Wortman v. Kleinschmidt
Decision Date | 27 June 1892 |
Citation | 30 P. 280,12 Mont. 316 |
Parties | WORTMAN v. KLEINSCHMIDT et al. |
Court | Montana Supreme Court |
Appeal from district court, Lewis and Clarke county; WILLIAM H HUNT, Judge.
Action by Daniel P. Wortman against Reinhold H. Kleinschmidt and another. From a judgment for plaintiff, defendants appeal. Modified.
Cullen Sanders & Shelton, for appellants.
H. G. & S. H. McIntire, for respondent.
The complaint, among other things, alleges that: "And plaintiff avers that, in addition to the sum specified and mentioned in said contract, the said plaintiff, for and at the special instance and request of said defendant Reinhold H. Kleinschmidt, performed extra work and furnished extra materials, over and above those specified in said contract the price of which was and is the sum of *** $763.40, making the total price of the work done and materials furnished by said plaintiff on said buildings the sum of *** $57,473.40." The account which was filed by the respondent for the purpose of securing a mechanic's lien upon the property contains this statement: "That in addition thereto certain extra work and materials furnished over and above those specified in said contract, were furnished and done by said Daniel P. Wortman on said buildings and structures, at the request of said Reinhold H. Kleinschmidt, the value of which was and is the sum *** $763.40." The account consists of these items, which are not set forth in the pleadings:
To contract for building granite block ..................... | $56,710 | 00 |
To extra work and sund. on same, as follows: | ||
Sept. 12th. | ||
To freight and transfer on glass ................................ | 19 | 69 |
To extra work on floor .......................................... | 72 | 00 |
To rubblestone and carpenter work ................................ | 7 | 00 |
To extra work per special contract on first"story ceiling ...... | 235 | 00 |
To setting and moving vault doors: | ||
640 brick ..................................................... | $ 5 | 44 |
Labora ......................................................... | 12 | 00 |
Brick mason .................................................... | 21 | 00 |
---------- | ||
To freight and transfer on 4 boxes of glass ..................... | 13 | 70 |
To 55 feet cherry dado, at $3.75 ............................... | 206 | 25 |
To one door and frame, with trimmings in basement ............... | 16 | 00 |
To plastering in basement ........................................ | 6 | 12 |
To 16 feet of base ............................................... | 2 | 60 |
To steps to annex second story .................................. | 12 | 00 |
To door in elevator shaft ........................................ | 8 | 00 |
To 29 hours' work ordered by Scott, at 40c ...................... | 11 | 60 |
To electric work on elevator ................................... | 120 | 00 |
---------- | ||
Ford .................................................... | $57,473 | 40 |
The answer denies that,
The replication is as follows: Plaintiff "avers that the additional work, labor, and materials, over and above that specified in the contract, which is set out in the complaint herein, were done and furnished by plaintiff on the buildings, in said complaint mentioned, at the instance and request of defendant Kleinschmidt, as set forth in paragraph 2 of the complaint herein, and were done and furnished, and the contract therefor made, long subsequent to the execution and delivery of said first-mentioned contract, and were all ordered and accepted, used and enjoyed, by said defendant Kleinschmidt, and were for his use and benefit; and were done and furnished on his promise to pay for the same; and were all done and furnished with the full knowledge of his architects and agents; and that no demand or intimation was made to plaintiff that he should have any written order therefor, nor was he in any wise notified to claim compensation therefor, in writing, nor in any other manner; wherefore plaintiff avers that said defendant should be now barred and estopped from asserting the necessity of any written order or paper for such extra work and materials." The contract is made a part of the complaint, and provides expressly for the payment of work of this character: "The contractor shall make no claim for additional work unless the same shall be done in pursuance of a written order from the architects, and notice of all claims shall be made to the architects in writing within three (3) days of the beginning of such work."
The case was tried upon these issues. The appellants objected to the introduction of any testimony in support of the claim for additional work or materials, upon the ground that the contractor had not complied with the plain terms of the agreement. The objection was overruled, and the jury were instructed in this language: "Upon the question of extra work you are instructed that if you believe from the evidence that Wortman did or performed any work, or furnished any materials, upon the said buildings of Kleinschmidt, extra and in addition to the work or material specified in his contract, and that said work was done and material was furnished at the request, or with the knowledge and consent, express or implied, of said Kleinschmidt or his agents, then the jury are instructed that the plaintiff is entitled to recover the reasonable value of such extra work and material from the defendant, and you should so find by your verdict."
Wortman, the respondent, testified: This communication was then read:
The respondent testified further: Respondent also testified that Kleinschmidt had at one time a superintendent, one Milligan, who bought some rubblestone. "In laying the center floor this Milligan and Kleinschmidt agreed that he should strip the floor, it being very crooked, and I was to lay the floor on the strips; but Milligan requested me, as Kleinschmidt's superintendent, to lay those strips, and allowed me three or four or six dollars, I forget the exact amount, for that work; I think the whole thing is some eighty odd dollars." The plans were changed so that two money vaults in the annex building were constructed, "as desired by Kleinschmidt and his architects," upon the opposite side of the room from what was originally designed. The position of the closets in the basement of the annex building was changed from the north west corner to the south west corner, in accordance with the request of "Kleinschmidt and his superintendent." Respondent further testified: ...
To continue reading
Request your trial