Westburne Supply, Inc. v. Diversified Design and Const., Inc.

Decision Date13 February 1992
Docket NumberCA-CV,No. 1,1
Citation170 Ariz. 598,826 P.2d 1224
PartiesWESTBURNE SUPPLY, INC., a Delaware corporation, Plaintiff-Appellant, v. DIVERSIFIED DESIGN AND CONSTRUCTION, INC., an Arizona corporation, Defendant-Appellee. 90-326.
CourtArizona Court of Appeals
OPINION

GERBER, Judge.

This appeal by the plaintiff Westburne Supply, Inc. (Westburne) from summary judgment granted in favor of the defendants Diversified Design and Construction, Inc. (Diversified) and its surety, Safeco Insurance Company of America (Safeco) involves an interpretation of Arizona's "Little Miller Act," Ariz.Rev.Stat.Ann. ("A.R.S.") § 34-221--s 34-226. The act, as amended in 1984, requires a subcontractor to provide an initial estimate of costs within twenty days of commencing to supply labor and materials along with a notice of any remaining unpaid balance within ninety days of completion.

The sole issues raised on appeal are (1) whether a claimant is required to file an additional notice if the amount of labor or materials furnished exceeds by twenty per cent or more the amount estimated in the initial preliminary twenty day notice, and (2) whether, in the absence of such notice, recovery on the bond claim is limited to the amount initially estimated plus twenty per cent.

FACTS AND PROCEDURAL HISTORY

The material facts are undisputed. Diversified was the general contractor on a construction project for the University of Arizona. Because this was a public construction project, Diversified had to provide a payment bond for the protection of claimants supplying labor or materials pursuant to A.R.S. § 34-222(A)(2). Safeco issued the required bond in the sum of $1,621,600.00.

Diversified subcontracted with Strong Mechanical Group, Inc. (Strong) for a portion of the materials and services. Strong contracted with Westburne to supply some of the construction materials.

Westburne properly served a preliminary twenty day notice to Diversified as required by A.R.S. § 34-223(A). The notice estimated that the cost of the materials supplied would be $1,500.

Notwithstanding this estimate, Westburne actually supplied materials to the project valued at $28,998.82. Strong made no payments to Westburne and did not complete its subcontract work. It was subsequently terminated from the project.

Pursuant to the notice requirements of A.R.S. § 34-223(A), Westburne sent Diversified a final written notice within ninety days from the last date it furnished supplies, claiming their value at $28,998.82. Beyond this notice and its initial notice with the $1,500 estimate, Westburne did not provide any other estimate of the cost of the additional materials it supplied.

Westburne filed suit to recover the full amount of its claim against the bond. Diversified took the position that Westburne could recover no more than $1,800, the amount twenty per cent more than the amount Westburne estimated in the preliminary $1,500 notice. The parties filed cross motions for summary judgment. The motions in effect asked whether, under the provisions of A.R.S. § 34-223(A), a supplier was required to file an additional supplemental notice in order to recover more than twenty per cent beyond the amount estimated in the original notice. The parties stipulated that the total amount Westburne would be entitled to receive if the court found in its favor was $21,000; they also stipulated, conversely, that if the court found against Westburne, its recovery would be limited to $1,800.

The trial court found that, under the statute, once the amount claimed exceeded by twenty per cent or more the amount estimated in the original notice, filing of a supplemental notice was necessary. It entered judgment for Westburne in the amount of $1,799.99 as Westburne's total recovery from the payment bond. This sum consisted of the original $1,500 estimated plus an amount less than twenty per cent of the original estimate. We agree with the trial court's decision for the reasons set forth below.

