Wells Bros Co of New York v. United States, 75

Decision Date08 November 1920
Docket NumberNo. 75,75
Citation254 U.S. 83,65 L.Ed. 148,41 S.Ct. 34
PartiesWELLS BROS. CO. OF NEW YORK v. UNITED STATES
CourtU.S. Supreme Court

Messrs. A. R. Serven and Burt E. Barlow, both of Washington, D. C., for appellant.

Mr. Assistant Attorney General Davis, for the United States.

Mr. Justice CLARKE delivered the opinion of the Court.

This is an appeal from a judgment of the Court of Claims, sustaining a general demurrer to and dismissing the amended petition.

The allegations of this amended petition, admitted by the demurrer and essential to be considered, are:

The appellant, a corporation organized under the laws of New York, and engaged in the general building and construction business, entered into a written contract with the United States for the construction of a post office and courthouse building in New Orleans, dated September 30, 1909, for which it was to be paid $817,000, but its bond for performance was not approved until 9 days later, on October 9; on the day after the contract was signed the United States 'ordered and directed' appellant to delay ordering limestone (as specified in the contract) for the exterior of the street fronts of the building 'for the reason, as stated, that a change was contemplated in said exterior face stonework, which would require an additional appropriation by Congress'; the appellant assented to a delay of two weeks only, but, although protesting that further delay would result in its damage, it refrained from purchasing limestone until August 19, 1910, when, the required appropriation by Congress having been obtained, a supplemental agreement was entered into by the parties to the contract, by which marble was substituted for limestone for the street fronts of the building, the compensation of the appellant was increased $210,500, and the time for completion of the building was extended from April 1, 1911, to February 5, 1912; during this delay the contractor proceeded with other work under the contract, and prior to August 19, 1910, it had completed all the required excavation, foundation, and structural steel work; after the 'modification and addition of August 19, 1910, to the contract work' the appellant so proceeded with the performance of the contract that by February 1, 1912, the building was substantially completed except the interior partitions, and thereupon the United States, again over the protest of appellant, 'ordered and directed' a delay, which continued to August 24, 1912, until congressional legislation was obtained authorizing the parcel post, whereupon the plans for the interior arrangements of the building were adapted to that service and the building was completed.

The claim is wholly for damages occasioned by the two delays thus described, and the question for decision is whether the terms of the contract authorized the government to require such delays without becoming liable to the contractor for damages which may have been caused to it thereby.

The contract involved contains this provision:

'It is further covenanted and agreed that the United States shall have the right of suspending the whole or any part of the work herein contracted to be done, whenever in the opinion of the architects of the building, or of the supervising architect, it may be necessary for the purpose or advantage of the work, and upon such occasion or...

To continue reading

Request your trial
47 cases
  • Buckley & Co., Inc. v. State
    • United States
    • New Jersey Superior Court
    • 30 Julio 1975
    ...entitled to recover for the resultant delays. Cf. Gherardi v. Trenton Bd. of Educa., supra; Wells Bros. Co. v. United States, 254 U.S. 83, 41 S.Ct. 34, 65 L.Ed. 148 (1920); Peter Kiewit Sons' Co. v. Iowa Southern Utilities[356 A.2d 67] Co., supra; Remo Engineering Corp. v. New York, 11 N.Y.......
  • State Hwy. Comm'n v. Green-Boots Const. Co.
    • United States
    • Oklahoma Supreme Court
    • 8 Julio 1947
    ...work unless it has been ordered in a particular manner.' 19 R.C.L. 1077, sec. 362. Mr. Justice Clarke, in the Wells Brothers Case, 254 U.S. 83, 41 S.Ct. 34, 35, 65 L.Ed. 148, said: 'Men who take $1,000,000 contracts for government buildings are neither unsophisticated nor careless.' We thin......
  • Port of Hous. Auth. of Harris Cnty. v. Zachry Constr. Corp.
    • United States
    • Texas Court of Appeals
    • 9 Agosto 2012
    ...against such delays as are complained of by the higher price exacted for the work.”Id. (quoting Wells Bros. Co. v. United States, 254 U.S. 83, 87, 41 S.Ct. 34, 65 L.Ed. 148 (1920)). Thus, in R.F. Ball, we noted that the common-law exceptions to no-damages-for-delay provisions are “generally......
  • State Highway Com'n v. Green-Boots Const. Co.
    • United States
    • Oklahoma Supreme Court
    • 8 Julio 1947
    ... ... Mr. Justice Clarke, in the Wells Brothers Case, 254 U.S. 83, ... 41 S.Ct. 34, 35, ... from the case of Plumley v. United States, 226 U.S ... 545, 33 S.Ct. 139, 140, 57 ... ...
  • Request a trial to view additional results
1 books & journal articles
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • 1 Abril 2021
    ...United States v. Rice, 317 U.S. 61 (1942); H.E. Crook Co. v. United States, 270 U.S. 4 (1926); Wells Bros. Co. of N.Y. v. United States, 254 U.S. 83 (1920). 83. Wells Bros. Co. , 254 U.S. at 87 (1920). 84. Id. 85. See, e.g. , United States v. Cook, 257 U.S. 523 (1922) (rejecting an architec......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT