Wilson v. Salt Lake City
Decision Date | 13 July 1918 |
Docket Number | 3135 |
Court | Utah Supreme Court |
Parties | WILSON v. SALT LAKE CITY |
On Appeal for Rehearing August 22, 1918.
Appeal from the District Court of Salt Lake County, Third District Hon. George G. Armstrong, Judge.
Action by R. E. Wilson against Salt Lake City, a municipal corporation.
Judgment for plaintiff. Defendant appeals.
AFFIRMED.
W. H Folland, City Atty., and H. H. Smith and W. W. Little Asst City Attys., for appellant.
Wm. McCrea and P. L. Williams for respondent.
The plaintiff commenced an action to recover from the defendant certain amounts alleged to be due and owing him for extra labor and materials furnished in the construction and completion of a reservoir for the defendant. The reservoir was designed for the purpose of supplying the inhabitants of Salt Lake City with water.
A written contract had been entered into between the parties on October 5, 1914, and the construction work was commenced by plaintiff on or about October 15, 1914, and thereafter continuously prosecuted until on or about December 20 of the same year, when owing to weather conditions, work was suspended until the early spring months of 1915, when it was again resumed and continued until the completion of the reservoir, September 28, 1915.
Under the contract entered into between the parties the plaintiff was to do all the work and furnish all the materials (computed on approximate quantities) necessary to construct the reservoir in a proper and workmanlike manner according to the plans and specifications furnished by the defendant city. Payments were made by the defendant (hereinafter for convenience referred to as the city), based on partial estimates as the work progressed, until the total sum of $ 40,451.53 had been paid to the plaintiff by the city on the contract, which sum was all the city was willing to concede that the plaintiff was entitled to for the work and labor furnished for the completed reservoir. The plaintiff claimed he had not been fully paid and after presenting his claim in due form for $ 16,517.47 over and above the amount paid by the city, and the city having rejected his claim, brought suit therefor in the district court for Salt Lake County, upon which he obtained, after a trial to the court without a jury, judgment against the city for $ 12,775.57, with interest and costs. From this judgment the city appeals.
The complaint sets forth three separate causes of action. The first cause of action involves the labor and material furnished by the plaintiff under the contract for the construction of the reservoir. While the evidence adduced by the respective parties is conflicting as to the amount of labor and material furnished, the trial court found for the plaintiff, and on this cause of action rendered a judgment against the city upon the several items alleged to be due the plaintiff, totaling the sum of $ 4,448.24. We find there is substantial evidence in support of all the findings with respect to the plaintiff's first cause of action, and therefore this court has not the power to and will not disturb the same. Goan v. Ogden, L. & C. R. Co., 51 Utah 285, 169 P. 949.
The second cause of action involves items in the furnishing of labor and material by plaintiff for the completion of the reservoir, alleged not to be within the terms of, nor contemplated by the parties under, the contract. The plaintiff alleged that the city engineer improperly and unnecessarily required him, when the work was suspended in 1914, to put earth on the slopes of the excavation and embankment of the reservoir to protect them during the winter season and until the work of construction might be resumed, in 1915, for which plaintiff claimed $ 8,135.52 after giving a credit of $ 650.16 paid by the city; a claim for removing dirt, in the sum of $ 40, that was disallowed by the trial court; a claim for $ 48 extra labor occasioned by an error on the part of the city in setting grade stakes, and for $ 25 the price of a hand rail. The last two items are confessed by the city on this appeal. The trial court again found the issues in favor of the plaintiff, and rendered judgment against the city on the several items allowed, the sum total being $ 8,208.53. As before, we find substantial evidence in the record to sustain the findings of the trial court both as to the amount of labor furnished and that the price charged therefor was reasonable.
The plaintiff testified that the charge made therefor against the city was but the actual cost to him of the labor performed plus 15 per cent. for engineering and reasonable profit. While there is some conflict in the testimony as to the amount of extra labor performed in the cleaning of the slopes of the reservoir we think the great weight of the evidence supports the plaintiff's contention and the finding made by the trial court, both as to the amount of extra labor and reasonableness of the charge made therefor.
However, it is contended by the city that, conceding the work now under consideration to be extra, the cleaning of the slopes of the reservoir comes within the contract entered into between the parties as to the price, and should be paid for at the contract price of thirty-five cents per cubic yard under certain provisions of the contract which read:
There are other provisions, not necessary to here set forth, contained in the instructions to bidders, the proposal and the specifications, all of which are embodied within and made a part of the contract, to the same effect, namely, that the work contemplated under the contract is to be confined to and done "in accordance with the plans, profiles, and specifications for the work." (Italics ours.)
The plaintiff contends, and throughout the trial in the district court prosecuted his case on the theory, that the labor of extra excavation and removal of earth from the slopes of the reservoir was improper, unnecessary, and not at all contemplated under the contract. This contention, directly opposed to that of the city, finds much support in the testimony, and the trial court found:
One of the plaintiff's witnesses, a Mr. Bigler, who was employed on the work by plaintiff, and who for twenty years had followed the occupation of general construction in railroad building, canal and street work, and who was experienced in the building of embankments for...
To continue reading
Request your trial-
Baker v. Wycoff (Industrial Commission, Intervener)
... ... Appeal ... from District Court, Third District, Salt Lake County; P. C ... Evans, Judge ... Action ... by Dennis ... AFFIRMED ... Gardner ... & Latimer, of Salt Lake City, for appellant ... Shirley ... P. Jones, of Salt Lake City, ... evidence to support it. Wilson v. Salt Lake ... City , 52 Utah 506, 174 P. 847; Carlquist v ... ...
-
Campbell Building Co. v. State Road Commission
... ... Appeal ... from District Court, Third District, Salt Lake County; Allen ... G. Thurman, Judge ... Action ... by ... Allen ... T. Sanford and E. A. Rogers, both of Salt Lake City, for ... appellant ... Joseph ... Chez, Atty. Gen., and Wm ... there is substantial evidence to sustain it. Wilson ... v. Salt Lake City , 52 Utah 506, 174 P. 847 ... We ... ...
-
Board of Educ. of Granite School Dist. v. Salt Lake County, 17175
...have not been exempted from this rule. Baker Lumber Co. v. A.A. Clark Co., 53 Utah 336, 178 P. 764 (1919); Wilson v. Salt Lake City, 52 Utah 506, 174 P. 847 (1918). In view of the Treasurer's delay in transferring Granite's revenues, the allowing of interest on school funds by other jurisdi......
-
Wunderlich Contracting Company v. United States
...was required and the defendants received the benefit of it, plaintiffs were entitled to recover the reasonable value. Wilson v. Salt Lake City, 52 Utah 506, 174 P. 847, and Drainage Dist. No. 1 v. Rude, 8 Cir., 21 F.2d 257, are to the same A contractor who bids for work has the right to rel......