DISCUSSION

In order to maintain an action on the payment bond, a claimant must comply with the notice requirements of A.R.S. § 34-223(A). When that statute was originally enacted, the only notice required was "written notice to [the] contractor within ninety days from the date on which said claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made...." 1969 Ariz.Sess.Laws, Ch. 52, § 11. In 1984, A.R.S. § 34-223(A) was amended to incorporate by reference various subsections of A.R.S. § 33-992.01 (the mechanics' liens law). The legislature also added the requirement that a claimant provide a written preliminary estimate within twenty days of furnishing supplies. 1984 Ariz.Sess.Laws, Ch. 242, § 1. The amended portion of § 34-223(A) reads as follows:

[A]ny such claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action upon such payment bond upon giving the contractor only a written preliminary twenty day notice, as provided for in § 33-992.01, subsection C, paragraphs 1, 2, 3 and 4 and subsections D, E and I, and upon giving written notice to such contractor within ninety days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied [sic] for whom the labor was done or performed.

A twenty day preliminary estimate and a ninety day final notice are both required under this version of the statute. The act cannot be read so as to allow either of these notices to substitute for any other.

In 1983, the legislature amended A.R.S. § 33-992.01 to impose a standard of accuracy on the preliminary notice. Amended subsection (I) provided in relevant part that a preliminary twenty day notice is not defective if additional "labor, professional services, materials, machinery, fixtures or tools ... exceed by less than twenty percent the estimated total price thereof." Subsection (I) of A.R.S. § 33-992.01 was incorporated into § 34-223(A). Subsection (H) of A.R.S. § 33-992.01 requires a further notice if additional materials supplied exceed "by twenty per cent or more the total price in any prior original or subsequent preliminary notice ..." However, subsection (H) was not incorporated by reference into amended § 34-223(A). There is a requirement in amended A.R.S. § 34-223(A) which calls for "substantial accuracy" in stating the amount claimed in the ninety day notice. There is no statutory language which would allow only one general notice to be accurate. We conclude that, given the incorporation of subsection (I) into § 34-223(A), a standard of twenty per cent was implicitly incorporated into the statute as the norm for substantial accuracy.

Westburne argues that the omission of subsection (H) from incorporation into § 34-223(A) manifests an intent that the twenty percent rule not apply in the public construction setting. We reject this contention because it would render subsection (I) meaningless. A cardinal rule of statutory interpretation is to give full effect to each statutory word or phrase so that no part is rendered...

To continue reading

Request your trial
4 cases
  • Arizona State Democratic Party v. State, 1CA-CV 02-0180.
    • United States
    • Arizona Court of Appeals
    • 30 Septiembre 2004
    ...contributions made to influence elections to individual political positions.16See Westburne Supply, Inc. v. Diversified Design and Const., Inc., 170 Ariz. 598, 600, 826 P.2d 1224, 1226 (App.1992) ("What a statute necessarily implies is as much a part of the statute as what it makes ¶ 58 Add......
  • Cemex Constr. Materials S., LLC v. Falcone Bros. & Assocs., Inc.
    • United States
    • Arizona Court of Appeals
    • 30 Abril 2015
    ...notice and a final ninety day notice, and neither notice may substitute for the other. Westburne Supply, Inc. v. Diversified Design & Constr., Inc., 170 Ariz. 598, 600, 826 P.2d 1224, 1226 (App.1992).¶ 12 The purpose of these notice requirements is “ ‘to fix a time limit after which the pri......
  • Long v. Napolitano
    • United States
    • Arizona Court of Appeals
    • 27 Agosto 2002
    ...necessarily implies is as much a part of the statute as what is explicitly stated. Westburne Supply, Inc. v. Diversified Design and Constr., Inc., 170 Ariz. 598, 600-01, 826 P.2d 1224, 1226-27 (App.1992). Thus, in light of the provision allowing counties to enter the class upon achieving th......
  • Phoenix City Prosecutor's Office v. Ybarra
    • United States
    • Arizona Court of Appeals
    • 21 Junio 2007
    ...the legislature implicitly did so by providing the right to the defendant only. Westburne Supply, Inc. v. Diversified Design & Constr., Inc., 170 Ariz. 598, 600-01, 826 P.2d 1224, 1226-27 (App.1992) (citing Hoyle v. Superior Court, 161 Ariz. 224, 227, 778 P.2d 259, 262 (App. 1989)) ("What a......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT