Wells Benz, Inc. v. United States

Decision Date02 June 1964
Docket NumberNo. 18435,18436.,18435
Citation333 F.2d 89
PartiesWELLS BENZ, INC., a corporation, Dale Benz, Inc., a corporation, and The Fidelity and Casualty Company of New York, a corporation, Appellants, v. UNITED STATES of America for the Use of MERCURY ELECTRIC COMPANY, a corporation, and Founders Insurance Company, a corporation, Appellees.
CourtU.S. Court of Appeals — Ninth Circuit

Betts & Loomis, Albert H. Ebright, James A. Williams, Los Angeles, Cal., for appellants.

Wiseman & Elmore, Aaron Elmore, Beverly Hills, Cal., Anderson, McPharlin & Conners, Kenneth E. Lewis, Los Angeles, Cal., for appellees.

Before POPE, KOELSCH and BROWNING, Circuit Judges.

KOELSCH, Circuit Judge.

These are two separate suits which were heard together, both here and in the district court. They involve four Miller Act Claims 40 U.S.C. § 270a and § 270b, prosecuted by Mercury Electric Company (Mercury), a subcontractor, against Wells Benz, Inc. and Dale Benz, Inc. (Wells and Benz), the prime contractors, together with their surety, the Fidelity and Casualty Company of New York. They also include counter-claims asserted by Wells and Benz.1 The district court rendered judgment for Mercury on three of its claims and against Wells and Benz on all the counter-claims. Only Wells and Benz have appealed.

In December, 1958, Wells and Benz, as prime contractors, awarded Mercury, the subcontractor, contracts for the electrical work and equipment on several construction projects of the Federal Government at Point Arguello and Point Mugu, California. There were four jobs, each of which was the subject of a separate contract. They were known as the "Instrumentation Job," the "Photo Tracking Job," the "Range Job" and the "Supply Department Job." Mercury fully performed the contract for the Range Job, but before the others were completed Wells and Benz ordered it to leave the materials and get off the jobs. Wells and Benz then engaged Dimac Electric Company, who finished the jobs on a cost-plus basis.2

These suits followed. Charging that Wells and Benz had wrongfully prevented performance of the contracts, Mercury sought damages on the theory of rescission. Wells and Benz admitted they had terminated Mercury's work, but alleged that Mercury had failed to "live up to the terms and conditions of the subcontract(s); they filed counter-claims against Mercury for breach of contract.

The case was heard without a jury. At the close of the evidence, the court announced generally that Mercury was entitled to judgment on all its claims except the one relating to the Photo Tracking Job; that Wells and Benz had overpaid Mercury for work on that job and should recover the overpayment; the court further stated that Wells and Benz should take nothing by their counterclaims and directed counsel for Mercury to prepare and submit findings of fact and conclusions of law consistent with its views. At the settlement hearing, however, there was considerable discussion and controversy concerning the basis for the court's decision and the findings that the judge entered were much briefer and somewhat different than the ones proposed by Mercury. On appeal, Wells and Benz vigorously attack these findings on the grounds that they are insufficient to support the judgments, analytically incorrect and clearly erroneous, and above all, "contrary to the real findings * * * and impressions of the trial court * * *."

A comparison discloses that, aside from dates, job references and monetary amounts, the findings in each suit are substantially the same. Thus, so far as pertinent, those in the Instrumentation Job suit read:

"8. On (here appears the date) the Contractor (i. e., Wells and Benz) gave notice * * * to the plaintiff * * * cancelling said subcontract and ordering plaintiff to remove all its personnel from the job and cease further work thereon, but to leave its equipment and materials, and pursuant only to such order, plaintiff complied therewith and ceased further work thereon. Prior to said cessation, plaintiff substantially performed and complied with each and all of the terms, conditions and obligations of said subcontract on its part to be performed and at the time of said notice stood ready, able and willing to complete the performance of the balance of its work under said subcontract.
"9. On (here appears the date) plaintiff gave a notice in writing to contractor declaring a rescission of said subcontract, on the grounds among others as follows:
"(a) Prevention of performance on the part of the contractor in peremptorily ordering plaintiff off the job;
"(b) * * *
"10. At the time of the termination by contractor of said subcontract, there was and is due, owing and unpaid to plaintiff, after allowing full credits to the defendants for payments made by them, or either of them, thereafter to material suppliers and after allowing for and deducting any and all other credits and offsets to which they, or either of them, were, or might be, entitled, a balance of ( ) Dollars for the work and materials delivered by plaintiff on the basis of the contract price * * *. The following Conclusions of Law, insofar as they may be considered Findings of Fact, are so found by this court to be true in all respects * * *
* * * * * *
"Conclusions of Law:
* * * * * *
"4. The third party plaintiffs and counter-claimants are not entitled to any judgment whatsoever on the third party claim or cross-claim against third party defendants * * *."

