William Green Construction Co., Inc. v. United States

Decision Date11 May 1973
Docket NumberNo. 124-72.,124-72.
PartiesWILLIAM GREEN CONSTRUCTION COMPANY, INC. and United States Fidelity & Guaranty Company v. The UNITED STATES.
CourtU.S. Claims Court

COPYRIGHT MATERIAL OMITTED

James V. Dolan, Washington, D. C., for plaintiffs; Stanley C. Morris, Jr., Washington, D. C., attorney of record. Richard A. Behrens, Michael Malley and Steptoe & Johnson, Washington, D. C., of counsel.

Judith Ann Yannello, Washington, D. C., with whom was Asst. Atty. Gen. Harlington Wood, Jr., for defendant.

Before COWEN, Chief Judge, and DAVIS, SKELTON, NICHOLS, KASHIWA, KUNZIG, and BENNETT, Judges.

ON DEFENDANT'S MOTION TO DISMISS THE PETITION

DAVIS, Judge:

Three separate government construction contracts are interlaced in this case. In November 1964 plaintiff William Green Construction Company (Green) agreed with the General Services Administration to build a women's residence hall at Howard University in the District of Columbia (the Howard University contract). About the same time Green also contracted with GSA to construct a Post Office and Federal Office Building in Portsmouth, New Hampshire (the FOB contract). A year and one-half later, the same agency arranged with plaintiff Green to erect the National Training School for Boys in Morgantown, West Virginia (Training School contract). Plaintiff United States Fidelity & Guaranty Company (USF & G) was the surety on the Howard University and FOB contracts; another company was surety on the Training School agreement. Green was also working, during this period, on three nonfederal projects on which USF & G was surety.

In 1965-1966, during performance of the Howard University work, the contractor and the defendant had a serious dispute whether certain of the government specifications were defective and impossible to carry out. When Green refused on that ground to go forward, the contracting officer terminated for default. Green challenged this determination, insisting that its inability to proceed was justified by the defects in the defendant's requirements.

In the discussions which followed, defendant indicated that it intended to set off, against amounts which would be owing on the other two of Green's federal contracts, the liquidated damages and excess completion costs assessable with respect to the just-terminated Howard University agreement. Green responded that such set-offs were improper — because the default-termination was unwarranted — and would make it financially impossible to proceed with completion of the other two contracts, and, more than that, the contractor's entire business would be destroyed. For this reason, Green and USF & G asked the GSA to isolate the Howard University dispute and not to impose set-offs, but the Government refused to make such a commitment.

Shortly after the Government had made it clear that it fully maintained its right of set-off, but before any set-off had actually occurred, Green informed GSA that, because of the threat to reduce payments on the other projects, it was financially unable to, and would not, proceed with the FOB and Training School contracts. These two agreements were then terminated by the Government for default. USF & G completed the FOB work, and apparently the other surety did the same for the Training School contract. Green likewise failed to complete the three nonfederal contracts it had, and went out of business.

Green appealed to the General Services Board of Contract Appeals from the default-termination of the Howard University contract, but it never sought review by the Board of the defaults with respect to FOB and Training School. The Howard appeal asked, not only for the conventional modern adjustment for an improper default-termination,1 but also for damages for losses on FOB and Training School, as well as on the non-federal projects, and for loss of Green's business as a whole. Because of the inclusion of these items of recovery, the Government moved the board to dismiss the appeal as for "breach of contract" and "unliquidated damages", beyond the board's authority. In 1968 the board partially granted this motion, dismissing all claims except that for an equitable adjustment under convenience-termination standards.

Later, in 1971, the parties stipulated before the board that Green "was not in default at the time it received notice of the termination of the Howard University contract and the Government concedes the termination for default was erroneously made by the contracting officer. The appeal, therefore, should be granted as defined by the prior decisions of the Board in this case." The GSBCA then found that the contractor's "right to proceed under the contract was improperly terminated for default", and remanded to the contracting officer to determine the equitable adjustment for the unreimbursed costs of performing the Howard work. The stipulation expressly provided that "any equitable adjustment under the contract shall not be prejudicial to the contractor's right to proceed in the Court of Claims for additional damages not the subject of such equitable adjustment." GSBCA No. 2114, 71-2 BCA ¶ 9116.

In 1972 Green and USF & G brought this action, alleging what we have thus far set forth, asking for the large damages (over $2,700,000) the board had dismissed from the Howard appeal, and claiming that those damages are recoverable on the theory that the United States breached all three of Green's federal contracts. Count I of the petition asserts the full claim as a breach of the Howard contract, while Count II bottoms the very same claim on alleged breach of the FOB and Training School agreements. Defendant has moved to dismiss the petition for failing to state any proper claim.

We think that the claimants do not have a "breach" claim against defendant on any of the three contracts, but that plaintiff Green does have a right to a convenience-termination type of equitable adjustment, under all three of them, and that such adjustments should be awarded administratively. We discuss the three agreements seriatim.

Howard University contract (Count I): The defendant's notice of default-termination of the Howard contract triggered the default-termination clause which provided that, if it was determined for any reason "that the Contractor was not in default under the provisions of this clause", or that "the delay was excusable", the matter was to be treated as a convenience-termination if the contract contained a convenience-termination article, and, if not, the contract was to "be equitably adjusted to compensate for such termination." We have held that the latter alternative calls for the general equivalent of a convenience-termination award. General Builders Supply Co. v. United States, 409 F.2d 246, 187 Ct.Cl. 477 (1969).

It follows that when the GSBCA determined that Green's right to proceed was wrongfully ended, and remanded for an appropriate adjustment, the contractor received the maximum to which it was entitled under the contract. There is no present complaint as to the amount of the equitable adjustment, and plaintiffs do not contend that such an award can or should cover the types of consequential damage they seek here. The petition suggests, however, that a breach claim for a wrongful default-termination somehow survived for these additional items of recovery.

But it is very plain under our decisions that the administrative remedy is the only one available to the contractor. Green does not retain a "breach" claim, for an improper default, which can be brought in court and through which a supplemental award can be obtained. See General Builders Supply Co., supra, 409 F.2d at 248 n. 3, 187 Ct.Cl. at 480 n. 3; G. C. Casebolt Co. v. United States, 421 F.2d 710, 712, 190 Ct.Cl. 783, 486-487 (1970). The exclusive remedy "under the contract" substitutes for the "breach" claim which would otherwise exist, and becomes the claimant's sole form of relief. The measure of recovery for a convenience-termination — costs incurred, plus a reasonable profit on work performed — is an adequate replacement for the common-law cause of action. See infra.

It is worth noting, in addition, that in any event the type of consequential damage for which plaintiffs now press could not be obtained under Count I even if there were no such default-termination clause in the contract and this suit were properly one for common-law breach for wrongful cancellation of the Howard University pact. On the face of the petition it was not the wrongful termination itself which caused either Green's inability to proceed on the other two federal contracts, or the stoppage of work on the three nonfederal projects, or plaintiff's eventual going-out-of-business, but the subsequent and separate threat of set-offs against payments owing on the FOB and Training School projects. Whatever else those threats may have been, they were in no way violations of the Howard contract, nor were they directly or integrally linked to the Howard default termination. They were, instead, independent acts of the Government directed to the other two federal projects.

Accordingly, defendant is quite right that Count I fails to state any claim at all and must be dismissed in toto. The equitable adjustment which Green is receiving, through the administrative proceedings, is all that it merits with respect to the Howard contract.

FOB contract (Count II): A. Even if the default-termination of the FOB agreement was invalid, Green should have appealed to the GSBCA, just as it sought review of the Howard termination. That was the channel expressly marked out by the contract and it should have been followed. If the FOB termination was improper, an equitable adjustment would be made under that contract which embodied the same default-termination form as the Howard agreement.

Plaintiffs try to avoid this conclusion by a number of arguments which we must reject. The first is that the claim in Count II is not for wrongful...

To continue reading

Request your trial
22 cases
  • Gulf Grp. Gen. Enters. Co. v. United States
    • United States
    • U.S. Claims Court
    • 2 Julio 2013
    ...(1993); Dairy Sales Corp. v. United States, 219 Ct. Cl. 431, 436-37, 593 F.2d1002, 1005 (1979); William Green Constr. v. United States, 201 Ct. Cl. 616, 626-27, 477 F.2d 930, 936-37 (1973), cert. denied, 417 U.S. 909 (1974). In addition to its breach claims, however, plaintiff also alleges ......
  • Morrison Knudsen Corp. v. Fireman's Fund Ins. Co.
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 11 Mayo 1999
    ...under federal-contracting law may not. See, e.g., Rhen v. United States, 17 Cl.Ct. 140, 143 (1989); William Green Constr. Co. v. United States, 201 Ct.Cl. 616, 477 F.2d 930, 936 (1973). See generally Cibinic & Nash, supra, at 692-93.27 The exception is GIT's claim of roughly $7,000 for "wea......
  • LEWIS JORGE CONST. v. POMONA UNIFIED SCHOOL
    • United States
    • California Supreme Court
    • 23 Diciembre 2004
    ...entire] net worth, and losses on the non-federal work — such damages are all deemed too remote." (William Green Construction Co., Inc. v. United States (1973) 201 Ct.Cl. 616, 477 F.2d 930, 936; accord, Olin Jones Sand Company v. United States (1980) 225 Ct.Cl. 741 [failure of government to ......
  • Hercules Inc. v. U.S., s. 92-5124
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 4 Mayo 1994
    ...dubious. It is the kind of consequential damages not normally awarded in contract breach cases. William Green Construction Co. v. United States, 201 Ct.Cl. 616, 477 F.2d 930 (1973), cert. denied, 417 U.S. 909, 94 S.Ct. 2606, 41 L.Ed.2d 213 (1974). Courts do not, in awarding breach damages, ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT