Wickwire v. City of Elkhart

Decision Date13 March 1896
Docket Number17,128
Citation43 N.E. 216,144 Ind. 305
PartiesWickwire et al. v. City of Elkhart et al
CourtIndiana Supreme Court

From the Elkhart Circuit Court.

The judgment is reversed, with instructions to overrule the demurrer.

UNKNOWN Note.--As to the right of the lowest bidder on public contract, see note to Anderson v. President and Directors of Public Schools (Mo.), 26 L.R.A. 707.

D. N Weaver, Osborne & Zook, A. Anderson and L. Hubbard, for appellants.

Chamberlain & Turner, for appellees.

OPINION

Hackney, C. J.

The appellants, who were property owners along the line of Jackson street, in the city of Elkhart, sued the appellees the city of Elkhart, the members of the common council and the mayor of said city and A. F. Nims, to enjoin the improvement of said street, by said Nims, under a contract awarded by the common council to him for the grading and paving of said street. The circuit court sustained the demurrer of the appellees to the complaint of the appellants and that ruling is the only assigned error. The improvement undertaken was by virtue of the Barrett law, R. S. 1894, section 4288 et seq., and the proceedings progressed without question to the action of the common council upon the bids for the work. One requirement of the ordinance was that bidders should deposit a certified check for $ 100 as security for the compliance with their bids in contracting for the work; a form of bid was prepared by the city and supplied to bidders, and the specifications contained the requirement that "All bids shall be made per square yard, setting out in full kinds of brick and other materials to be used, also the price per running foot of curbing; and no bid shall be entertained having within it any provisions whatsoever. But the price per square yard shall include all the necessary work and materials in making the pavement complete. All work specified to be completed by August 1, 1893." The appellee, Nims, one Mayer and others, were competing bidders. The two bidders named were lower in their bids than any other bidders, and the bid of Mayer was $ 887 less than that of Nims, while the bid of Nims varied from the form provided by the city in containing, in connection with the item of excavating, a charge of one cent per cubic yard for each one hundred feet of hauling beyond one thousand feet; that the work should be completed by December, 1, 1893, instead of August 1, 1893; that he should have the use of the city's street roller without charge, and that the engineer should "make an estimate the first part of each month for all work done the preceding month, and 90 per cent. of same to be paid at once, and the total amount on completion of the contract." The council accepted the bid of Nims, "striking out conditions mentioned in his bid," declared it to be the best bid, and directed the preparation of a contract with Nims. A contract was prepared, reported to and approved by the council, and the mayor was ordered to execute the same on the part of the city. Nims executed the contract and gave bond to the approval of the council, but the mayor declined to execute the contract. The contract so prepared contained the following provisions not contemplated by the form of bid so provided and not mentioned in any other proceeding of the council: 1. Limiting the hauling of surplus dirt to one-half mile; 2. That the work should be completed on or about December 1, 1893, and if employes should strike the time for completion should be extended; 3. That estimates should be made each thirty days after the work should begin, and 90 per cent. of such estimates should be paid by the city to Nims, within ten days after making each estimate, "as an advancement upon said work," for which Nims should pay the city at the rate of 6 per centum from the dates of payments to a period not to exceed sixty days after the completion of the work, and the city to advance the balance unpaid upon said work within said sixty days.

The statute, R. S. 1894, section 4288, provides for the giving of the contract to "the best bidder, after advertising for three weeks * * * to receive proposals therefor;" it provides, further, section 4290, that the corporation "shall be liable to the contractor for the contract price of said improvement" and the lot owners shall be liable to the city, upon a basis prescribed, and the property shall be liable to a lien for the amount. The liability of the city to the contractor, it is further provided by section 4292, may be discharged, in part, by estimates as the work progresses and payments from the treasury upon such estimates, deducting a reasonable percentage thereof to secure the completion of the contract.

In Elliott on Roads and Streets, p. 371, the correct doctrine with relation to the special assessment of property for such improvements, is stated with clearness and precision. It is said: "The right to levy local assessments is regarded as an extraordinary one, and it cannot be deduced from the general words of an act incorporating a municipal corporation, unless the words employed assume to grant, and do clearly grant, that right. The words of a statute assuming to grant the authority to levy local assessments will not be extended by construction for or against the corporation; the construction is strict, and nothing in its favor will be intended...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT