscape contract. Outdoor also alleged it was due an additional amount of $7400 for extra work not included in the contracts.

Weitzul answered and alleged that Outdoor materially breached the agreements. Weitzul alleged that it had paid all that was due. Weitzul further alleged that Outdoor had not allowed all lawful credits and offsets.

The parties tried the case to a jury. The trial court submitted the case to the jury on a substantial performance theory. The jury found Outdoor substantially performed both the sprinkler and landscape contracts. The jury found Outdoor should recover $1072.50 on the sprinkler contract and $8063.66 on the landscape contract. In the damage issue, the court instructed the jury that a contractor who has substantially performed his contract may recover the contract price less the reasonable cost of completion and remedying any defects.

The jury did not find that Outdoor performed other compensable work for Weitzul. The jury found Outdoor entitled to attorneys' fees for the trial and possible appeal of the case. The trial court entered judgment on the verdict for Outdoor.

THE PARTIES' CONTENTIONS
A. Weitzel's Contentions
1. The Sprinkler Contract

Weitzul contends Outdoor produced no evidence of the cost to remedy Outdoor's incomplete and defective performance of the sprinkler contract. Weitzul asserts Outdoor did not secure a jury finding of the cost to remedy defects under this agreement. Weitzul contends that without such a finding, Outdoor cannot recover under a substantial performance theory. Specifically, Weitzul argues Outdoor sought recovery of $1072.50 representing the unpaid balance of the full contract amount. The jury awarded Outdoor $1072.50. Weitzul concludes the jury made no finding of any cost to remedy defects. Weitzul argues Outdoor cannot prevail because the jury's answer to the question is an answer of "none" to the cost of remedying defects.

2. The Landscape Contract

Weitzul contends Outdoor produced no evidence of the cost to remedy Outdoor's incomplete and defective performance under the landscape contract. Weitzul introduced evidence to support its claims against Outdoor for incomplete and defective performance. This evidence included Weitzul's cost to remedy the defects. Weitzul argues that this evidence did not show the cost to remedy defects or the cost of completion because its evidence was not expert testimony or probative of that issue.

In summary, Weitzul argues that because no expert testified about the cost of remedying defects and Outdoor offered no evidence about reasonable amounts in Dallas County, Texas, to remedy any defects, Outdoor did not prove its substantial performance action. Weitzul contends Outdoor should recover nothing.

B. Outdoor's Contentions
1. The Sprinkler Contract

Outdoor argues the jury heard evidence from both sides about the sprinkler contract. Outdoor contends there was a dispute on the backcharges Weitzul claimed it could take. Outdoor argues the jury found the cost of remedying defects on the sprinkler contract was "none" by answering the damage question $1072.50. Outdoor contends the jury's answer was proper under the evidence.

2. The Landscape Contract

Outdoor contends the parties tried the entire case on the evidence and the documents on Weitzul's backcharges to the contract. Outdoor points out Weitzul's president testified about the backcharges and costs Weitzul incurred to remedy defects Weitzul alleged resulted because of Outdoor's deficient performance. Outdoor disputed all of the backcharges claimed by Weitzul and introduced evidence that showed certain items were minor maintenance, repair, or warranty items.

STANDARD OF REVIEW

Weitzul's first three points of error are no evidence points. In deciding a no evidence question, we consider only that evidence and reasonable inferences therefrom that tend to support the jury findings. We disregard all contrary evidence and inferences. Best v. Ryan Auto Group, Inc., 786 S.W.2d 670, 671 (Tex.1990); Kartalis v. Lakeland Plaza Joint Venture, 784 S.W.2d 64, 67 (Tex.App.--Dallas 1989, writ denied). We uphold the jury's findings if there is more than a scintilla of evidence to support them. Stedman v. Georgetown Sav. & Loan Ass'n, 595 S.W.2d 486, 488 (Tex.1979). The reviewing court is not a fact finder. We may not substitute our judgment for that of the jury, even if a different answer could be reached on the evidence. Clancy v. Zale Corp., 705 S.W.2d 820, 826 (Tex.App.--Dallas 1986, writ ref'd n.r.e.).

The jury is the exclusive judge of the controverted fact issues raised by the evidence, the weight given to the evidence, and the inferences drawn therefrom. The jury is the exclusive judge of the witnesses' credibility. Beck v. Lawler, 422 S.W.2d 816, 819 (Tex.Civ.App.--Fort Worth 1967, writ ref'd n.r.e.).

THE APPLICABLE LAW

Outdoor pleaded it should recover on the contract. Weitzul claimed Outdoor's performance was incomplete and defective. Weitzul claimed offsets for its costs to remedy Outdoor's defective performance. Outdoor disputed Weitzul's claims for backcharges. A pleading of full performance will support the submission of a substantial performance issue. See Del Monte Corp. v. Martin, 574 S.W.2d 597, 599 (Tex.Civ.App.--San Antonio 1978, no writ).

A contractor that substantially performs a building contract may recover the full contract price less the cost of remedying those defects that are remediable. Vance v. My Apartment Steak House, 677 S.W.2d 480, 481 (Tex.1984). When a contractor brings suit to recover for substantial performance and the owner alleges remediable defects in the construction, the contractor must prove he did substantially perform. The contractor must also prove the consideration owed him under the contract and the cost of remedying the defects due to his errors or omissions. Vance, 677 S.W.2d at 483.

If the owner sues or counterclaims alleging the contractor is in breach of the construction contract, the owner's measure of damage is the cost of completing the job or of remedying those defects that are remediable. If the owner has paid only part of the contract price to the contractor, then the amount of the owner's damages is credited against the balance of his payments owed on the contract. See Turner, Collie & Braden, Inc. v. Brookhollow, Inc., 642 S.W.2d 160, 164 (Tex.1982). The facts of the case determine the proper measure of damages as well as any allowance offsets. Vance, 677 S.W.2d at 481 n. 1.

APPLICATION OF THE LAW TO THE FACTS
A. The Sprinkler Contract

The price for installing the sprinkler system was $11,000. Outdoor acknowledged payments from Weitzul totaling $9927.50. Outdoor sued for an unpaid balance of $1072.50. Outdoor's partners and employees testified Outdoor completed the sprinkler system contract. Outdoor's witnesses testified any work done on the sprinkler system was merely maintenance or warranty work.

Tom Weitzul, Weitzul's president, testified he had been in the construction business for eighteen to nineteen years. His company maintained offices in Dallas, Hawaii, and Guam. His company has done a number of municipal projects in Texas, California, Hawaii, and Guam. Weitzul testified the contracts with Outdoor permitted Weitzul to take over the contracts if Outdoor did not properly perform. He also testified the contracts permitted Weitzul to repair or remedy any defects and backcharge Outdoor for these costs. Weitzul introduced evidence showing a $595 backcharge on the sprinkler contract. Weitzul contended Outdoor was due only $477.50.

Weitzul contends that the jury's award of the remaining full contract balance of $1072.50 amounts to a finding of "none" to the cost to remedy defects. Weitzul argues that absent a jury finding of costs to remedy defects, Outdoor cannot prevail on a substantial performance theory on the sprinkler system. We disagree.

The jury's effective answer of "none" to the cost of remedying defects does not mean Outdoor did not meet its burden of proof on its substantial performance claim. See Ambassador Dev. Corp. v. Valdez, 791 S.W.2d 612, 616 (Tex.App.--Fort Worth 1...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
29 cases
  • ABRAXAS PETROLEUM v. HORNBURG
    • United States
    • Texas Court of Appeals
    • 16 Marzo 2000
    ...any allowance offsets. Vance v. My Apartment Steak House, 677 S.W.2d 480, 481 n.1 (Tex. 1984); Weitzul Const., Inc. v. Outdoor Environs, 849 S.W.2d 359, 363 (Tex.App.--Dallas 1993, writ denied). The universal rule for measuring damages for the breach of a contract is just compensation for t......
  • Balfour Beatty Rail, Inc. v. Kan. City S. Ry. Co.
    • United States
    • U.S. District Court — Northern District of Texas
    • 25 Marzo 2016
    ...is generally the cost of completing the job or remedying the defects that are remediable. Weitzul Constr., Inc. v. Outdoor Environs , 849 S.W.2d 359, 363 (Tex.App.–Dallas 1993, writ denied). If the owner has paid only part of the contract price to the contractor, the owner's damages are cre......
  • Tribble & Stephens Co. v. Rgm Constructors
    • United States
    • Texas Court of Appeals
    • 28 Octubre 2004
    ...him under the contract, and the cost of remedying the defects due to his errors or omissions. Weitzul Constr., Inc. v. Outdoor Environs, 849 S.W.2d 359, 363 (Tex.App.-Dallas 1993, writ denied). RGM argued in its summary judgment motion that there was a fact issue as to the appropriate cost ......
  • Sharifi v. Steen Auto., LLC
    • United States
    • Texas Court of Appeals
    • 14 Junio 2012
    ...Vance v. My Apartment Steak House of San Antonio, Inc., 677 S.W.2d 480, 481 n. 1 (Tex.1984); Weitzul Constr., Inc. v. Outdoor Environs, 849 S.W.2d 359, 363 (Tex.App.-Dallas 1993, writ denied); Abraxas Petroleum Corp., 20 S.W.3d at 760. Damages must be measured by a legal standard, and that ......
  • Get Started for Free