Wilson v. Borden
Decision Date | 02 March 1903 |
Citation | 68 N.J.L. 627,54 A. 815 |
Parties | WILSON v. BORDEN. |
Court | New Jersey Supreme Court |
(Syllabus by the Court.)
Error to Circuit Court, Monmouth County.
Action by Wayman Wilson against Matthew C. D. Borden. Judgment for plaintiff, and defendant brings error. Reversed.
John S. Applegate & Son, for plaintiff in error.
James S. Legnan, for defendant in error.
VAN SYCKEL, J. This is a suit on a building contract, by contractor against owner, to recover for work done under the contract, dated April 23, 1901. The plaintiff alleged that the owner unlawfully rescinded the contract, and he was permitted by the trial court to recover the cost of the work he had done, and materials furnished.
The first question in the case is whether the owner was justified in putting an end to the contract.
Section 13 of the contract provides "that if the architect shall certify that the refusal, neglect or failure of the contractor to comply with the contract is sufficient ground for such action, the owner may terminate the employment of the contractor." On the 27th of August, 1901, the architects sent to Borden a letter, of which the following is a copy:
After receiving this letter the defendant, on the 7th of September, 1901, caused the notice referred to in the letter of the architects to be served on the plaintiff; having first changed its date to September 7, 1901. The said notice was as follows:
An implication may be drawn from the letter of the architects that in their judgment the owner had a right to rescind, but the contractor should not be deprived of his contract by implication when there is an express provision in the contract that...
To continue reading
Request your trial-
Hollingsworth v. Leachville Special School District
...certificate given by him was insufficient in law to comply with the contract, article 5. 157 N.Y.S. 782; 70 N.J.L. 4, 56 A. 304; 68 N.J.L. 627, 54 A. 815; 104 F. 930; 144 N.Y. 691, 39 394; 193 Mo.App. 132, 182 S.W. 143; 95 S.E. 113; 105 A. 467. 4. The three days' notice prescribed by articl......
-
Savannah Lighting Co. v. Fidelity & Deposit Co. of Md.
... ... to justify the owner in taking possession of the premises and ... completing the work." ... See, ... also, Wilson v. Borden, 68 N. J. Law, 627, 54 A. 815 ... (4); White v. Mitchell, 30 Ind.App. 342, 65 N.E ... 1061 (1, 4) ... In the ... ...
-
Rowland v. Hudson County
...not done, such profit, if any, as he would have made by doing it for the unpaid balance of the contract price; and Wilson v. Borden, 68 N.J.L. 627, 54 A. 815 (E. & A. 1902), is an application of the doctrine so stated. Neither case reaches the present Kent v. Darman, 137 A. 467, 468 (Sup.Ct......
-
Beaver Valley Painting, Inc. v. Terminal Const. Corp.
...for concluding that Beaver Valley was entitled to recover any damages in excess of actual outlay and expense. In Wilson v. Borden, E. & A. 1903, 68 N.J.L. 627, 54 A. 815, a building contractor sued the owner for work done under a contract, claiming that the owner unlawfully rescinded the co......