We agree with Wells and Benz that the judgments cannot be sustained unless these findings clearly reflect that Wells and Benz were not justified in preventing Mercury from performing the contracts. That is the gist of Mercury's claims and the rule is well settled that a claim "* * * may not be upheld as to any item that is not supported by definite findings of fact extending to all essential issues * * *." United States v. Seminole Nation, 299 U.S. 417, 422, 57 S.Ct. 283, 287, 81 L.Ed. 316 (1937). But we reject Wells and Benz' thesis that these findings are fatally deficient. We refer especially to Finding No. 8. As already noted, the court therein stated (a) that Wells and Benz stopped Mercury's work; (b) that up to that time Mercury had substantially performed and complied with its contract, and (c) that Mercury stood ready, able and willing to complete the performance of the balance of its work under said contract. These three findings are tantamount to and require the conclusions that Wells and Benz' act was not warranted and afforded Mercury just cause to treat the contracts at an end.

True, they do not state that any party had breached the contracts, and that issue was basic, both to Mercury claims and Wells and Benz' counterclaims; but the lack of an express statement does not necessarily constitute a vital omission, for the rule in this court, as well as in other jurisdictions, has long been that "* * * whenever, from facts found, other facts may be inferred which will support the judgment, such inferences will be deemed to have been drawn. The findings of fact by a trial court must receive such a construction as will uphold, rather than defeat, its judgment." Clyde Equipment Co. v. Fiorito, 16 F.2d 106, 107 (9th Cir.1926); Carr v. Yokohama Specie Bank, Inc., 200 F.2d 251, 255 (9th Cir. 1952; 5 Am.Jur.2d, Appeal and Error, § 844 at p. 288 (1962). And in the cases at bar, the answer to the question who was at fault can fairly be determined from the facts the court did declare.

Substantial performance is performance. Musto Sons-Keenan Co. v. Pacific States Corp., 48 Cal.App. 452, 458, 192 P. 138 (1920). With reference to a building contract, it does imply something less than a strict and literal compliance with the contract provisions but fundamentally it means that the deviation is unintentional and so minor or trivial as not "substantially to defeat the object which the parties intend to accomplish." Connell v. Higgins, 170 Cal. 541, 556, 150 P. 769, 775 (1915).3 Similarly and consistent with the rule governing contracts generally, a building contract may not be repudiated or unilaterally terminated by one party simply because the other is in default; rather, the party may treat his own obligation at an end only if the other's breach is so gross that the very object of the contract is defeated, United States v. Southern Construction Co., 293 F.2d 493, 498 (6th Cir. 1961); Murphy v. Sheftel, 121 Cal.App. 533, 9 P.2d 568, 571 (1932); United States Plywood Corp. v. Hudson Lumber Co., 113 F.Supp. 529, 534 (D.C.S.D.N.Y. 1953); Restatement, Contracts, § 274 (1932); 12 Am.Jur. Contracts, § 440, p. 1020 (1938); 13 Am.Jur.(2d) Building etc. Contracts, § 101 at p. 97 (1964) and the type of variation which is contemplated by a finding of substantial performance is not of the latter character.4

Although the doctrine of substantial performance is customarily applied to a completed contract,5 it does not follow the district court's conclusion must be overturned on that account. We are persuaded the district court applied the term by analogy and, as we have before noted, we are able to supply the inference that the contract was wrongfully terminated from the finding of substantial performance.

Finding "8" likewise constituted a sufficient determination of all issues tendered by the counter-claims for the validity of those claims, and the incidental matter of damages depended upon Mercury's failure to substantially perform the contracts. Manifestly, the implied finding that Wells and Benz had wrongfully terminated Mercury's performance — the issue central to Mercury's cases — necessarily extended to Wells and Benz' counter-claims and was also dispositive of them. Wells and Benz' expenditures in completing the jobs after they had terminated the contract with no finding justifying termination when Mercury had (as the court found) substantially performed and was ready,...

To continue reading

Request your trial
38 cases
  • Abramson v. Board of Regents, University of Hawaii
    • United States
    • Hawaii Supreme Court
    • April 2, 1976
    ...369 U.S. 828, 82 S.Ct. 845, 7 L.Ed.2d 793 (1962); Blumenthal v. United States, 306 F.2d 16 (3d Cir. 1962); Wells-Benz, Inc. v. United States, 333 F.2d 89 (9th Cir. 1964); Manning v. Jones, 349 F.2d 992, 996 (8th Cir. 1965). See also Elam v. United States, 250 F.2d 582 (6th Cir. 1958). This ......
  • Flores v. Sessions
    • United States
    • U.S. District Court — Central District of California
    • June 27, 2017
    ...as not substantially to defeat the object which the parties intend to accomplish.’ " Id. (quoting Wells Benz, Inc. v. U.S. for Use of Mercury Elec. Co. , 333 F.2d 89, 92 (9th Cir. 1964) (citation and some quotation marks omitted)). "This standard doesn't require perfection.... Deviations ar......
  • Flores v. Barr
    • United States
    • U.S. District Court — Central District of California
    • September 27, 2019
    ...and so minor or trivial as not ‘substantially to defeat the object which the parties intend to accomplish.’ " Wells Benz, Inc. v. United States , 333 F.2d 89, 92 (9th Cir. 1964) (citation omitted). The Court will therefore apply the preponderance of the evidence standard to the issue of whe......
  • JJ Henry Co. v. United States
    • United States
    • U.S. Claims Court
    • June 20, 1969
    ...Co., 37 Cal.2d 739, 235 P.2d 1 (1951). 7 In Miller Act cases, reference is often made to state law. In Wells Benz, Inc. v. United States, 333 F.2d 89 (9th Cir. 1964), a subcontractor had recovered his Miller Act claim against Wells & Benz, the prime contractor, on the basis of an alleged br......
  • Request a trial to view additional results
3 books & journal articles
  • Management of Contract Terminations from Multiple Perspectives
    • United States
    • ABA General Library The Construction Lawyer No. 42-1, January 2022
    • January 1, 2022
    ...Homes, LLC v. Choate , 2011 Ark. App. 260, 10, 383 S.W.3d 418, 425 (2011). 5 Wells Benz, Inc. v. U.S. for Use of Mercury Elec. Co ., 333 F.2d 89, 93 (9th Cir. 1964). 6 “Termination for cause is recognized as a ‘species of forfeiture’ and ‘drastic adjustment of the contracting relationship’ ......
  • A 'binary choice' for families in ice detention: examining the legitimation costs of litigating the flores settlement agreement
    • United States
    • Georgetown Immigration Law Journal No. 36-1, July 2021
    • July 1, 2021
    ...Robert J. Kelleher, died. 32. Flores v. Barr, 407 F. Supp. 3d 909, 915–16 (C.D. Cal. 2019) (quoting Wells Benz, Inc. v. United States, 333 F.2d 89, 92 (9th Cir. 1964) (describing that substantial compliance “does imply something less than a strict and literal compliance with the contract pr......
  • Transactional Lessons from the Bankruptcy Battle Over Silver Linings Playbook
    • United States
    • California Lawyers Association Business Law News (CLA) No. 2022-3, 2022
    • Invalid date
    ...Cal. App. 3d 239 (1979)).30. Id. (citing Rouser v. White, 825 F.3d 1076, 1082 (9th Cir. 2016) (quoting Wells Benz, Inc. v. United States, 333 F.2d 89, 92 (9th Cir. 1964)).31. 23 Williston on Contracts § 63:3 (4th ed.).32. Ex. "Termination Clause. Any breach of this agreement by [Party A] wo......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT